1、Lessons Learned Entry: 0749Lesson Info:a71 Lesson Number: 0749a71 Lesson Date: 1999-08-23a71 Submitting Organization: GRCa71 Submitted by: Joe MorrisSubject: Facilities, Mod/Rehab Projects, Construction Mtgs. Description of Driving Event: Building Rehab projects are typically done on the second shif
2、t (4:00 p.m.-12:00 a.m.) and construction meetings are held every week to discuss the progress of the job. These meeting times and dates are left up to the participants to determine. The contract requires the meeting, but does not dictate a specific time.The Contractors job superintendent doesnt sta
3、rt work until 4:00 p.m. and when construction meetings start at 3:00 p.m. some valuable input from the field is missing. The Contractors Project Manager is always in attendance, however the field representation is also required. If the meetings were moved until 4:00 p.m., many of the Governments rep
4、resentatives would not be in attendance due to their work schedule.Lesson(s) Learned: a71 It is hard to get complete attendance at the weekly construction meetings.Recommendation(s): a71 In the specification section 01200 Project Meetings, specifically require attendance of the weekly construction m
5、eetings by the Contractors job superintendent.Evidence of Recurrence Control Effectiveness: Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-N/ADocuments Related to Lesson: N/AMission Directorate(s): N/AAdditional Key Phrase(s): a71 Facilitiesa71 Logi
6、sticsa71 Procurement Small Business & Industrial RelationsAdditional Info: Approval Info: a71 Approval Date: 2000-04-14a71 Approval Name: Eric Raynora71 Approval Organization: QSa71 Approval Phone Number: 202-358-4738Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-