VA 23 72 00-2011 AIR-TO-AIR ENERGY RECOVERY EQUIPMENT.pdf

上传人:eventdump275 文档编号:1074930 上传时间:2019-04-06 格式:PDF 页数:9 大小:35.40KB
下载 相关 举报
VA 23 72 00-2011 AIR-TO-AIR ENERGY RECOVERY EQUIPMENT.pdf_第1页
第1页 / 共9页
VA 23 72 00-2011 AIR-TO-AIR ENERGY RECOVERY EQUIPMENT.pdf_第2页
第2页 / 共9页
VA 23 72 00-2011 AIR-TO-AIR ENERGY RECOVERY EQUIPMENT.pdf_第3页
第3页 / 共9页
VA 23 72 00-2011 AIR-TO-AIR ENERGY RECOVERY EQUIPMENT.pdf_第4页
第4页 / 共9页
VA 23 72 00-2011 AIR-TO-AIR ENERGY RECOVERY EQUIPMENT.pdf_第5页
第5页 / 共9页
点击查看更多>>
资源描述

1、05-11 23 72 00-1 SECTION 23 72 00 AIR-TO-AIR ENERGY RECOVERY EQUIPMENT SPEC WRITER NOTE: Delete between /-/ if not applicable to project. Also delete any other item or paragraph not applicable in the section and renumber the paragraphs. PART 1 - GENERAL 1.1 DESCRIPTION This Section specifies /air to

2、 air heat pipe heat exchangers /rotary air-to-air heat exchangers /air-to-air plate heat exchangers /and /run-around heat recovery systems/. 1.2 RELATED WORK A. Section 01 00 00, GENERAL REQUIREMENTS: Requirements for pre-test of equipment. /B. Section 13 05 41, SEISMIC RESTRAINT REQUIREMENTS FOR NO

3、N-STRUCTURAL COMPONENTS: Seismic requirements for non-structural equipment./ C. Section 23 05 11, COMMON WORK RESULTS FOR HVAC: General mechanical requirements and items, which are common to more than one section of Division 23. D. Section 23 21 23, HYDRONIC PUMPS: Requirements for pumping equipment

4、. E. Section 23 07 11, HVAC and BOILER PLANT INSULATION: Requirements for piping insulation. F. Section 23 21 13, HYDRONIC PIPING: Requirements for piping for expansion tanks. G. Section 23 82 16, AIR COILS: Requirements for run-around system coils. H. Section 23 31 00, HVAC DUCTS and CASINGS: Requi

5、rements for sheet metal ducts and fittings. I. Section 23 40 00, HVAC AIR CLEANING DEVICES: Requirements for filters used before heat recovery coils. J. Section 23 09 23, DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC: Requirements for controls and instrumentation. K. Section 23 05 93, TESTING, ADJUSTING an

6、d BALANCING FOR HVAC: Requirements for testing, adjusting and balancing of HVAC system. L. Section 23 08 00 COMMISSIONING OF HVAC SYSTEMS: Requirements for commissioning, systems readiness checklists, and training. M. Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS 1.3 QUALITY ASSURANCE A. Refer

7、 to paragraph, GUARANTEE in specification Section 00 72 00, GENERAL CONDITIONS. Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-05-11 23 72 00-2 B. Refer to specification Section 01 00 00, GENERAL REQUIREMENTS for performance tests and instructions t

8、o VA personnel. C. Refer to paragraph QUALITY ASSURANCE in specification Section 23 05 11, COMMON WORK RESULTS FOR HVAC. D. Performance Criteria: Heat recovery equipment shall be provided by a manufacturer who has been manufacturing such equipment and the equipment has a good track record for at lea

9、st 3 years. E. Performance Test: In accordance with PART 3. 1.4 SUBMITTALS A. Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, and SAMPLES. B. Manufacturers Literature and Data: 1. Heat Pipe Heat Exchanger 2. Rotary Heat Exchanger 3. Plate Heat Exchanger 4. Run-Around Energy

