1、Designation: C1037 08 (Reapproved 2015)Standard Practice forInspection of Underground Precast Concrete UtilityStructures1This standard is issued under the fixed designation C1037; the number immediately following the designation indicates the year oforiginal adoption or, in the case of revision, the
2、 year of last revision. A number in parentheses indicates the year of last reapproval. Asuperscript epsilon () indicates an editorial change since the last revision or reapproval.1. Scope1.1 This practice covers the inspection of undergroundprecast concrete utility structures designed and manufactur
3、edin accordance with Practice C857 and Specification C858.1.2 This standard does not purport to address all of thesafety concerns, if any, associated with its use. It is theresponsibility of the user of this standard to establish appro-priate safety and health practices and determine the applica-bil
4、ity of regulatory limitations prior to use.2. Referenced Documents2.1 ASTM Standards:2C31/C31M Practice for Making and Curing Concrete TestSpecimens in the FieldC39/C39M Test Method for Compressive Strength of Cylin-drical Concrete SpecimensC857 Practice for Minimum Structural Design Loading forUnde
5、rground Precast Concrete Utility StructuresC858 Specification for Underground Precast Concrete Util-ity Structures3. Terminology3.1 Description of Term Specific to This Standard:3.2 inspectoras used in this practice, an individual as-signed by the manufacturer or by the purchaser to perform aninspec
6、tion.4. Manufacturers Responsibility4.1 The manufacturer shall develop and use an effectivequality control program that shall include material controls,tests, and inspections as agreed upon between manufacturerand purchaser throughout the fabrication process.4.2 The manufacturers inspection records
7、and associatedtest data shall be made available to the inspector.4.3 The manufacturer shall notify the inspector of anychanges in material, method of fabrication, or quality controlprocedure.4.4 The manufacturer shall designate an individual as liai-son to the inspector. He will sign the inspection
8、activity reports,and when necessary, will be available to the inspector todiscuss matters pertaining to inspection, fabrication, and qual-ity control.4.5 The manufacturer shall prepare sufficient concrete testcylinders to meet the purchasers requirements for compressivestrength. Test cylinders shall
9、 be prepared in accordance withPractice C31/C31M and tested in accordance with Test MethodC39/C39M. Results shall be entered in an inspection activityreport.4.6 The manufacturer, upon request, shall assemble (withoutgrout) selected concrete component sections to form a com-plete structure assembly t
10、o determine that fit-up requirementsare as specified.4.7 The manufacturer shall provide marking according topurchaser requirements or according to Specification C858.5. Inspectors Responsibility5.1 The inspector shall familiarize himself with the manu-facturers quality control program.5.2 The inspec
11、tor shall determine that the fabrication of theprecast units complies with drawings approved by thepurchaser, including hardware and general requirements.5.3 The inspector shall immediately report to the purchaserand manufacturer any component parts, complete structures,etc., not in compliance.5.4 T
12、he inspector shall clearly indicate on the inspectionactivity report any fabrication problems encountered andsolutions utilized.6. Inspection Procedure6.1 The inspector shall inspect forms, materials, and fabri-cated parts used in the product.1This practice is under the jurisdiction of ASTM Committe
13、e C27 on PrecastConcrete Products and is the direct responsibility of Subcommittee C27.10 onUtility Structures.Current edition approved Nov. 1, 2015. Published November 2015. Originallyapproved in 1985. Last previous edition approved in 2008 as C1037 08. DOI:10.1520/C1037-08R15.2For referenced ASTM
14、standards, visit the ASTM website, www.astm.org, orcontact ASTM Customer Service at serviceastm.org. For Annual Book of ASTMStandards volume information, refer to the standards Document Summary page onthe ASTM website.Copyright ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocke
15、n, PA 19428-2959. United States16.2 During each inspection, the inspector shall examinecomplete units for all specified features that can be determinedby visual observation.6.3 The first section of each type of precast structure fromany set of forms shall be assembled by the manufacturerwithout grou
16、t and the inspector shall check that fit-up require-ments are as specified.6.4 The inspector shall check that all materials conform torequirements of Specification C858.7. Fabrication Inspection7.1 Reinforcing Steel:7.1.1 The inspector shall check all reinforcing steel todetermine that it has been c
