REG NASA-LLIS-0578-1997 Lessons Learned Cassini-Huygens Probe On-Pad Cooling Incident (1997).pdf

上传人:赵齐羽 文档编号:1018225 上传时间:2019-03-21 格式:PDF 页数:4 大小:17.01KB
下载 相关 举报
REG NASA-LLIS-0578-1997 Lessons Learned Cassini-Huygens Probe On-Pad Cooling Incident (1997).pdf_第1页
第1页 / 共4页
REG NASA-LLIS-0578-1997 Lessons Learned Cassini-Huygens Probe On-Pad Cooling Incident (1997).pdf_第2页
第2页 / 共4页
REG NASA-LLIS-0578-1997 Lessons Learned Cassini-Huygens Probe On-Pad Cooling Incident (1997).pdf_第3页
第3页 / 共4页
REG NASA-LLIS-0578-1997 Lessons Learned Cassini-Huygens Probe On-Pad Cooling Incident (1997).pdf_第4页
第4页 / 共4页
亲,该文档总共4页,全部预览完了,如果喜欢就下载吧!
资源描述

1、Lessons Learned Entry: 0578Lesson Info:a71 Lesson Number: 0578a71 Lesson Date: 1997-12-11a71 Submitting Organization: JPLa71 Submitted by: D. Oberhettinger/D. LordSubject: Cassini-Huygens Probe On-Pad Cooling Incident (1997) Abstract: After Cassini was mated to the launch vehicle, excessively high v

2、elocity cooling airflow blew insulation particles into the Descent Module. The responsibility for supplying cooling to the probe on the launch pad had been informally transferred from ESA to JPL without adequate control of the on-pad interface.Require that program decisions affecting interfaces auto

3、matically trigger a review of the need to change the IRD or ICD. Ensure that the verification methodology is thorough and considers responsibilities as well as requirements. Description of Driving Event: On August 28, 1997, after the Cassini spacecraft was initially positioned on the launch pad and

4、mated to the Titan IVB/Centaur launch vehicle, a cooling incident occurred which affected the Huygens Probe. During ground operations, cool air is injected into the probe to prevent internal heat build-up and damage to probe hardware. Prior to movement to the launch pad, cooling was provided without

5、 incident by a JPL cart. At the launch pad, cooling air was provided by the facility and routed to the probe through a diverter box provided by JPL, as shown in Figure 1. After mating Cassini to the launch vehicle, cooling air was supplied to the probe at approximately 0.26 kg/s (35 lbs/min). This a

6、ir was routed to the descent module via the European Space Agency (ESA)-furnished ducting whose configuration and effects were not fully communicated. This produced a high-velocity airflow in the vicinity of internal probe insulation. It was later determined that the desired flow in that configurati

7、on was 0.04 kg/sec, and the air flow was adjusted accordingly.Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-refer to D description D Figure 1. Worst Case On-Pad Configuration To assess potential damage from the high airflow, a borescope was used to

8、 inspect the area inside the Descent Module (DM) in the vicinity of the air inlet. A tear approximately 5 cm long was seen on a Kapton blanket, along with evidence of foam insulation particles. The spacecraft was removed from the launch pad and returned to the Payload Hazardous Servicing Facility (P

9、HSF) for removal and more detailed inspection of the probe. The probe was cleaned, repaired, re-verified, reinstalled on the spacecraft, and transported back to the launch pad. These unplanned activities resulted in a delay of seven days in the scheduled launch of the Cassini-Huygens mission. A fail

10、ure review board concluded that, although ESA originally had responsibility for providing cooling air to the probe, the responsibility for supplying cooling to the probe on the launch pad was informally transferred from ESA to JPL without adequately defining and documenting nor implementing the resu

11、lting new interface requirement. Thus, no unambiguous assignment of responsibility for interface control existed. In addition, the internal probe cooling configuration at the launch pad, prior to backshell close-out, was changed without adequate review and coordination. These two factors resulted in

12、 excessive cooling air velocity within the DM, which caused the damage.Additional Keyword(s): Test & Launch Operations, Requirements DocumentationReference(s):Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-1. JPL Problem/Failure Report No. Z440982.

