1、Designation: C1244M 11 (Reapproved 2017)Standard Test Method forConcrete Sewer Manholes by the Negative Air Pressure(Vacuum) Test Prior to Backfill (Metric)1This standard is issued under the fixed designation C1244M; the number immediately following the designation indicates the year oforiginal adop
2、tion or, in the case of revision, the year of last revision. A number in parentheses indicates the year of last reapproval. Asuperscript epsilon () indicates an editorial change since the last revision or reapproval.1. Scope1.1 This test method covers procedures for testing precastconcrete manhole s
3、ections when using the vacuum test methodto demonstrate the integrity of the installed materials and theconstruction procedures. This test method is used for testingconcrete manhole sections utilizing mortar, mastic, or gasketedjoints.1.2 This test method is intended to be used as a preliminarytest
4、to enable the installer to demonstrate the condition of theconcrete manholes prior to backfill. Users are hereby cautionedthat misuse or misapplication of the test criteria containedherein can cause permanent damage to the system being tested.NOTE 1Vacuum test criteria presented in this test method
5、are similarto those in general use. The test and criteria have been widely andsuccessfully used in testing manholes.NOTE 2It should be understood that no correlation has been foundbetween vacuum (air) and hydrostatic tests.1.3 This test method is the companion to inch-pound TestMethod C1244.1.4 This
6、 standard does not purport to address all of thesafety problems, if any, associated with its use. It is theresponsibility of the user of this standard to establish appro-priate safety and health practices and determine the applica-bility of regulatory limitations prior to use.1.5 This international
7、standard was developed in accor-dance with internationally recognized principles on standard-ization established in the Decision on Principles for theDevelopment of International Standards, Guides and Recom-mendations issued by the World Trade Organization TechnicalBarriers to Trade (TBT) Committee.
8、2. Referenced Documents2.1 ASTM Standards:2C822 Terminology Relating to Concrete Pipe and RelatedProductsC924 Practice for Testing Concrete Pipe Sewer Lines byLow-Pressure Air Test Method (Withdrawn 2013)3C969 Practice for Infiltration and Exfiltration AcceptanceTesting of Installed Precast Concrete
9、 Pipe Sewer LinesC1244 Test Method for Concrete Sewer Manholes by theNegative Air Pressure (Vacuum) Test Prior to Backfill3. Terminology3.1 For definitions of terms relating to manholes, seeTerminology C822.4. Summary of Practice4.1 All lift holes and any pipes entering the manhole are tobe plugged.
10、Avacuum will be drawn and the vacuum drop overa specified time period is used to determine the acceptability ofthe manhole.5. Significance and Use5.1 This is not a routine test. The values recorded areapplicable only to the manhole being tested and at the time oftesting.6. Preparation of the Manhole
11、6.1 All lift holes shall be plugged.6.2 All pipes entering the manhole shall be temporarilyplugged, taking care to securely brace the pipes and plugs toprevent them from being drawn into the manhole.1This test method is under the jurisdiction of ASTM Committee C13 onConcrete Pipe and is the direct r