10、Recovery System C. Certificate: Submit, simultaneously with shop drawings, an evidence of satisfactory service of the equipment on three similar installations. D. Submit type, size, arrangement and performance details. Present application ratings in the form of tables, charts or curves. E. Provide i

11、nstallation, operating and maintenance instructions, in accordance with Article, INSTRUCTIONS, in Section 01 00 00, GENERAL REQUIREMENTS. F. Completed System Readiness Checklists provided by the Commissioning Agent and completed by the contractor, signed by a qualified technician and dated on the da

12、te of completion, in accordance with the requirements of Section 23 08 00 COMMISSIONING OF HVAC SYSTEMS. 1.5 APPLICABLE PUBLICATIONS A. The publications listed below form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only.

13、 B. Air Conditioning, Heating, and Refrigeration Institute (AHRI) AHRI 1060-2005 . Performance Rating of Air-to-Air Heat Exchangers for Energy Recovery Ventilation Equipment C. American Society of Heating, Refrigeration and Air Conditioning Engineers (ASHRAE): 15-10 Safety Standard for Refrigeration

14、 Systems (ANSI) 52.1-92 Gravimetric and Dust-Spot Procedures for Testing Air-Cleaning Devices Used in General Ventilation for Removing Particulate Matter Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-05-11 23 72 00-3 52.2-07 Method of Testing Gener

15、al Ventilation Air-Cleaning Devices for Removal Efficiency by Particle Size 84-08 Method of Testing Air-to-Air Heat/Energy Exchangers D. American Society for Testing and materials (ASTM) D635-10 Standard Test Method for Rate of Burning and/or Extent and Time of Burning of Plastics in a Horizontal Po

16、sition E84-10 . Standard Test Method for Surface Burning Characteristics of Building Materials E. American Society of Civil Engineers (ASCE) ASCE 7-10 Minimum Design Loads for Buildings and Other Structures F. Underwriters Laboratories, Inc (UL) 1812-2009 Standard for Ducted Heat Recovery Ventilator

17、s 1815-2009 Standard for Nonducted Heat Recovery Ventilators PART 2 - PRODUCTS DESIGNERS NOTE: For high-humidity locations (VA HVAC Design Manual), provide copper tubes and copper fins. See Section 23 82 16, AIR COILS for details 2.1 AIR-TO-AIR HEAT PIPE HEAT EXCHANGERS A. Thermal recovery units sha

18、ll be capable of operating at temperatures ranging from a minimum of -29 degrees C (-20 degrees F) to a maximum of 49 degrees C (120 degrees F). The heat transfer between air streams shall take place in a counterflow arrangement. The unit shall have no moving part and shall be one piece construction

19、. B. Tube core shall be either 18-mm (5/8 inch) or 25-mm (1 inch) OD seamless /aluminum/copper/ tubing permanently expanded into the fins to form a firm, rigid and complete metal pressure contact between the tube and fin collar of all operating conditions. For high-humidity locations, provide copper

20、 tunes and copper fins. C. Fin: /Aluminum/Integral aluminum/copper/ 1. Fin Spacing: /3.2 mm (0.125 inch)/2.3 mm (0.091 inch)/1.8 mm (0.071 inch)/1.7 mm (0.067 inch)/1.4 mm (0.056 inch)/0.2 mm (0.0075 inch)/ 2. Fin and Tube Joint: Mechanical bond and silver brazed. D. Coating: /Thermoplastic vinyl/ep

21、oxy/Synthetic resin/phenolic/Polytetrafluoroethylene/Vinyl ester/ apply to supply and exhaust. Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-05-11 23 72 00-4 E. Secondary surfaces shall be of continuous plate type aluminum fins, 0.18 mm (0.007 inch

22、) thick, and of corrugated design to produce maximum heat transfer efficiencies. F. Basic capillary wick shall be an integral part of the inner wall of the tube and provide a completely wetted surface for maximum heat pipe capacity with minimum heat transfer resistance. G. Refrigerants used shall be

