1、Lessons Learned Entry: 1348Lesson Info:a71 Lesson Number: 1348a71 Lesson Date: 2003-07-15a71 Submitting Organization: GSFCa71 Submitted by: Mathew SchwallerSubject: ADEOS-II NASA Ground Network (NGN) Development and Early Operations - Management of System Components Description of Driving Event: Mos
2、t of the components that comprise the NASA Ground Network that supports the ADEOS-II mission were provided to the NGN as contributions from operational entities under the management of various NASA organizations. This approach presented both opportunities and challenges during the ADEOS-II NGN devel
3、opment and early operations. The one lesson learned in this regard with respect to managing the contribution of system components by various organizational entities is summarized below. It should be noted that ADEOS-II is a international partner mission, with the Japanese Space Agency (NASDA) as the
4、 mission lead. NASA provided NGN ground system support through an MOU with NASDA.Lesson(s) Learned: Engage Operational Component Management in Integration and Testing.Integration of NGNs many components was a challenge both in terms of the management of the system-to-system interfaces and in the man
5、agement of lines of authority and reporting for the various organizations involved. One of the methods used to manage this complexity was to charter a quarterly review panel consisting of “stake-holder” participants with management authority of the various NGN components. The actual ADEOS-II review
6、panel consisted of stake-holder participants from NASA/GSFC Code 450 (ground station and CSOC responsibilities), NASA/GSFC Code 420 (EOS-G Program Office), NASA/GSFC Code 423 (DAACs and networking), NASA/GSFC Code 290 (networks), NOAA/NESDIS (real-time interfaces). Code 300 (quality assurance) also
7、participated as a panel member, and NASA/JPL participated ex officio (SeaWinds management).The ADEOS-II quarterly review panel proved to be very effective in identifying and working-off Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-actions at the m
8、anagement level, and in directing actions to the working level as needed during the late phases of development and testing. The quarterly review panel was declared a success and disbanded after the successful ADEOS-II NGN Operations Readiness Review held in September 2002.Recommendation(s): Engage O
9、perational Component Management in Integration and Testing.Recommendations:1. Engage managers from operational components in the integration and test phases when re-using operational components in the development of ground systems for new missions.2. Establish a review panel of cognizant managers fr
10、om contributing organization and do not disband the panel until after successful operational phase transition occurs. Evidence of Recurrence Control Effectiveness: N/ADocuments Related to Lesson: N/AMission Directorate(s): a71 ScienceAdditional Key Phrase(s): a71 Administration/Organizationa71 Groun
11、d Equipmenta71 Ground Operationsa71 Information Technology/Systemsa71 Softwarea71 Test & VerificationAdditional Info: Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Approval Info: a71 Approval Date: 2003-07-28a71 Approval Name: Al Galloa71 Approval Organization: GSFCa71 Approval Phone Number: 301-286-3756Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-