1、09-11 28 13 53-1 SECTION 28 13 53 SECURITY ACCESS DETECTION SPECS WRITER NOTE: Delete / _ / if not applicable to project. Also delete any other item or paragraph not applicable in the section and renumber the paragraphs. Insert additional provisions as required for this project. PART 1 GENERAL 1.1 D
2、ESCRIPTION A. Provide and install a complete Detection and Screening System, hereinafter referred to as the Security Access Detection as specified in this section. 1.2 RELATED WORK SPECS WRITER NOTE: Delete any item or paragraph not applicable in the section and renumber the paragraphs. A. Section 0
3、1 00 00 - GENERAL REQUIREMENTS. For General Requirements. B. Section 07 84 00 - FIRESTOPPING. Requirements for firestopping application and use. C. Section 10 14 00 - SIGNAGE. Requirements for labeling and signs. D. Section 28 05 00 - COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY. For gener
4、al requirements that are common to more than one section in Division 28. E. Section 28 05 13 - CONDUCTORS AND CABLES FOR ELECTRONIC SAFETY AND SECURITY. Requirements for conductors and cables. F. Section 28 05 26 - GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY. Requirements for grounding
5、of equipment. G. Section 28 05 28.33 - CONDUITS AND BOXES FOR ELECTRONIC SAFETY AND SECURITY. Requirements for infrastructure. H. Section 28 08 00 - COMMISIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS. For commissioning requirements, systems readiness checklists, and training. I. Section 28 13 00
6、 - PHYSICAL ACCESS CONTROL SYSTEMS (PACS). Requirements for physical access control integration. J. Section 28 13 16 - ACCESS CONTROL SYSTEM AND DATABASE MANAGEMENT. Requirements for control and operation of all security systems. K. Section 28 16 00 - INTRUSION DETECTION SYSTEM. Requirements for ala
7、rm systems. L. Section 28 23 00 - VIDEO SURVEILLANCE. Requirements for security camera systems. Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-09-11 28 13 53-2 M. Section 28 26 00 - ELECTRONIC PERSONAL PROTECTION SYSTEM (EPPS). Requirements for emer
8、gency and interior communications. 1.3 QUALITY ASSURANCE /A. Refer to 28 05 00 COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY, Part 1/ A. The Contractor shall be responsible for providing, installing, and the operation of the Security Access Detection as shown. The Contractor shall also prov
9、ide certification as required. B. The security system shall be installed and tested to ensure all components are fully compatible as a system and can be integrated with all associated security subsystems, whether the security system is stand-alone or a part of a complete Information Technology (IT)
10、computer network. C. The Contractor or security sub-contractor shall be a licensed security Contractor as required within the state or jurisdiction of where the installation work is being conducted. D. Manufacturers Qualifications: The manufacturer shall regularly and presently produce, as one of th
11、e manufacturers principal products, the equipment and material specified for this project, and shall have manufactured the item for at least three years. E. Product Qualification: 1. Manufacturers product shall have been in satisfactory operation, on three installations of similar size and type as t
12、his project, for approximately three years. 2. The Government reserves the right to require the Contractor to submit a list of installations where the products have been in operation before approval. F. Contractor Qualification: 1. The Contractor or security sub-contractor shall be a licensed securi
13、ty Contractor with a minimum of five (5) years experience installing and servicing systems of similar scope and complexity. The Contractor shall be an authorized regional representative of the Security Management Systems (PACS) manufacturer. The Contractor shall provide four (4) current references f
14、rom clients with systems of similar scope and complexity which became operational in the past three (3) years. At least three (3) of the references shall be utilizing the same system components, in a similar configuration as the proposed system. The references must include a current point of Provide
15、d by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-09-11 28 13 53-3 contact, company or agency name, address, telephone number, complete system description, date of completion, and approximate cost of the project. The owner reserves the option to visit the ref
