REG NASA-LLIS-3617-2011 Lessons Learned - Performance Measurement Baseline (PMB) Implementation Reporting Expectations on Letter Contract Award.pdf

上传人:hopesteam270 文档编号:1019428 上传时间:2019-03-21 格式:PDF 页数:2 大小:59.22KB
下载 相关 举报
REG NASA-LLIS-3617-2011 Lessons Learned - Performance Measurement Baseline (PMB) Implementation Reporting Expectations on Letter Contract Award.pdf_第1页
第1页 / 共2页
REG NASA-LLIS-3617-2011 Lessons Learned - Performance Measurement Baseline (PMB) Implementation Reporting Expectations on Letter Contract Award.pdf_第2页
第2页 / 共2页
亲,该文档总共2页,全部预览完了,如果喜欢就下载吧!
资源描述

1、Public Lessons Learned Entry: 3617 Lesson Info: Lesson Number: 3617 Submitting Organization: MSFC Submitted by: Kristen Kehrer Subject: Performance Measurement Baseline (PMB) Implementation Reporting Expectations on Letter Contract Award Abstract: The Earned Value Management (EVM) requirements, incl

2、uding Contract Performance Report (CPR) reporting, were included in the Constellation Program (CxP) Extravehicular Activity (EVA) Project prime contract. The Prime operated without a Performance Measurement Baseline (PMB) for a year while under letter contract. Letter contract definitization can tak

3、e months/years to occur, and during that time NASA projects have little insight into contract performance. Additionally, there is a tendency for contractors to delay establishing a PMB, even an interim PMB, prior to contract definitization. Without an interim PMB, it is difficult to determine curren

4、t performance, assess technical, cost or schedule risks/impacts and planning and control by both the prime contractor and the government is diminished. Description of Driving Event: The event driving this lesson learned was a pilot project conducted on the CxP Extravehicular Activity (EVA) Project a

5、s part of the Agencys EVM Capability Project. Lesson(s) Learned: Prime contractors must comply with the EVM System and reporting requirements included in Letter Contract awards and projects should only allow waivers to these requirements due to extreme circumstances. This includes the initialization

6、 of the PMB, submission of the CPR and the Integrated Master Schedule (IMS), and conduct of the Integrated Baseline Review (IBR) to the extent practical within 180 days after award (in accordance with the contract EVM clause). Additionally, Projects should strive for timely contract definitization o

7、f letter contracts so that a comprehensive and reliable PMB can be established, performance measured and evaluated, and better insight is gained into the contractors and the overall Projects ability to meet the technical/cost/schedule objectives. Recommendation(s): Ensure Agency EVM System Descripti

8、on Document (SDD) and best practices clearly discuss application of EVM on prime contracts and major subcontractors to include expectations regarding initializing the PMB and EVM reporting on letter contract awards. EVM Capability team developed training and revisions to appropriate EVM related Hand

9、books should address EVM requirements and best practices of PMB development under letter contracts. Evidence of Recurrence Control Effectiveness: Projects receive EVM reporting from contracts operating under letter contract conditions. Projects are able to assess cost and schedule performance prior

10、to contract definitization. Letter contracts are definitized in accordance with NFS 1843.7005 which refers to FAR 16.603 (Letter contracts definitized within target date of 180 days after date of letter contract or before completion of 40% of the work to be performed, whichever occurs first). Docume

11、nts Related to Lesson: Federal Acquisition Regulation (FAR) 16.603 NASA FAR Supplement 1843.7005 Mission Directorate(s): Exploration Systems Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Science Space Operations Aeronautics Research Additional Key

12、Phrase(s): Program Management. Program Management.Acquisition / procurement strategy and planning Additional Info: Project: Constellation Program and Extravehicular Activity (EVA) Project Approval Info: Approval Date: 2011-11-30 Approval Name: mbell Approval Organization: HQ Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-

展开阅读全文
相关资源
猜你喜欢
相关搜索

当前位置:首页 > 标准规范 > 国际标准 > 其他

copyright@ 2008-2019 麦多课文库(www.mydoc123.com)网站版权所有
备案/许可证编号:苏ICP备17064731号-1