1、 10-10 07 01 50.19 - 1 SECTION 07 01 50.19 PREPARATION FOR RE-ROOFING SPEC WRITER NOTES: 1. Delete text in / / if not applicable to project. Also delete any other item or paragraph not applicable in the section and renumber the paragraphs. 2. Edit Description article below after establishing re-roof
2、ing scope and editing section to correspond to Project requirements. PART 1 - GENERAL 1.1 DESCRIPTION A. /Roof tear-off,/ /partial roof tear-off,/ /temporary roofing membrane,/ /roof re-cover preparation,/ /removal of base flashings/ on existing construction in preparation to receive new roofing mem
3、brane. SPEC WRITER NOTE: Modify paragraph below to adequately describe existing roofing system or systems to be prepared for re-roofing. B. Existing Membrane Roofing System: /Built-up asphalt/ /Built-up coal-tar/ /EPDM/ /CSPE/ /PVC/ /TPO/ /Modified bituminous/ roofing membrane, with related insulati
4、on, surfacing, and components and accessories between deck and roofing membrane. SPEC WRITER NOTE: References in Related Work article below are in addition to cross-references to other sections located in the section text. 1.2 RELATED WORK A. Use of the premises and phasing requirements: Section 01
5、00 00 GENERAL REQUIREMENTS. B. Temporary construction and environmental-protection measures for reroofing preparation: Section 01 00 00 GENERAL REQUIREMENTS C. HVAC equipment removal and reinstallation: Division 23 sections. D. Electrical equipment disconnection and reconnection: Division 26 section
6、s. 1.3 APPLICABLE PUBLICATIONS SPEC WRITER NOTES: 1. Update applicable publications to current issue at time of project specification preparation. 2. Update material requirements to agree with applicable requirements (types, grades, classes,) specified in the referenced Applicable Publications. Prov
7、ided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-10-10 07 01 50.19 - 2 A. Publications listed below form a part of this specification to the extent referenced. Publications are referenced in the text by the basic designation only. Editions of applicable p
8、ublications current on date of issue of bidding documents apply unless otherwise indicated. B. American National Standards Institute/Single-Ply Roofing Institute (ANSI/SPRI): ANSI/SPRI FX-1-01(R2006) Standard Field Test Procedure for Determining the Withdrawal Resistance of Roofing Fasteners. C. AST
9、M International (ASTM): C208-08.Cellulosic Fiber Insulating Board C728-05.Perlite Thermal Insulation Board C1177/C1177M-08.Standard Specification for Glass Mat Gypsum Substrate for Use as Sheathing C1278/C1278M-07.Standard Specification for Fiber-Reinforced Gypsum Panel D1079-09Standard Terminology
10、Relating to Roofing and Waterproofing D. FM Approvals: RoofNav Approved Roofing Assemblies and Products. 4450-89.Approved Standard for Class 1 Insulated Steel Deck Roofs 4470-10.Approved Standard for Class 1 Roof Coverings 1-28-09.Loss Prevention Data Sheet: Design Wind Loads. 1-29-09.Loss Preventio
11、n Data Sheet: Above-Deck Roof Components 1-49-09.Loss Prevention Data Sheet: Perimeter Flashing E. National Roofing Contractors Association: Roofing and Waterproofing Manual 1.4 MATERIALS OWNERSHIP A. Assume ownership of demolished materials and remove from Project site and dispose of legally, unles
12、s indicated to be reused, reinstalled, or otherwise to remain Owners property. 1.5 DEFINITIONS A. Refer to ASTM D1079 and NRCA “The NRCA Roofing and Waterproofing Manual“ for definition of terms. Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-10-10
13、07 01 50.19 - 3 1.6 QUALITY CONTROL A. Requirements of Division 07 roofing section for qualifications of roofing system and roofing insulation Installer; work of this section shall be performed by same Installer. 1. Where Project requirements include removal of asbestos-containing material, Installe
14、r must be legally qualified to perform the required work. 2. Where Project requirements include work affecting existing roofing system to remain under warranty, Installer must be approved by warrantor of existing roofing system. B. Regulatory Requirements: Comply with governing EPA notification regu
15、lations. Comply with hauling and disposal regulations of authorities having jurisdiction. C. Reroofing Conference: Conduct conference at Project site. 1. Meet with Owner; Architect-Engineer; testing and inspecting agency representative; roofing system manufacturers representative; roofing Installer
16、including project manager, superintendent, and foreman; and installers whose work interfaces with or affects reroofing. 2. Review methods and procedures related to roofing system tear-off and replacement 1.7 SUBMITTALS A. Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND S
17、AMPLES. B. Manufacturers Literature and Data: 1. Recover boards. C. List of proposed infill materials. D. List of proposed temporary roofing materials. E. Fastener pull-out test report. F. Photographs or Videotape: Document existing conditions of adjacent construction including site improvements. G.