12、esponsibility of Subcommittee C13.06 on Manholesand Specials.Current edition approved April 1, 2017. Published April 2017. Originallyapproved in 1993. Last previous edition approved in 2011 as C1244M 11. DOI:10.1520/C1244M-11R17.2For referenced ASTM standards, visit the ASTM website, www.astm.org, o
13、rcontact ASTM Customer Service at serviceastm.org. For Annual Book of ASTMStandards volume information, refer to the standards Document Summary page onthe ASTM website.3The last approved version of this historical standard is referenced onwww.astm.org.Copyright ASTM International, 100 Barr Harbor Dr
14、ive, PO Box C700, West Conshohocken, PA 19428-2959. United StatesThis international standard was developed in accordance with internationally recognized principles on standardization established in the Decision on Principles for theDevelopment of International Standards, Guides and Recommendations i
15、ssued by the World Trade Organization Technical Barriers to Trade (TBT) Committee.17. Procedure7.1 The test head shall be placed at the top of the manholein accordance with the manufacturers recommendations.7.2 A vacuum of 33.8 kPa of Hg shall be drawn on themanhole, the valve on the vacuum line of
16、the test head closed,and the vacuum pump shut off. The time shall be measured forthe vacuum to drop to 30.4 kPa of Hg.7.3 The manhole shall pass if the time for the vacuumreading to drop from 33.8 kPa of Hg to 30.4 kPa of Hg meetsor exceeds the values indicated in Table 1.7.4 If the manhole fails th
17、e initial test, necessary repairsshall be made by an approved method. The manhole shall thenbe retested until a satisfactory test is obtained.7.5 Use or failure of this vacuum test shall not precludeacceptance by appropriate water infiltration or exfiltrationtesting, (see Practice C969), or other me
18、ans.8. Precision and Bias8.1 No justifiable statement can be made either on theprecision or bias of this procedure, since the test result merelystates whether there is conformance to the criteria for thesuccess specified.9. Keywords9.1 acceptance criteria; concrete; manhole sections; testmethod; vac
19、uum testAPPENDIX(Nonmandatory Information)X1. Air Testing for a Single Diameter PipeX1.1 The standard accepted method of air testing, for asingle diameter pipe, Practice C924, allows a drop of 3.4 kPapressure during the time calculated by the formula:Tpress5KD2LQwhere:T = time for drop in pressure o
20、f 3.4 kPaK = 5.3108for SI unitsD = inside pipe diameter, mmL = length of line, mQ = air loss, m3/minX1.2 A pressure drop of 3.4 kPa of Hg for the vacuum testcompares to a pressure drop of 3.4 kPa of Hg for the air test.1“ Hg5 3.376850 kPaTherefore, the time relationship is:Tvac5 3.4 TpressorTvac5Tpr
21、ess.294X1.3 The allowable test times cited in Practice C924, Table2, for pipe sizes 100 to 600 mm diameter are shown in TableX1.1 and Table X1.2. The allowable test times for sizes above600 mm were obtained by extrapolation. Therefore, using theappropriate Q. we find that:TABLE 1 Minimum Test Times
22、for Various Manhole Diameters(7503000 mm) in SecondsDepth, mDiameter, mm750 825 900 1050 1200 1350 1500 1650 1800Time, in seconds1.2677910121315161.8 9 10 11 13 15 18 20 22 252.4 11 12 14 17 20 23 26 29 333.0 14 15 18 21 25 29 33 36 413.7 17 18 21 25 30 35 39 43 494.3 20 21 25 30 35 41 46 51 574.9 2
23、2 24 29 34 40 46 52 58 675.5 25 27 32 38 45 52 59 65 736.1 28 30 35 42 50 53 65 72 816.7 31 33 39 46 55 64 72 79 897.3 33 36 42 51 59 64 78 87 977.9 36 39 46 55 64 75 85 94 1058.5 39 42 49 59 69 81 91 101 1139.1 42 45 53 63 74 87 98 108 121TABLE 1 Minimum Test Times for Various Manhole Diameters(750