13、Cassini-Huygens Probe On-Pad Cooling Incident: Report of Formal Review Board,“ JPL Document D-15158, October 24, 19973. Probe Interface Requirements Document (IRD) PD-699-080Lesson(s) Learned: The Cassini-Huygens Probe review board identified a solution to each of two Interface Requirements Documen

14、t (IRD)-related problems:1. The probe IRD was not updated when the responsibility for probe cooling was split between organizations.2. The specification compliance matrix failed to identify an inconsistency across the interface.End-to-end responsibility for elements within a given interface should r

15、eside within a single organization. Specifically, one single individual should be assigned responsibility for on-pad cooling (purge source, to purge outlet, to thermally controlled elements).Recommendation(s): 1. Require that program decisions affecting interfaces, whether made at the working group

16、level or at program reviews, automatically trigger a review of the need to change the IRD or Interface Control Drawing (ICD).2. Ensure that the verification methodology is thorough and considers responsibility statements as well as requirements.Evidence of Recurrence Control Effectiveness: N/ADocume

17、nts Related to Lesson: N/AMission Directorate(s): N/AAdditional Key Phrase(s): a71 Administration/OrganizationProvided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-a71 Configuration Managementa71 Test & VerificationAdditional Info: Approval Info: a71 Approval Date: 1997-12-16a71 Approval Name: Carol Dumaina71 Approval Organization: 125-204a71 Approval Phone Number: 818-354-8242Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-

展开阅读全文
相关资源
猜你喜欢
  • GOST EN 407-2012 Occupational safety standards system Personal protective means of hands Protective gloves from heat and fire Technical requirements Test methods《职业安全标准体系 个人护手方法 防热.pdf GOST EN 407-2012 Occupational safety standards system Personal protective means of hands Protective gloves from heat and fire Technical requirements Test methods《职业安全标准体系 个人护手方法 防热.pdf
  • GOST EN 454-2013 Food processing machinery and equipment Planetary mixers Safety and hygiene requirements《食品加工机械和设备 行星式混合机 安全和卫生要求》.pdf GOST EN 454-2013 Food processing machinery and equipment Planetary mixers Safety and hygiene requirements《食品加工机械和设备 行星式混合机 安全和卫生要求》.pdf
  • GOST EN 455-1-2014 Medical gloves for single use Part 1 Method for determination of tightness《一次性医用手套 第1部分 紧密性的测定方法》.pdf GOST EN 455-1-2014 Medical gloves for single use Part 1 Method for determination of tightness《一次性医用手套 第1部分 紧密性的测定方法》.pdf
  • GOST EN 455-2-2014 Medical gloves for single use Part 2 Method for determination of physical-mechanical properties《一次性医用手套 第2部分 物理特性的测定方法》.pdf GOST EN 455-2-2014 Medical gloves for single use Part 2 Method for determination of physical-mechanical properties《一次性医用手套 第2部分 物理特性的测定方法》.pdf
  • GOST EN 474-10-2012 Earth-moving machinery Safety Part 10 Requirements for trenchers《土方机械 安全 第10部分 挖沟机要求》.pdf GOST EN 474-10-2012 Earth-moving machinery Safety Part 10 Requirements for trenchers《土方机械 安全 第10部分 挖沟机要求》.pdf
  • GOST EN 474-11-2012 Earth-moving machinery Safety Part 11 Requirements for earth and landfill compactors《土方机械 安全 第11部分 土方回填压实机要求》.pdf GOST EN 474-11-2012 Earth-moving machinery Safety Part 11 Requirements for earth and landfill compactors《土方机械 安全 第11部分 土方回填压实机要求》.pdf
  • GOST EN 474-2-2012 Earth-moving machinery Safety Part 2 Requirements for tractor-dozers《土方机械 安全 第2部分 推土机要求》.pdf GOST EN 474-2-2012 Earth-moving machinery Safety Part 2 Requirements for tractor-dozers《土方机械 安全 第2部分 推土机要求》.pdf
  • GOST EN 495-5-2012 Roofing and hydraulic-insulating flexible polymeric (thermoplastic or elastomer) materials Method for determination of foldability at low temperatures《屋面和液压绝缘柔性聚.pdf GOST EN 495-5-2012 Roofing and hydraulic-insulating flexible polymeric (thermoplastic or elastomer) materials Method for determination of foldability at low temperatures《屋面和液压绝缘柔性聚.pdf
  • GOST EN 511-2012 Occupational safety standards system Personal protective means of hands Protective gloves against cold General technical requirements Test methods《职业安全标准体系 个人护手方法 .pdf GOST EN 511-2012 Occupational safety standards system Personal protective means of hands Protective gloves against cold General technical requirements Test methods《职业安全标准体系 个人护手方法 .pdf
  • 相关搜索

    当前位置:首页 > 标准规范 > 国际标准 > 其他

    copyright@ 2008-2019 麦多课文库(www.mydoc123.com)网站版权所有
    备案/许可证编号:苏ICP备17064731号-1