1、Pipeline Control Room ManagementAPI RECOMMENDED PRACTICE 1168 SECOND EDITION, FEBRUARY 2015Special NotesAPI publications necessarily address problems of a general nature. With respect to particular circumstances, local, state, and federal laws and regulations should be reviewed.Neither API nor any o
2、f APIs employees, subcontractors, consultants, committees, or other assignees make any warranty or representation, either express or implied, with respect to the accuracy, completeness, or usefulness of the information contained herein, or assume any liability or responsibility for any use, or the r
3、esults of such use, of any information or process disclosed in this publication. Neither API nor any of APIs employees, subcontractors, consultants, or other assignees represent that use of this publication would not infringe upon privately owned rights.API publications may be used by anyone desirin
4、g to do so. Every effort has been made by the Institute to assure the accuracy and reliability of the data contained in them; however, the Institute makes no representation, warranty, or guarantee in connection with this publication and hereby expressly disclaims any liability or responsibility for
5、loss or damage resulting from its use or for the violation of any authorities having jurisdiction with which this publication may conflict.API publications are published to facilitate the broad availability of proven, sound engineering and operating practices. These publications are not intended to
6、obviate the need for applying sound engineering judgment regarding when and where these publications should be utilized. The formulation and publication of API publications is not intended in any way to inhibit anyone from using any other practices.Any manufacturer marking equipment or materials in
7、conformance with the marking requirements of an API standard is solely responsible for complying with all the applicable requirements of that standard. API does not represent, warrant, or guarantee that such products do in fact conform to the applicable API standard.Users of this Recommended Practic
8、e should not rely exclusively on the information contained in this document. Sound business, scientific, engineering, and safety judgment should be used in employing the information contained herein. All rights reserved. No part of this work may be reproduced, translated, stored in a retrieval syste
9、m, or transmitted by any means, electronic, mechanical, photocopying, recording, or otherwise, without prior written permission from the publisher. Contact the Publisher, API Publishing Services, 1220 L Street, NW, Washington, DC 20005.Copyright 2015 American Petroleum InstituteForewordNothing conta
10、ined in any API publication is to be construed as granting any right, by implication or otherwise, for the manufacture, sale, or use of any method, apparatus, or product covered by letters patent. Neither should anything contained in the publication be construed as insuring anyone against liability
11、for infringement of letters patent.Shall: As used in a standard, “shall” denotes a minimum requirement in order to conform to the specification.Should: As used in a standard, “should” denotes a recommendation or that which is advised but not required in order to conform to the specification. This do
12、cument was produced under API standardization procedures that ensure appropriate notification and participation in the developmental process and is designated as an API standard. Questions concerning the interpretation of the content of this publication or comments and questions concerning the proce
13、dures under which this publication was developed should be directed in writing to the Director of Standards, American Petroleum Institute, 1220 L Street, NW, Washington, DC 20005. Requests for permission to reproduce or translate all or any part of the material published herein should also be addres
14、sed to the director.Generally, API standards are reviewed and revised, reaffirmed, or withdrawn at least every five years. A one-time extension of up to two years may be added to this review cycle. Status of the publication can be ascertained from the API Standards Department, telephone (202) 682-80
15、00. A catalog of API publications and materials is published annually by API, 1220 L Street, NW, Washington, DC 20005.Suggested revisions are invited and should be submitted to the Standards Department, API, 1220 L Street, NW, Washington, DC 20005, standardsapi.org.iiiContentsPage1 Scope . . . . . .
16、 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11.1 Purpose. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
17、 . . . . . . . . . . . . . 11.2 General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12 Normative References. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
18、 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13 Terms, Definitions, and Abbreviations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13.1 Definitions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
19、 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13.2 Abbreviations. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34 Personnel Roles, Authorities, and Respon
20、sibilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34.1 General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34.2 Pipeline Controller A
21、uthorities and Associated Responsibilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34.3 Interfacing with the Public . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 54.4 Non-Controller Operatio
22、ns Authorities and Associated Responsibilities . . . . . . . . . . . . . . . . . . . . . . . . . . 55 Guidelines for Shift Turnover . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 65.1 General . . . . . . . . . . . . . . . .
23、 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 65.2 Shift Turnover Process . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 65.3 Sh
24、ift Turnover Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 65.4 Shift Turnover Information Exchange . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
25、. . . 75.5 Information to Exchange . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 76 Provide Adequate information. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
26、. . . . . . . . . . 106.1 General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 106.2 Supervisory Control and Data Acquisition (SCADA) System . . . . . . . . . . . . . . . . . . . . . .
27、. . . . . . . . . . . . . 106.3 Point-to-Point Verification . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 106.4 Internal Communication . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
28、 . . . . . . . . . . . . . . . . . . . . . . . . 116.5 Testing Backup SCADA Systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 117 Fatigue Management . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
29、 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 127.1 General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 127.2 Work Schedule. . . . . . . . . . . . . . . . . . . . . . . .
30、. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 127.3 On-shift Breaks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 137.4 On-shift Stimulation . . .
31、 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 137.5 Education . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
32、 . . 137.6 Pipeline Control Room Environment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 137.7 Exercise Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
33、. . . . . . . . . 137.8 Fatigue-mitigation Room . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 137.9 Hotel/Sleep Facilities. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
34、. . . . . . . . . . . . . . . . . . . . . . 137.10 Transportation Service . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 138 Change Management . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
35、. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 148.1 General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 148.2 Inclusion of Pipeline Control Room Representative . .
36、. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 148.3 Systems/Processes Undergoing Change. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 148.4 Notification and Training . . . . . . . . . . . . . . . . . . . . .
37、 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 148.5 Emergency Change Management . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14vContentsPage9 Operating Experience . . . . . . . . . . . .
38、 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1510 Training. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1610.1 General .
39、 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1610.2 Roles and Responsibilities. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
40、. . . . . . . . . . 1610.3 Shift Turnover. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1610.4 Fatigue Mitigation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
41、 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1610.5 Alarm Management . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1710.6 Change Management . . . . . . . . . . . . . . . . . . . . . . . . . .
42、. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1710.7 Operating Experience . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1710.8 Team Training. . . . . . . . . . . . . . . .
43、. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1710.9 Other Training . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1811 Workloa
44、d of Pipeline Controllers. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18Bibliography . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
45、. . . . . . . . . 191Pipeline Control Room Management1 Scope1.1 PurposeThe purpose of this recommended practice is to provide pipeline operators, and pipeline Controllers with guidance on industry best practices on control room management to consider when developing or enhancing processes, procedure
46、s, and training. This document was written for operators with continuous and non-continuous operations, as applicable.1.2 GeneralThis document addresses pipeline safety elements in Pipeline Control Rooms for hazardous liquid and natural gas pipelines in both the transportation and distribution secto
47、rs: personnel roles, authorities, and responsibilities; guidelines for shift turnover; provide adequate information; fatigue mitigation; change management; training; operating experience; and workload of pipeline Controllers.2 Normative ReferencesThis document contains no normative references. A lis
48、t of documents associated with API RP 1168 is included in the bibliography.3 Terms, Definitions, and Abbreviations3.1 DefinitionsFor the purposes of this document, the following definitions apply.3.1.1 abnormal operating conditionAOCA condition identified by the operator that may indicate a malfunct
49、ion of a component or deviation from normal operations that may: a) indicate a condition exceeding design limits; and/orb) result in a hazard(s) to persons, property, or the environment.2 API RECOMMENDED PRACTICE 11683.1.2 abnormal operationAONon-emergency operation while exceeding normal operating design limits, typically caused by an AOC such as: a) unintended closure of valves or shutdowns;b) increase or decrease of pressure or flow rate outside of normal operating limits;c) loss of communications;d) operation of any safety device; ande) any other malfunction of a component,