18、 Landfill Records: Indicate receipt and acceptance of hazardous wastes by a licensed landfill facility. H. Qualification Data: For Installer. 1. Certificate indicating Installer is licensed to perform asbestos abatement. 2. Certificate indicating Installer is approved by warrantor of existing roofin
19、g system. Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-10-10 07 01 50.19 - 4 1.8 PROJECT CONDITIONS A. Owner will occupy portions of building below reroofing area. Conduct reroofing so Owners operations will not be disrupted. 1. Coordinate work ac
20、tivities daily with Owner. 2. Provide Owner with not less than 72 hours notice of activities that may affect Owners operations. SPEC WRITER NOTE: Retain subparagraph below if known impaired deck areas. B. Protect building and landscaping from damage. C. Maintain access to existing walkways and adjac
21、ent occupied facilities. D. Available Information: The following are available for Contractor reference: SPEC WRITER NOTE: Retain three subparagraphs below if applicable. Consider including this information in Division 00 Document “Available Information.“ 1. Roof Moisture Survey of existing membrane
22、 roofing system. 2. Analysis of test cores from existing membrane roofing system. 3. Construction Drawings and Project Manual for existing roofing system. 4. Contractor is responsible for interpretation and conclusions based upon available information. E. Weather Limitations: Proceed with reroofing
23、preparation only when weather conditions permit Work to proceed without water entering existing roofing system or building. SPEC WRITER NOTE: Retain one of two paragraphs below or delete if no hazardous materials. Modify to correspond to Project requirements. F. Hazardous Materials: It is not expect
24、ed that Contractor will encounter hazardous materials such as asbestos-containing materials. 1. Owner will remove hazardous materials before start of the Work. 2. Do not disturb materials suspected of containing hazardous materials. Notify Architect-Engineer and Owner. Hazardous materials will be re
25、moved by Owner under a separate contract. G. Hazardous Materials: A report on the presence of hazardous materials is available to Contractor for review and use. 1. Examine report to become aware of locations where hazardous materials are present. 2. Hazardous material remediation is specified elsewh
26、ere in the Contract Documents. Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-10-10 07 01 50.19 - 5 1.9 WARRANTY SPEC WRITER NOTE: Retain this article if portions of existing roof still under warranty are to remain or if an adjoining existing roof i
27、s under warranty. A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces affected by reroofing, by methods and with materials acceptable to warrantor. 1. Notify warrantor of existing roofing system before proceeding, and upon completion of reroofing. 2. Obtain documentatio
28、n verifying that existing roofing system has been inspected by warrantor and warranty remains in effect. Submit documentation at Project closeout. PART 2 - PRODUCTS 2.1 INFILL MATERIALS SPEC WRITER NOTE: Retain this article when patching and retaining portions of existing roofing system. A. Use infi
29、ll materials matching existing membrane roofing system materials. 2.2 TEMPORARY ROOFING MATERIALS A. Design of temporary roofing and selection of materials are responsibilities of Contractor. 2.3 RECOVER BOARDS SPEC WRITER NOTE: Retain one of first six paragraphs below if required or delete this art
30、icle A. Insulation Serving as Recover Board: Requirements are specified in Section 07 22 00 ROOF AND DECK INSULATION. B. Recover Board: ASTM C208, Type II, Grade 2, cellulosic-fiber insulation board; 13 mm (1/2 inch) thick. C. Recover Board: Fan-folded, unfaced, extruded-polystyrene board insulation
31、; /5-mm (3/16-inch)/ /-mm (1/4-inch)/ /10-mm (3/8-inch)/ nominal thickness. D. Recover Board: ASTM C1177/C1177M, glass-mat, water-resistant gypsum substrate; /6 mm (1/4 inch)/ /13 mm (1/2 inch)/ /Type X, 16 mm (5/8 inch)/ thick. E. Recover Board: ASTM C1278/C1278M, cellulosic-fiber-reinforced, water
32、-resistant gypsum substrate; /6 mm (1/4 inch)/ /10 mm (3/8 inch)/ /13 mm (1/2 inch)/ /16 mm (5/8 inch)/ thick. Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-10-10 07 01 50.19 - 6 F. Recover Board: ASTM C728, perlite board; /13 mm (1/2 inch)/ /19 mm
33、 (3/4 inch)/ /25 mm (1 inch)/ thick. G. Fasteners: Factory-coated steel fasteners, No. 12 or 14, and metal or plastic plates listed in FM Approvals “RoofNav.“ 2.4 AUXILIARY REROOFING MATERIALS A. General: Auxiliary reroofing preparation materials recommended by roofing system manufacturer and compat
