1、Designation: C497M 05C497M 13Standard Test Methods forConcrete Pipe, Manhole Sections, or Tile (Metric)1This standard is issued under the fixed designation C497M; the number immediately following the designation indicates the year oforiginal adoption or, in the case of revision, the year of last rev
2、ision. A number in parentheses indicates the year of last reapproval. Asuperscript epsilon () indicates an editorial change since the last revision or reapproval.This standard has been approved for use by agencies of the Department of Defense.1. Scope1.1 These test methods cover testing of concrete
3、pipe, manhole sections, and tile. The test methods described are used inproduction testing and acceptance testing to evaluate the properties provided for in the specifications.1.2 The test methods appear in the following order:SectionExternal Load Crushing Strength 4Flat Slab Top 5Core Strength 6Abs
4、orption 7Hydrostatic 8Permeability 9Manhole Step 10Cylinder 11Gasket Lubricant 12Joint Shear 13Alkalinity 14Gasket Measurements 151.3 The test specimens shall not have been exposed to a temperature below 4C for the 24 h immediately preceding the test.1.4 If any test specimen fails because of mechani
5、cal reasons such as failure of testing equipment or improper specimenpreparation, it shall be discarded and another specimen taken.1.5 Specimens shall be selected in accordance with the specifications for the type of pipe or tile being tested.1.6 These methods are the metric companion of Test Method
6、s C497.1.7 This standard does not purport to address all of the safety concerns, if any, associated with its use. It is the responsibilityof the user of this standard to consult and establish appropriate safety and health practices and determine the applicability ofregulatory limitations prior to us
7、e.2. Referenced Documents2.1 ASTM Standards:2C31/C31M Practice for Making and Curing Concrete Test Specimens in the FieldC39/C39M Test Method for Compressive Strength of Cylindrical Concrete SpecimensC42/C42M Test Method for Obtaining and Testing Drilled Cores and Sawed Beams of ConcreteC617 Practic
8、e for Capping Cylindrical Concrete SpecimensC670 Practice for Preparing Precision and Bias Statements for Test Methods for Construction MaterialsC822 Terminology Relating to Concrete Pipe and Related ProductsC1231/C1231M Practice for Use of Unbonded Caps in Determination of Compressive Strength of H
9、ardened Concrete CylindersD2240 Test Method for Rubber PropertyDurometer HardnessE4 Practices for Force Verification of Testing Machines1 These test methods are under the jurisdiction of ASTM Committee C13 on Concrete Pipe and are the direct responsibility of Subcommittee C13.09 on Methods of Test.C
10、urrent edition approved Oct. 1, 2005Feb. 15, 2013. Published October 2005March 2013. Originally approved in 1980. Last previous edition approved in 20042005 asC497M 04C497M 05.1. DOI: 10.1520/C0497M-05.10.1520/C0497M-13.2 For referencedASTM standards, visit theASTM website, www.astm.org, or contactA
11、STM Customer Service at serviceastm.org. For Annual Book of ASTM Standardsvolume information, refer to the standards Document Summary page on the ASTM website.This document is not an ASTM standard and is intended only to provide the user of an ASTM standard an indication of what changes have been ma
12、de to the previous version. Becauseit may not be technically possible to adequately depict all changes accurately, ASTM recommends that users consult prior editions as appropriate. In all cases only the current versionof the standard as published by ASTM is to be considered the official document.Cop
13、yright ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959. United States13. Terminology3.1 DefinitionsFor definitions of terms relating to concrete pipe, see Terminology C822.4. External Load Crushing Strength Test by the Three-Edge Bearing Test Method4.1 Summar
14、y of Test MethodThe test specimen is tested in a machine designed to apply a crushing force upon the specimenin a plane through the vertical axis extending along the length of the specimen.4.2 Significance and UseThe crushing test method shall be either a quality control test performed to establish
15、that the finished,shippable pipe has sufficient strength to withstand the crushing loads stated in the specifications or a proof of design test performedto prove the adequacy of design.4.3 Apparatus:4.3.1 The testing machine shall be of any type of sufficient capacity and shall be capable of providi
16、ng the rate of loadingprescribed in 4.5.3.4.3.2 The testing machine shall be substantial and rigid throughout, so that the distribution of the load will not be affectedappreciably by the deformation or yielding of any part.4.3.3 The three-edge-bearing method of loading shall be used. The test specim
17、en shall be supported on a lower bearing of twoparallel longitudinal strips and the load applied through an upper beam (Fig. 1, Fig. 2, Fig. 3, and Fig. 4). At the option of themanufacturer, either or both the lower bearing and the upper bearing shall extend the full length or any portion of the len