24、3000 mm) in Seconds (continued)Depth, mDiameter, mm1950 2100 2250 2400 2550 2700 2850 3000Time, in seconds1.21819212324252729.826234363841432.43538415485154573.04452660636771.7535767717681854.3 62 67 72 78 83 89 94 1004.9 70 76 83 89 95 101 108 1145.5 79 86 93 100 107 114 121 1286.1 88 95 103 111 11
25、9 126 135 1426.7 97 105 114 122 131 139 148 1567.3 106 114 124 133 143 152 161 1707.9 114 124 134 144 155 164 175 1858.5 123 133 145 155 167 177 188 1999.1 132 143 155 166 178 189 202 213C1244M 11 (2017)2for 750 mm Q 5 .20 m3/min!, Tvac5 2.6 31027D2QL 5 .073 Lfor 825 mm Q 5 .22 m3/min!, Tvac5 2.6 31
26、027D2QL 5 .080 Lfor 1050 mm Q 5 .25 m3/min!, Tvac5 2.6 31027D2QL 5 .115 Lfor 1200 mm Q 5 .28 m3/min!, Tvac5 2.6 31027D2QL 5 .134 Lfor 1350 mm Q 5 .31 m3/min!, Tvac5 2.6 31027D2QL 5 .153 Lfor 1500 mm Q 5 .34 m3/min!, Tvac5 2.6 31027D2QL 5 .172 Lfor 1650 mm Q 5 .37 m3/min!, Tvac5 2.6 31027D2QL 5 .191
27、Lfor 1800 mm Q 5 .40m3/min!, Tvac5 2.6 31027D2QL 5 .211 Lfor 1950 mm Q 5 .42m3/min!, Tvac5 2.6 31027D2QL 5 .233 Lfor 2100 mm Q 5 .45m3/min!, Tvac5 2.6 31027D2QL 5 .253 Lfor 2250 mm Q 5 .48m3/min!, Tvac5 2.6 31027D2QL 5 .273 Lfor 2400 mm Q 5 .51m3/min!, Tvac5 2.6 31027D2QL 5 .294 Lfor 2550 mm Q 5 .54
28、m3/min!, Tvac5 2.6 31027D2QL 5 .314 Lfor 2700 mm Q 5 .57m3/min!, Tvac5 2.6 31027D2QL 5 .335 Lfor 2850 mm Q 5 .59m3/min!, Tvac5 2.6 31027D2QL 5 .355 Lfor 3000 mm Q 5 .62m3/min!, Tvac5 2.6 31027D2QL 5 .376 LTABLE X1.1 Minimum Test Times for Various Pipe Diameters(Practice C924)Nominal Pipe Size, mm Ti
29、me (T), min/100 m100 0.9150 2.0200 3.5250 4.7300 6.0375 6.8450 7.7525 9.7600 11.0675 13.0750 15.0825 17.0900 19.0TABLE X1.2 Allowable Air Loss for Various Pipe Diameters(Practice C924)Nominal Pipe Size, mm Air Loss (Q), m3/min100 0.6150 0.6200 0.6250 0.7300 0.8375 0.11450 0.14525 0.15600 0.17750 0.2
30、0825 0.221050 0.251200 0.281350 0.311500 0.341650 0.371800 0.40C1244M 11 (2017)3ASTM International takes no position respecting the validity of any patent rights asserted in connection with any item mentionedin this standard. Users of this standard are expressly advised that determination of the val
31、idity of any such patent rights, and the riskof infringement of such rights, are entirely their own responsibility.This standard is subject to revision at any time by the responsible technical committee and must be reviewed every five years andif not revised, either reapproved or withdrawn. Your com
32、ments are invited either for revision of this standard or for additional standardsand should be addressed to ASTM International Headquarters. Your comments will receive careful consideration at a meeting of theresponsible technical committee, which you may attend. If you feel that your comments have
33、 not received a fair hearing you shouldmake your views known to the ASTM Committee on Standards, at the address shown below.This standard is copyrighted by ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959,United States. Individual reprints (single or multiple
34、copies) of this standard may be obtained by contacting ASTM at the aboveaddress or at 610-832-9585 (phone), 610-832-9555 (fax), or serviceastm.org (e-mail); or through the ASTM website(www.astm.org). Permission rights to photocopy the standard may also be secured from the Copyright Clearance Center, 222Rosewood Drive, Danvers, MA 01923, Tel: (978) 646-2600; http:/ 11 (2017)4
copyright@ 2008-2019 麦多课文库(www.mydoc123.com)网站版权所有
备案/许可证编号:苏ICP备17064731号-1