23、 approved by EPA. H. Exhaust and supply airstreams shall be separated from each other by a vertical partition, so that there will be no cross-contamination. 1. Partition Material: /Galvanized steel /Stainless steel/. 2. Partition Material Thickness: 1.7 mm (16-Gauge). I. Casing shall be a minimum of

24、 1.9 mm (14-Gauge) galvanized steel flanged casing, with airtight partition between airstreams. J. End covers shall be a minimum of 1.0 mm (20-Gauge) galvanized steel. K. Tilt-Control Mechanism: For summer-winter operation with an electric actuator; and having control panels and sensing bulbs as sho

25、wn on the drawings. SPEC WRITER NOTE: Show control panels and sensing bulbs on drawings L. Provide flexible connectors for each side of the unit. The flexible connector shall be fabricated in a manner that will allow the unit to tilt without binding. /M. Control: Integral plenum containing heat-pipe

26、 coil and gasketed, face-and-bypass, opposed-blade dampers with rods extended outside casing for damper operator and linkage./ /N. Control: Pivot center of bottom of heat-pipe coil on shaft and bearings to tilt coil. Include tilt controls with electric actuator and linkage, thermostats, sensors, and

27、 polyester fabric with PVC-coated flexible connector for automatic supply temperature regulation, summer/winter changeover, and frost protection./ 2.2 ROTARY AIR-TO-AIR HEAT EXCHANGER: A. Exchanger Rotor or Wheel: Aluminum transfer media with a flame spread rating of 25 and less and smoke developed

28、rating of 50 and less, and independently tested in accordance with ASTM standard E-84. Rotor media shall be independently tested in accordance with ASHRAE Standard 84. It shall allow laminar flow (but not radial) when operating within published operating airflow ranges and prevent leakage, bypassing

29、 and cross contamination by cross flow within wheel. Size the transfer media to allow passage of /300/500/800/1200/ micrometers particles without fouling or clogging. When latent heat transfer is required, treat media with non-degrading /desiccant/silica-gel desiccant Provided by IHSNot for ResaleNo

30、 reproduction or networking permitted without license from IHS-,-,-05-11 23 72 00-5 coating/ that is bacteriostatic, non-corroding and non-toxic. No asbestos material will be allowed. Wheel shall not condense water directly or require a condensate drain for summer or winter operation. Performance ra

31、ting shall be in accordance with AHRI Standard 1060. DESIGNER NOTE: 3 Angstrom (3A) and 4 Angstrom (4A) molecular sieves desiccant coatings provide superior protection to cross contamination. B. Rotor: /Glass-fiber/Polymer/segmented wheel strengthened with radial spokes impregnated with non-migratin

32、g, water-selected, /3A/4A/ molecular-sieve desiccant coating. 1. Maximum Solid Size for media to pass:/500/800/1200/micrometers./ C. Casings shall be sealed on periphery of rotor as well as on duct divider and purge section. Seals shall be adjustable, of extended life materials and effective in limi

33、ting air leakage. D. Wheel shall be supported by ball or roller bearings and belt driven by a fractional horsepower, totally enclosed, NEMA Standard motor through a close coupled positively lubricated speed reducer, or gear/chain speed reduction. Refer to Section 23 05 12, GENERAL MOTOR REQUIREMENTS

34、 FOR HVAC and STEAM GENERATION EQUIPMENT. 1. Motors for constant speed exchanger wheels shall be an AC motor. 2. Variable-speed exchanger wheels shall have exchanger wheel speed and leaving-air temperature controlled by means of a variable-speed motor controller. / The speed shall be controlled as n

35、oted in paragraph G below. /Operation shall be from 115/1/60 and by a proportioning temperature controller which shall vary output voltage of a silicon controlled rectifier (SCR) to a rectified power motor which will change speed in proportion to changes of voltage to its armature./ Automatic change

