1、Lessons Learned Entry: 0860Lesson Info:a71 Lesson Number: 0860a71 Lesson Date: 1999-08-23a71 Submitting Organization: GRCa71 Submitted by: Joe MorrisSubject: Facilities, Mod & Rehab, Added Team Member Description of Driving Event: The Mod and Rehab projects are typically requiring that people be mov
2、ed out of offices while the construction activity is taking place. As a result, there is an extra burden on the Project Manager to coordinate people moves. Along with the moves come the issues of telephone and computer moves, because different organizations handle these moves. In addition, there is
3、also the issue of where are the people going to be temporarily moved to.During the planning phases of moves, it becomes a full-time job to coordinate all the above activities.Lesson(s) Learned: It becomes a logistics nightmare for a Project Manager to coordinate people moves in a Mod and Rehab proje
4、ct.Recommendation(s): Include in the Project Team a Move Coordinator. This person would work along with the Project Manager to ensure a smooth transition for the inconvenienced building occupants.Evidence of Recurrence Control Effectiveness: N/ADocuments Related to Lesson: Provided by IHSNot for Res
5、aleNo reproduction or networking permitted without license from IHS-,-,-N/AMission Directorate(s): N/AAdditional Key Phrase(s): a71 Administration/Organizationa71 FacilitiesAdditional Info: Approval Info: a71 Approval Date: 2000-06-5a71 Approval Name: Eric Raynora71 Approval Organization: QSa71 Approval Phone Number: 202-358-4738Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-