17、overed by mill reports, with data inreports conforming to designated standard, and has not beendamaged. Material with kinks or bends not indicated onfabrication drawings shall not be used. Heating to bendmaterial is not permitted.7.1.2 All reinforcing steel shall be free of form releasecoatings and
18、loose rust as specified in Specification C858,although a light film of red rust is not objectionable.7.1.3 Reinforcing steel shall be checked for size, spacing,proper bends, and lengths in accordance with the drawings.7.2 Assembled Reinforcing Inspection:7.2.1 All material shall be properly spliced
19、and locatedaccording to the drawings.7.2.2 Reinforcing steel shall be secured in such a mannerthat shifting will not occur during handling of the cage orplacing of concrete. All chairs, bolsters, braces, and spacers incontact with form and reinforcing rod shall be of material thatwill not deteriorat
20、e. The cage shall be properly positioned inthe form to provide the specified concrete cover over the steel.7.2.3 The inspector shall check electrical ground connec-tions or any other special items as specified.7.3 Hardware Inspection:7.3.1 Hardware shall be inspected to ensure compliancewith purchas
21、ers specifications.7.3.2 Hardware shall be placed and securely fastened atdesignated locations to prevent shifting or movement duringconcrete placing.7.3.3 Hardware and other embedded items shall be free ofform release coatings.7.3.4 Threaded inserts and duct terminators shall be free ofconcrete and
22、 other foreign matter.7.4 Concrete Inspection:7.4.1 Concrete shall be placed to prevent segregation, voidsor honeycombed areas. Placing of concrete shall be observed toensure that it is being placed properly in accordance withapplicable standards.7.4.2 The inspector shall observe condition of concre
23、te afterthe forms are removed. Surfaces shall be sound. Patching andfinishing shall be permitted to remove minor honeycomb.Chips, voids, and through cracks shall be repaired by anacceptable method in accordance with Specification C858.Extensive voids, chips, through cracks, or deep honeycombshall be
24、 referred to the design engineer or purchasers engineerfor method of repair or acceptability.7.4.3 The inspector shall observe that specified curing isprovided.7.5 Dimensions InspectionThe inspector shall measure foroverall dimensions (that is, length, width, height, wallthickness, and squareness, e
25、tc.) the first concrete section ofeach type produced from each form. The tolerances shallcomply to the finished product in accordance to SpecificationC858.8. Tests8.1 The inspector shall check results of slump tests, ifspecified, for compliance to specifications.8.2 The inspector shall review compre
26、ssive strength data onproduct covered. If not to specified strength, the inspector shallhave concrete tested by method and manner agreed uponbetween the manufacturer and purchaser.9. Nonconforming Material9.1 Material found not to be in conformance with Specifi-cation C858 shall be rejected unless a
27、cceptance is authorized.10. Evidence of Inspection and Reporting10.1 Inspection documents, etc., shall be in accordance withthe specifications.10.2 Inspection records on products completed and shippedbetween inspections need only be prepared at the purchasersrequest.11. Keywords11.1 inspection; insp
28、ector; precast concrete; utility struc-ture; utility vaultASTM International takes no position respecting the validity of any patent rights asserted in connection with any item mentionedin this standard. Users of this standard are expressly advised that determination of the validity of any such pate
29、nt rights, and the riskof infringement of such rights, are entirely their own responsibility.This standard is subject to revision at any time by the responsible technical committee and must be reviewed every five years andif not revised, either reapproved or withdrawn. Your comments are invited eith
30、er for revision of this standard or for additional standardsand should be addressed to ASTM International Headquarters. Your comments will receive careful consideration at a meeting of theresponsible technical committee, which you may attend. If you feel that your comments have not received a fair h
31、earing you shouldmake your views known to the ASTM Committee on Standards, at the address shown below.This standard is copyrighted by ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959,United States. Individual reprints (single or multiple copies) of this standa
32、rd may be obtained by contacting ASTM at the aboveaddress or at 610-832-9585 (phone), 610-832-9555 (fax), or serviceastm.org (e-mail); or through the ASTM website(www.astm.org). Permission rights to photocopy the standard may also be secured from the Copyright Clearance Center, 222Rosewood Drive, Danvers, MA 01923, Tel: (978) 646-2600; http:/ 08 (2015)2