REG NASA-LLIS-0726--2000 Lessons Learned End-To-End Compatibility and Mission Simulation Testing.pdf

上传人:unhappyhay135 文档编号:1018372 上传时间:2019-03-21 格式:PDF 页数:5 大小:19.96KB
下载 相关 举报
REG NASA-LLIS-0726--2000 Lessons Learned End-To-End Compatibility and Mission Simulation Testing.pdf_第1页
第1页 / 共5页
REG NASA-LLIS-0726--2000 Lessons Learned End-To-End Compatibility and Mission Simulation Testing.pdf_第2页
第2页 / 共5页
REG NASA-LLIS-0726--2000 Lessons Learned End-To-End Compatibility and Mission Simulation Testing.pdf_第3页
第3页 / 共5页
REG NASA-LLIS-0726--2000 Lessons Learned End-To-End Compatibility and Mission Simulation Testing.pdf_第4页
第4页 / 共5页
REG NASA-LLIS-0726--2000 Lessons Learned End-To-End Compatibility and Mission Simulation Testing.pdf_第5页
第5页 / 共5页
亲,该文档总共5页,全部预览完了,如果喜欢就下载吧!
资源描述

1、Best Practices Entry: Best Practice Info:a71 Committee Approval Date: 2000-03-30a71 Center Point of Contact: GSFCa71 Submitted by: Wilson HarkinsSubject: End-To-End Compatibility and Mission Simulation Testing Practice: End-to-End Compatibility and Mission Simulation testing are conducted on all por

2、tions of the Ground Data Systems (GDS). These tests are performed to fully demonstrate the operational compatibility and the ability of the entire system to perform as expected during the flight mission.Programs that Certify Usage: This practice has been used on all flight programs managed by the Go

3、ddard Space Flight Center (GSFC). They are required to use this practice.Center to Contact for Information: GSFCImplementation Method: This Lesson Learned is based on Reliability Practice Number PT-TE-1437 from NASA Technical Memorandum 4322A, NASA Reliability Preferred Practices for Design and Test

4、.Benefits:This testing significantly enhances flight reliability by ensuring that all portions of the flight operational system work together as expected. This includes the proper flow of data to the end users.Implementation Method:Provided by IHSNot for ResaleNo reproduction or networking permitted

5、 without license from IHS-,-,-The GSFC Mission Operations and Data Systems Directorate (MO&DSD) develops, maintains, and operates a worldwide Ground Data System (GDS) to support a wide range of flight missions. Various organizational units within the MO&DSD such as branches, sections, and mission re

6、adiness test teams collaborate with the Flight Project and the Flight Assurance Directorate in planning and performing a wide range of mission readiness testing. The purpose of this readiness testing is to verify the performance and to demonstrate the readiness of the integrated GDS to support speci

7、fic flight missions. This practice is implemented by the MO&DSD in the following three basic phases.Phase A: Acceptance and Interface Testing of Individual Elements of GDSAcceptance and Interface testing is performed on each element of the GDS for each flight mission. This testing is particularly ap

8、plicable to those hardware and software elements in the GDS that have been updated, modified, or added to meet specific requirements of a mission.The acceptance and interface testing is followed by a formal Project Integration and Test Program. The Project Integration and Test Program verifies that

9、the GDS can meet all of the project mission support requirements and documents the systems operational readiness. After all requirements have been verified, all discrepancies have been resolved, and all corrective actions have been completed, the verification process through Integration and Test is

10、complete. The GDS is now ready to participate in Phase B, Compatibility Testing.Phase B: Compatibility TestingCompatibility testing is conducted on all portions of the operational system including the payload, the operational software, and the ground systems. The ground systems include the Space and

11、 Ground Networks, the Mission Operations Control Center (MOCC), and the data processing facilities. When the mission scenario calls for electrical operation of the payload aboard the STS or in conjunction with it, compatibility of the operational system is demonstrated with the use of the appropriat

12、e elements of the STS, such as the Orbiter Payload Data Handling System and the Mission Control Center. After completion of compatibility testing, the GDS is ready to participate in Phase C, Mission Readiness and Mission Simulations Testing.Phase C: Mission Readiness And Mission Simulation TestingMi

13、ssion Readiness Testing is conducted to verify that system design specifications are being routinely met, to ascertain the level of operational proficiency being maintained throughout the networks, and to evaluate the networks abilities to meet or exceed design specifications in response to project

14、requirements. An evaluation phase follows in which all Discrepancy Reports (DRs) are reviewed by a DR Review Board.Mission Simulation Testing includes data flow tests performed on the total system in a realistic mission timeline. When practical, external stimulus of the spacecraft instruments and at

15、titude control Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-sensors are used.Mission Readiness and Mission Simulation Testing is carried out in accordance with formal test plans prepared and approved by the MO&DSD with concurrence by the flight pr

16、ojects. These test plans define test coordination, system requirements, test procedures, problem resolution procedures, and reporting requirements. In order to ensure an integrated testing effort, testing and planning is coordinated through a Mission Readiness Test Team comprised of project and MO&D