16、erence sites, with the site owners permission and representative, to verify the quality of installation and the references level of satisfaction with the system. The Contractor shall provide copies of system manufacturer certification for all technicians. The Contractor shall only utilize factory-tr
17、ained technicians to install, program, and service the PACS. The Contractor shall only utilize factory-trained technicians to install, terminate and service controller/field panels and reader modules. The technicians shall have a minimum of five (5) continuous years of technical experience in electr
18、onic security systems. The Contractor shall have a local service facility. The facility shall be located within 60 miles of the project site. The local facility shall include sufficient spare parts inventory to support the service requirements associated with this contract. The facility shall also i
19、nclude appropriate diagnostic equipment to perform diagnostic procedures. The COTR reserves the option of surveying the companys facility to verify the service inventory and presence of a local service organization. 2. The Contractor shall provide proof project superintendent with BICSI Certified Co
20、mmercial Installer Level 1, Level 2, or Technician to provide oversight of the project. 3. Cable installer must have on staff a Registered Communication Distribution Designer (RCDD) certified by Building Industry Consulting Service International. The staff member shall provide consistent oversight o
21、f the project cabling throughout design, layout, installation, termination and testing. SPEC WRITER NOTE: In the following paragraph use 4 hours for metropolitan areas and 8 hours for rural areas. G. Service Qualifications: There shall be a permanent service organization maintained or trained by the
22、 manufacturer which will render satisfactory service to this installation within / four / eight / hours of receipt of notification that service is needed. Submit name and address of service organizations. Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,
23、-,-09-11 28 13 53-4 1.4 SUBMITTALS SPECS WRITER NOTE: Delete and/or amend all paragraphs and sub-paragraphs and information as needed to ensure that only the documentation required is requested per the Request for Proposal (RFP). A. Submit below items in conjunction with Master Specification Section
24、s 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES, Section 02 41 00, DEMOLITION, and Section 28 05 00, COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY. B. Provide certificates of compliance with Section 1.3, Quality Assurance. C. Provide a complete and thorough pre-installation and as-buil
25、t design package in both electronic format and on paper, minimum size 48 x 48 inches (in.) (1220 x 1220 millimeters) (mm); drawing submittals shall be per the established project schedule. D. Pre-installation design and as-built packages shall include, but not be limited to: 1. Index Sheet that shal
26、l: a. Clearly define each page of the design package to include facility name, building name, floor, and sheet number. b. Provide a complete list of all security abbreviations and symbols. c. Reference all general notes that are utilized within the design package. d. Specification and scope of work
27、pages for all individual security systems that are applicable to the design package that will: 1) Outline all general and job specific work required within the design package. 2) Provide a detailed device identification table outlining device Identification (ID) and use for all security systems equi
28、pment utilized in the design package. 2. Drawing sheets that will be plotted on the individual floor plans or site plans shall: a. Include a title block as defined above. b. Clearly define the drawings scale in both standard and metric measurements. c. Provide device identification and location. Pro
29、vided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-09-11 28 13 53-5 d. Address all signal and power conduit runs and sizes that are associated with the design of the electronic security system and other security elements. e. Identify all pull box and condu
30、it locations, sizes, and fill capacities. f. Address all general and drawing specific notes for a particular drawing sheet. 3. A detailed riser drawing for each applicable security subsystem shall: a. Indicate the sequence of operation. b. Relationship of integrated components on one (1) diagram. c.