36、over for summar-winter operations shall be controlled by an adjustable thermoswitch. Set point of adjustable proportioning temperature controller and thermoswitch shall be indicated on visible scale. System shall be capable of speed reduction down to 5 percent of capacity while maintaining adequate

37、torque at any point of operation to rotate wheel. E. An automatic, factory-fabricated, field-adjustable purge unit shall limit exhaust air carry-over to less than 1.0 percent of rated volume. Purge shall be effective when static pressure difference between supply and exhaust is 125 Pa (one-half, inc

38、h wg) or greater, and it shall have provision for restriction or adjustment to limit purge air volume to not over five percent of rated air flow when a static pressure difference up to 2.5 kPa (10 inch wg) exists. Provided by IHSNot for ResaleNo reproduction or networking permitted without license f

39、rom IHS-,-,-05-11 23 72 00-6 F. Unit shall be constructed of heavy gage steel to insure rigidity and stability. Casing side panels shall be removable to insure easy access to internal parts and have integral flanges for flanged duct connection and lifting holes or lugs. G. Controls starting relay sh

40、all be factory mounted and wired, and include a manual motor starter for field wiring. / Variable frequency controller shall be factory mounted and wired, permitting input of field connected 4-20 mA or 1-10-V control signal./ Variable frequency controller shall be factory mounted and wired, with exh

41、aust-air sensor to vary rotor speed and maintain exhaust temperature above freezing /Variable frequency controller shall be factory mounted and wired, with exhaust- and outdoor-air sensors, automatic changeover thermostat and set-point adjuster, to vary rotor speed and maintain/exhaust temperature a

42、bove freezing and/ air differential temperature above set point. When exhaust-air temperature is less than outdoor-air temperature, the rotor shall be at maximum speed. /1. Pilot-Light Indicator: Display rotor rotation and speed. Speed Settings: Adjustable settings for maximum and minimum rotor spee

43、d limits./ H. Filters: MERV 7, 2-inch throw-away type. Refer to Section 23 40 00 HVAC Air Cleaning Devices. 2.3 AIR-TO-AIR PLATE HEAT EXCHANGER A. Comply with UL Standards 1812. B. Plates: Corrugated 0.53 mm (0.021 inch)/ diamond embossed aluminum/stainless steel/polypropylene copolymer (high densit

44、y plastic)/ enthalpic / spacing as recommended by the manufacturer. C. Bedding: Thermosetting reinforced resin. Provide plate seal-off and passage separation at top, bottom and center divider. The resins shall be self-extinguishing type in accordance with ASTM D635. D. Casing and End Strips: Casing

45、of 1.6 mm (16 gage) galvanized steel, except casings for corrosive air streams shall be stainless steel. End strips of the same material as exchanger plates. Ends of unit exchanger plates shall be sealed with high temperature silicon sealant prior to installation of end strip for corrosive air strea

46、ms provide welded end strips to avoid cross contaminations. E. Casings shall have integral flanges for flanged duct connections and shall have lifting holes or lugs. F. Drain Pan: Same material as unit casing. Drain-pan surface shall be covered with molded ABS, and shall have drain connections on ex

47、haust and supply side. Comply with requirements in ASHRAE 62.1-2004. G. Accessories: Furnish where indicated on the drawings. Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-05-11 23 72 00-7 1. Face and Bypass Dampers: Manufacturers standard, complet

48、e with operators, with factory-installed controls to operate face-and-bypass dampers during summer and winter. /2. Defrost System. Factory installed and capable of maintaining at least 85 percent of the non-frosted performance at -29 degrees C (-20 degrees F)./ /H. Water Wash: Automatic system with

49、spray manifold to individual spray tubes or traversing type with stainless-steel-screw operating mechanism and electric motor drive; activated by time clock with detergent injection./ I. Extended-Surface, Disposable Panel Filters: MERV 7, 2-inch throw-away type. Refer to Section 23 40 00 HVAC Air Cleaning Devices. SPEC WRITER NOTE: