1、Public Lessons Learned Entry: 4878 Lesson Info: Lesson Number: 4878 Submitting Organization: KSC Submitted by: Jenni Palmer Subject: Disconnect Between CxP Supportability Plan and GOP Integrated Logistics Support Plan Abstract: The Constellation Program (CxP) Supportability Plan for Level II was dev
2、eloped in parallel with the Ground Operations Project (GOP) Integrated Logistics Support Plan (ILSP) for Level III. A lack of collaboration led to disconnects between the direction provided in the Level II Supportability plan and the implementation provided in the Project Level ILSP. Higher-level do
3、cuments should be developed first and should drive the creation of lower-level documents. Description of Driving Event: The Level II Constellation Program Supportability Plan was compared with the Ground Operations Project ILSP to map the flowdown of requirements from the higher-level document to th
4、e lower-level document. Gaps and disconnects were uncovered between the direction given in the Supportability Plan and the Project ILSP. Lesson(s) Learned: Sequential development is necessary to ensure continuity between parent and child documents. Recommendation(s): Ensure the program-level Support
5、ability Plan is used as a parent document when creating project-level ILSP, and routinely perform a gap analysis to assess inconsistencies between the parent and child documents. Evidence of Recurrence Control Effectiveness: N/A Documents Related to Lesson: N/A Mission Directorate(s): Exploration Sy
6、stems Additional Key Phrase(s): Additional Categories. Additional Categories.Logistics Additional Info: Project: Constellation Approval Info: Approval Date: 2012-10-01 Approval Name: mbell Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Approval Organization: HQ Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-