31、 Include the number, size, identification, and maximum lengths of interconnecting wires. d. Wire/cable types shall be defined by a wire and cable schedule. The schedule shall utilize a lettering system that will correspond to the wire/cable it represents (example: A = 18 AWG/1 Pair Twisted, Unshield
32、ed). This schedule shall also provide the manufacturers name and part number for the wire/cable being installed. 4. A detailed system drawing for each applicable security system shall: a. Clearly identify how all equipment within the system, from main panel to device, shall be laid out and connected
33、. b. Provide full detail of all system components wiring from point-to-point. c. Identify wire types utilized for connection, interconnection with associate security subsystems. d. Show device locations that correspond to the floor plans. e. All general and drawing specific notes shall be included w
34、ith the system drawings. 5. A detailed schedule for all of the applicable security subsystems shall be included. All schedules shall provide the following information: a. Device ID. b. Device Location (e.g. site, building, floor, room number, location, and description). c. Mounting type (e.g. flush,
35、 wall, surface, etc.). d. Power supply or circuit breaker and power panel number. Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-09-11 28 13 53-6 e. In addition, provide the Security Access Detection detector or screening device ID, type (e.g. walk-
36、through screener, X-ray, explosive detector, etc.), type of technology used by system for detection and model number. 6. Provide detail and elevation drawings for all devices that define how they were installed and mounted. E. The pre-installation design packages shall go through a full review proce
37、ss conducted by the Contractor along with a VA representative to ensure all work has been clearly defined and completed. All reviews shall be conducted in accordance with the project schedule. There shall be four (4) stages to the review process: 1. 35 percent 2. 65 percent 3. 90 percent 4. 100 perc
38、ent F. The Contractor shall provide manufacturer security system product cut-sheets that clearly and completely indicate the description and function of each component of the security systems they are associated with. Also, indicate all termination points of devices and interconnections required for
39、 operation of the system, and between modules and devices. G. The Contractor shall submit for approval at least 30 days prior to commencement of formal testing, a Security System Operational Test Plan. Include detailed procedures for operational testing of each component and security subsystem, to i
40、nclude performance of an integrated system test. H. The Contractor shall submit manufactures certification of Underwriters Laboratories, Inc. (UL) listing for all security system devices, power sources, control panels, and monitoring equipment. I. The Contractor shall provide complete maintenance an
41、d operating manuals from the manufacturer that support as-builts and system design, to include all technical product sheets and overall system schematics. Two (2) weeks prior to the final inspection, four (4) copies of the maintenance and operating manuals also need to be submitted to the RE. J. Cer
42、tifications: Two (2) weeks prior to final inspection, submit four (4) copies of the following to the RE: Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-09-11 28 13 53-7 1. Complete maintenance and operating manuals from the manufacturer that support
43、 as-built and systems design, to include all technical data sheets and overall system schematics. 2. Certification by the Contractor that the materials submitted is in accordance with the drawings and specifications. 3. Certification by the Contractor that a complete security system installation has
44、 been installed, tested and adjusted. K. Completed System Readiness Checklists provided by the Commissioning Agent and completed by the contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 28 08 00 COMMISSIONING OF ELECTRONI
45、C SAFETY AND SECURITY SYSTEMS. 1.5 APPLICABLE PUBLICATIONS A. The publications listed below (including amendments, addenda, revisions, supplement, and errata) form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only. B. Ame
46、rican Society for Testing and Materials (ASTM) C1238-97 (R03) . Standard Guide for Installation of Walk-Through Metal Detectors C. Department of Justice American Disability Act (ADA) 28 CFR Part 36-94 ADA Standards for Accessible Design D. Department of Veterans Affairs VHA National CAD Standard App
47、lication Guide, 2006 VA BIM Guide, V1.0 10 E. Federal Communications Commision (FCC): (47 CFR 15) Part 15 Limitations on the Use of Wireless Equipment/Systems F. Government Accountability Office (GAO): GAO-03-8-02 Security Responsibilities for Federally Owned and Leased Facilities G. Institute of El
48、ectrical and Electronics Engineers (IEEE): C95.1-05 . Standards for Safety Levels with Respect to Human Exposure in Radio Frequency Electromagnetic Fields H. National Fire Protection Association (NFPA): 70-11 Article 780-National Electrical Code I. National Institute of Justice (NIJ) Provided by IHS
49、Not for ResaleNo reproduction or networking permitted without license from IHS-,-,-09-11 28 13 53-8 0601.02-03 . Standards for Walk-Through Metal Detectors for use in Weapons Detection 0602.02-03 . Hand-Held Metal Detectors for Use in Concealed Weapon and Contraband Detection J. National Electrical Manufactures Association (NEMA) 250-08 . Enclosures for