34、ible with components of existing and new membrane roofing system. B. Base Sheet Fasteners: Capped head, factory-coated steel fasteners, listed in FM Approvals “RoofNav.“ C. Metal Flashing Sheet: Metal flashing sheet is specified in Section 07 60 00 SHEET METAL FLASHING AND TRIM. PART 3 - EXECUTION 3
35、.1 PREPARATION SPEC WRITER NOTE: Retain first paragraph below if portions of roof area that are to remain unaltered and in-service during the Work require protection. A. Protect existing membrane roofing system that is indicated not to be reroofed. 1. Limit traffic and material storage to areas of e
36、xisting roofing membrane that have been protected. 2. Maintain temporary protection and leave in place until replacement roofing has been completed. Remove temporary protection on completion of reroofing. B. Coordinate with Owner to shut down air-intake equipment in the vicinity of the Work. Cover a
37、ir-intake louvers before proceeding with reroofing work that could affect indoor air quality or activate smoke detectors in the ductwork. 1. Comply with Owners requirements for maintaining fire watch when temporarily disabling smoke detectors. C. During removal operations, have sufficient and suitab
38、le materials on-site to facilitate rapid installation of temporary protection in the event of unexpected rain. D. Maintain roof drains in functioning condition to ensure roof drainage at end of each workday. Prevent debris from entering or blocking roof drains and conductors. Use roof-drain plugs sp
39、ecifically designed for this purpose. Remove roof-drain plugs at end of each workday, when no work is taking place, or when rain is forecast. Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-10-10 07 01 50.19 - 7 1. If roof drains are temporarily bloc
40、ked or unserviceable due to roofing system removal or partial installation of new membrane roofing system, provide alternative drainage method to remove water and eliminate ponding. 2. Do not permit water to enter into or under existing membrane roofing system components that are to remain. E. Verif
41、y that rooftop utilities and service piping have been shut off before beginning the Work. 3.2 ROOF TEAR-OFF A. General: Notify Owner each day of extent of roof tear-off proposed for that day and obtain authorization to proceed. B. Remove aggregate ballast from roofing membrane./Store aggregate balla
42、st for reuse./ C. Remove loose aggregate from aggregate-surfaced built-up bituminous roofing using a power broom. D. Remove pavers and accessories from roofing membrane. Store and protect pavers and accessories for reuse. Discard cracked pavers. SPEC WRITER NOTE: Retain first paragraph below for pro
43、tected roofing membrane. E. Remove protection mat and insulation from protected roofing membrane. 1. Discard insulation that is wet and exceeds /128/ kg/cu. m (/8/ lb/cu. ft.). 2. Store insulation for reuse and protect from physical damage. F. Roof Tear-Off: Remove existing roofing membrane and othe
44、r membrane roofing system components down to the deck. Remove /cover boards/ /roof insulation/ /substrate boards/. SPEC WRITER NOTE: Retain first subparagraph below if applicable. 1. Dry bitumen and felts that are firmly bonded to concrete decks may remain. Remove wet or unadhered bitumen and felts.
45、 2. Comply with FM Approvals requirements for removal of excess asphalt from steel decks. 3. Remove fasteners from deck /or cut fasteners off slightly above deck surface and apply recover board prior to installing roof membrane/. G. Partial Roof Tear-Off: Where indicated, remove existing roofing mem
46、brane and other membrane roofing system components down to the deck. 1. Remove /cover boards/ /roof insulation/ /substrate boards/. SPEC WRITER NOTE: Retain first subparagraph below if applicable. Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-10-10
47、 07 01 50.19 - 8 2. Dry bitumen and felts that are firmly bonded to concrete decks may remain. Remove wet or unadhered bitumen and felts. 3. Comply with FM Approvals requirements for removal of excess asphalt from steel decks. 4. Remove fasteners from deck /or cut fasteners off slightly above deck s
48、urface and apply recover board prior to installing roof membrane/. SPEC WRITER NOTE: Retain paragraph below if partial roof tear-off is limited to removing existing roofing membrane and selected components within membrane roofing system that have been identified for removal. H. Partial Roof Tear-Off
49、: Remove existing roofing membrane and immediately check for presence of moisture by visually observing /cover boards/ /roof insulation/ /substrate boards/ that will remain. 1. Coordinate with Owners inspector to schedule times for tests and inspections immediately after membrane removal. 2. Remove wet o