18、gth ofthe specimen.4.3.4 The lower bearings shall consist of wood or hard rubber strips. Wooden strips shall be straight, have a cross section ofnot less than 50 mm in width and not less than 25 mm nor more than 38 mm in height and shall have the top inside corners roundedto a radius of 13 mm. Hard
19、rubber strips shall have a durometer hardness of not less than 45 nor more than 60. They shall berectangular in cross section, having a width of not less than 50 mm, a thickness of not less than 25 mm nor more than 38 mm,and shall have the top inside corner rounded to a radius of 13 mm.4.3.5 The low
20、er bearing strips shall be fastened to a wooden or steel beam or directly to a concrete base, any of which shallprovide sufficient rigidity so that the deflection is not greater than 1720 of the specimen length when the maximum load is applied.The rigid base shall be at least 150 mm wide. The interi
21、or vertical sides of the strips shall be parallel and spaced a distance apartof not more than 25 mm per 300 mm of specimen diameter, but in no case less than 25 mm. The bearing faces of the lower stripsshall not vary from a straight line vertically or horizontally by more than 2.5 mm/m of length und
22、er no load.4.3.6 The upper bearing shall be a rigid wood beam with or without an attached hard rubber strip. The wood shall be sound,free of knots, and straight and true from end to end. It shall be fastened to a steel or wood-faced steel beam of such dimensionsthat deflections under maximum load wi
23、ll not be greater than 1720 of the specimen length. The bearing face of the upper bearingshall not deviate from a straight line by more than 2.5 mm/m of length. When a hard rubber strip is used on the bearing face itshall have a durometer hardness of not less than 45 nor more than 60, and shall have
24、 a width of not less than 50 mm and a thicknessof not less than 25 mm nor more than 38 mm and shall be secured to a wood beam meeting the above requirements.4.3.7 If mutually agreed upon by the manufacturer and the owner prior to the test, before the specimen is placed, a fillet ofplaster of paris n
25、ot exceeding 25 mm in thickness shall be cast on the surface of the upper and lower bearings. The width of thefillet cap, upper or lower, shall be not more than 80 mm/m of the specimen diameter, but in no case less than 25 mm.4.3.8 The equipment shall be so designed that the load will be distributed
26、 about the center of the overall length ( L1) of thespecimen (Fig. 1, Fig. 2, Fig. 3, and Fig. 4). At the option of the manufacturer, the center of the load shall be applied at any pointof the overall length (L1) of the specimen. The load shall be applied either at a single point or at multiple poin
27、ts dependent on thelength of the specimen being tested and the rigidity of the test frame.NOTE 1The user of these test methods is advised that multiple points of load applications to the upper bearing will permit use of lighter beams withoutexcessive deflection.4.4 Calibration The loading device sha
28、ll be one which shall provide an accuracy of 62 % at the specified test loads. Acalibration curve shall be used. The machines used for performing the three-edge-bearing tests shall be verified in accordance withPractices E4.4.5 Conditioning The moisture requirements of 1.3 are not required, at the o
29、ption of the manufacturer.4.6 Procedure:4.6.1 Place the specimen on the two lower bearing strips in such a manner that the pipe or tile rests firmly and with uniformbearing on each strip.4.6.2 Mark the two ends of the specimen at a pointmidway between the lower bearing strips and then establish the
30、diametrically opposite point on each end. Place the upper bearingso that it is aligned with these marks.4.6.3 For reinforced concrete pipe, any rate or load application up to a maximum of 109.4 kN/linear metre of pipe per minuteshall be used up to 75 % of the specified design strength, at which time
31、 the rate of loading shall be reduced to a maximum uniformrate of 43.8 kN/linear metre of pipe per minute. If both the design strength and the ultimate strength are being determined, aC497M 132specified rate of loading need not be maintained after the design strength has been reached. For nonreinfor
32、ced concrete pipe, anyrate of load application up to a maximum of 109.4 kN/linear metre of pipe per minute shall be used up to 75 % of the specifiedultimate strength, at which time the rate of loading shall be reduced to the maximum uniform rate of 43.8 kN/linear metre of pipeper minute.NOTE 1The fi
33、gures illustrate a method of applying the load to the pipeFIG. 1 Three-Edge-Bearing Test, Circular PipeC497M 1334.6.4 As defined in Terminology C822, the design strength is the maximum load, expressed as a D-load, supported by the pipebefore a crack having a width of 0.3 mm occurs throughout a conti