17、SD development, test, and operations representatives.Test Facilities and Systems Used for Compatibility and Simulations TestingThis section on test facilities and systems used for compatibility and simulation testing provides a description of the major elements of the GDS and how they are used in th

18、ese test programs.The Simulations Operations Center (SOC) located at the GSFC provides support and test tools that can emulate the spacecraft, the MOCC, the Network Control Center, and the Ground and Space Networks. System evaluations and validation test and simulation programs are also conducted to

19、 characterize new or modified Space and Ground Network capabilities, to verify that system design specifications are being met routinely, to ascertain the level of operational proficiency being maintained throughout the networks, and to evaluate network abilities to meet or exceed design specificati

20、ons in response to user requirements. The SOC provides various resources used to simulate and test ground data system elements. These resources include the Project Platform Training Simulator, the SOC Mission Control Simulator, the RF Simulations Operations Center, the Portable Simulations System, a

21、nd various utility programs such as a Super Programmable Data Formatter and the data blocker/deblocker. The SOC has a standard NASA Communications (NASCOM) interface which permits it to communicate with all ground data system elements during Simulation and End-to-End Testing.The Platform Training Si

22、mulator provides support for training Flight Operations Teams (FOT) in normal and contingency operations of the spacecraft. The FOT can refine and practice operations and contingency procedures without using valuable spacecraft time. The Training Simulator is also used to support the Integration and

23、 Test data flows and the Network Simulation tests.The SOC Mission Control Simulator emulates the Johnson Space Centers payload support functions for simulations with the MOCC.The RF SOC is a simulations facility used for Space Network (SN) simulations and data flows. It has the capability to communi

24、cate with the Tracking and Data Relay Satellite E through a small satellite earth terminal located at the GSFC.The Data Evaluation Lab (DEL) provides recording systems, engineering support, and special data services. It can generate, quality check, and provide distribution for pre-mission simulation

25、 tapes and Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-analog tapes. Additionally, the DEL can playback generated tapes in the form of data flow to the Mission Operations Center (MOC) and other elements in support of engineering, pre-mission, and

26、 operational readiness tests.The SUPER Programmable Data Formatter (PDF) is a portable, stand-alone system used in the SOC or at remote sites for ground system data flow tests, interface verification tests, and end-to-end rehearsals. The SUPER PDF can generate simulated real-time and playback teleme

27、try. It is packaged in a portable unit for supporting tests from the Ground network (GN), spacecraft integration areas, or launch sites.Mobile Compatibility Test Vans (CTV), normally stationed at the GSFC, travel to the spacecraft factory or to the launch site. They are used for verifying the spacec

28、rafts RF compatibility with the network by performing initial checkout of the spacecraft RF interface with the tracking and data networks. The CTVs also provide the MOCC with a direct link to the spacecraft at the manufacturers plant. The CTV can send spacecraft telemetry data via the GN and NASCOM

29、to all support elements and can receive commands from the MOC via the SN and the NASCOM. They can also be used as a data source for performing network verification tests.Monitoring and Witnessing of Ground Data System TestingThe GSFC Office of Flight Assurance assigns an Assurance Management Represe

30、ntative (AMR), a Systems Assurance Manager (SAM), and others as needed to perform assurance functions on flight projects. These functions include identifying tests to be monitored or witnessed, determining the level of coverage based on the test objectives and criticality, and arranging for the cove

31、rage by assurance representatives or their contractors. The assurance functions also include observing and reporting on the success of the test in meeting its objectives. The results are documented and identify any events or anomalies for use by engineering and management. The AMR test report contai

32、ns the objectives of the test, anomaly reports, corrective actions expected, and the AMRs appraisal of whether test objectives were met.Technical Rationale:The detailed performance of the Ground Data System in meeting the specific technical requirements of spaceflight missions is thoroughly evaluate

33、d and validated in order to ensure mission readiness and compatibility with mission requirements. This readiness includes the training of control center operational personnel by simulating and practicing both nominal and contingency flight operations.References1. GSFC Document Entitled “Directorate

34、Test Support“, Subject - Code 500 Directorate Test Support2. GSFC Document Entitled “Flight Assurance Procedure“ No. P-303-1025, Subject-Monitoring Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-and Witnessing Ground Data System Testing“3. GSFC, SPA

35、R-3, Standard Payload Assurance Requirements (SPAR) for GSFC Orbital Project, Paragraph 3.7 March 1990Impact of Non-Practice: Nonpractice of End-to-End Compatibility and Mission Simulation Testing could result in marginal performance or failure of the mission due to incompatibilities in the Ground D

36、ata System. Control center operational errors due to inadequate training could significantly impact the health and safety of the spacecraft.Related Practices: N/AAdditional Info: Approval Info: a71 Approval Date: 2000-03-30a71 Approval Name: Eric Raynora71 Approval Organization: QSa71 Approval Phone Number: 202-358-4738Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-