1、Lessons Learned Entry: 1295Lesson Info:a71 Lesson Number: 1295a71 Lesson Date: 2002-08-09a71 Submitting Organization: GSFCa71 Submitted by: Richard FitzgeraldSubject: Key Personnel Retention After Launch Description of Driving Event: Initial budgets for retaining key satellite and instrument personn
2、el after launch were inadequateLesson(s) Learned: There will be on-orbit problems, which require time and attention from key development personnel.Recommendation(s): Plans for operations resources must include provisions for maintaining key satellite and instrument personnel support to address on-or
3、bit anomalies for up to one year after launch Evidence of Recurrence Control Effectiveness: N/ADocuments Related to Lesson: N/AMission Directorate(s): a71 Sciencea71 Space Operationsa71 Exploration SystemsProvided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,
4、-,-Additional Key Phrase(s): a71 Flight OperationsAdditional Info: Approval Info: a71 Approval Date: 2002-10-10a71 Approval Name: Al Galloa71 Approval Organization: GSFCa71 Approval Phone Number: 301-286-3756Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-