34、nuous length of 300 mm or more measured parallel to thelongitudinal axis of the pipe barrel. The crack is 0.3 mm in width when the point of the measuring gage will, without forcing,penetrate 1.5 mm at close intervals throughout the specified distance of 300 mm. Measure the width of the crack by mean
35、s of aNOTE 1The figure illustrates a method of applying the load to the pipe.FIG. 2 Three-Edge-Bearing Test, Arch PipeNOTE 1The figure illustrates a method of applying the load to the pipe.FIG. 3 Three-Edge-Bearing Test, Horizontal Elliptical PipeNOTE 1The figure illustrates a method of applying the
36、 load to the pipe. Three-Edge-Bearing Test, Vertical Elliptical PipeFIG. 4 Three-Edge-Bearing Test, Vertical Elliptical PipeC497M 134gage made from a leaf in thickness (as in a set of standard machinist gages), ground to a point of 1.5 mm in width with cornersrounded and with a taper of 0.25 mm/mm a
37、s shown in Fig. 6.NOTE 2As used in this specification, the 0.3-mm crack is a test criterion for pipe tested in three-edge bearing test and is not intended as an indicationof overstressed or failed pipe under installed conditions.4.6.5 As defined in Terminology C822, the ultimate strength is the maxi
38、mum load supported by the pipe.NOTE 3Ultimate strength of concrete pipe in the buried condition is dependent on varying soil bedding factors and varying failure modes and shallhave no relationship to the ultimate strength as defined under three-edge bearing conditions.4.7 Calculations:4.7.1 Strength
39、 test results shall be calculated in terms of pounds per linear foot. The length used in calculating the strengthvalues shall be that indicated by L in Fig. 1, Fig. 2, Fig. 3, and Fig. 4. For plain end pipe, no bell or spigot, the length L shall bethe overall length. For pipe having a bell or spigot
40、 on one end with the opposite end being plain, L shall be the distance from theplain end to the center of the joint, where L equals the overall length minus 12 the depth of the bell, or the overall length minus12 the length of the spigot.4.7.2 The ultimate strength in pounds per linear metre shall b
41、e calculated by dividing the maximum test load applied to the pipeby the laying length, L.4.7.3 The D-load strength in newtons per linear metre per millimetre of inside diameter or horizontal span shall be either the0.3-mm crack D-load strength or the ultimate D-load strength. The 0.3-mm crack D-loa
42、d shall be calculated by dividing the testload required to produce the 0.3-mm crack by the laying length, L, and by the pipe inside diameter or horizontal span. The ultimateD-load strength shall be calculated by dividing the ultimate test load applied to the pipe by the laying length, L, and by the
43、pipeinside diameter or horizontal span.4.8 Precision and BiasThe user of these test methods is advised that the true value for the strength of a concrete pipe cannotbe determined because the specimen is tested to destruction and exact duplicate specimens cannot be obtained. Therefore, nocalculations
44、 of precision and bias are presently possible. Specifications that include this test method for the various types ofconcrete pipe should include a provision for additional tests of one or more specimens.5. Flat Slab Top Test Method5.1 Summary of Test MethodA load is applied to the flat slab top and
45、the supporting capacity of the flat slab top is measured.5.2 Significance and UseThe test method is a proof of design test performed to prove the adequacy of the design.5.3 Conditioning The moisture requirements of 1.3 are not required, at the option of the manufacturer.5.4 ProcedurePlace the sectio
46、n that has been designated to receive the flat slab top on a firm, even surface. Assemble the flatslab top to this section. If a frame or riser has been designed to be fitted to the access portion of the flat slab top, assemble it tothe slab top. Apply the test load to the riser or frame as assemble
47、d to the flat slab top. If no access opening has been provided toFIG. 5 Lower Bearing Strip DetailFIG. 6 Gage Leaf for Measuring CracksC497M 135the flat slab top, apply the test load to the center of the flat slab top by means of a 300 by 300 by 100-mm wood bearing block.See Fig. 7. Calculate the te
48、st load as follows:Pu 51.3 D12.17L11I! (1)where:P u = applied minimum ultimate proof-of-design test load, N,D = total calculated field dead load on the slab, N,L = calculated live load on the flat slab top, andI = impact factor, 30 % minimum.6. Core Strength Test Method6.1 Summary of Test MethodThe
49、compressive strength of the concrete in the pipe is determined by making crushing tests ofcores cut from the pipe.6.2 Significance and UseThe core strength test is a quality control test performed to establish the fact that the finished,shippable precast concrete product has sufficient concrete strength to meet the strengths stated in the specifications.6.3 ApparatusA core drill shall be used for securing cylindrical core specimens from the wall of the pipe; a shot drill or adiamond drill shall be used.6.4 Test Specimens:6.4.1 A core specimen fo