1、Designation: C1479M 12C1479M 13Standard Practice forInstallation of Precast Concrete Sewer, Storm Drain, andCulvert Pipe Using Standard Installations (Metric)1This standard is issued under the fixed designation C1479M; the number immediately following the designation indicates the year oforiginal ad
2、option or, in the case of revision, the year of last revision. A number in parentheses indicates the year of last reapproval. Asuperscript epsilon () indicates an editorial change since the last revision or reapproval.1. Scope1.1 This practice covers the installation of precast concrete pipe intende
3、d to be used for the conveyance of sewage, industrialwastes, and storm water, and for the construction of culverts.1.2 This practice is the SI companion to Practice C1479.1.3 This standard does not purport to address all of the safety concerns, if any, associated with its use. It is the responsibili
4、tyof the user of this standard to establish appropriate safety and health practices and determine the applicability of regulatorylimitations prior to use.2. Referenced Documents2.1 ASTM Standards:2C822 Terminology Relating to Concrete Pipe and Related ProductsC1417 Specification for Manufacture of R
5、einforced Concrete Sewer, Storm Drain, and Culvert Pipe for Direct DesignD698 Test Methods for Laboratory Compaction Characteristics of Soil Using Standard Effort (12 400 ft-lbf/ft3 (600 kN-m/m3)D1557 Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf
6、/ft3 (2,700kN-m/m3)D2487 Practice for Classification of Soils for Engineering Purposes (Unified Soil Classification System)D2488 Practice for Description and Identification of Soils (Visual-Manual Procedure)IEEE/ASTM SI 10 Standard for Use of the International System of Units (SI): The Modern Metric
7、 System2.2 AASHTO Standards:3Standard Specifications for Highway BridgesM 145 Classification of Soils and SoilAggregate Mixtures for Highway Construction PurposesT 99 The Moisture-Density Relations of Soils Using a 5.5-lb (2.5-kg) Rammer and a 12-in. (305-mm) DropT 180 The Moisture-Density Relations
8、 of Soils Using a 10-lb (4.54-kg) Rammer and an 18-in. (457-mm) DropT 310 In-Place Density and Moisture Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth)2.3 ASCE Standard:4ASCE 15 Standard Practice for the Direct Design of Buried Precast Reinforced Concrete Pipe Using Standard In
9、stallations(SIDD)3. Terminology3.1 For definitions of terms relating to concrete pipe, see Terminology C822.3.2 For terminology related to soil classifications, see Practices D2487 and D2488.3.3 For terminology and definitions of terms relating to structural design, see ASCE 15.3.4 Fig. 1 illustrate
10、s the definitions and limits of the terms: foundation, subgrade, bedding, outer bedding, middle bedding,haunch, lower side, backfill or overfill, invert, crown, springline, top of pipe, and bottom of pipe as used in this practice.1 This practice is under the jurisdiction of ASTM Committee C13 on Con
11、crete Pipe and is the direct responsibility of Subcommittee C13.05 on Special Projects.Current edition approved Sept. 1, 2012Feb. 1, 2013. Published October 2012February 2013. Originally approved in 2007. Last previous edition approved in 20102012as C1479M 10.C1479M 12. DOI: 10.1520/C1479M-12.10.152
12、0/C1479M-13.2 For referencedASTM standards, visit theASTM website, www.astm.org, or contactASTM Customer Service at serviceastm.org. For Annual Book of ASTM Standardsvolume information, refer to the standards Document Summary page on the ASTM website.3 Available from American Association of State Hi
13、ghway and Transportation Officials (AASHTO), 444 N. Capitol St., NW, Suite 249, Washington, DC 20001,http:/www.transportation.org.4 Available from American Society of Civil Engineers (ASCE), 1801 Alexander Bell Dr., Reston, VA 20191, http:/www.asce.org.This document is not an ASTM standard and is in
14、tended only to provide the user of an ASTM standard an indication of what changes have been made to the previous version. Becauseit may not be technically possible to adequately depict all changes accurately, ASTM recommends that users consult prior editions as appropriate. In all cases only the cur
15、rent versionof the standard as published by ASTM is to be considered the official document.Copyright ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959. United States14. Significance and Use4.1 This practice is useful as a reference by an owner and the owners en
16、gineer in preparing project specifications.5. NotationsDi = inside diameter of pipe, mmDo = outside diameter of pipe, mmH = design height of earth above top of pipe, mw = unit weight of soil, N/m36. Standard Installations6.1 The precast concrete pipe/soil system shall be constructed to conform to th
17、e requirements of Figs. 2 and 3 and Tables 1 and2 as designated on the plans.7. Excavation7.1 When rock or other unyielding foundation material is encountered, it shall be removed at least to the requirements shownin Figs. 2 and 3 and Tables 1 and 2. Overexcavated areas shall be backfilled with appr
18、oved materials and compacted to at leastthe standard proctor density specified for the bedding.7.2 Where surface water or groundwater conditions exist, the site and trench shall be dewatered.FIG. 1 Pipe/Installation TerminologyC1479M 1328. Foundation8.1 The foundation shall be moderately firm to har
19、d in situ soil, stabilized soil, or compacted fill material.8.2 When unsuitable or unstable material is encountered, the foundation shall be stabilized.8.3 Methods to prevent migration of soil fines shall be provided when groundwater or existing soil conditions are conduciveto particle migration. Gr
20、avelly soils, with little or no fines, could migrate under certain conditions, causing lack of support.8.4 Pipe installed over an unyielding foundation shall be cushioned so as to prevent blasting shock when future blasting isanticipated in the area.9. Bedding9.1 The bedding shall be constructed uni
21、formly over the full length of the pipe barrel, as required for the designated standardinstallation, to distribute the load-bearing reaction uniformly on the pipe barrel over its full length, and to maintain the requiredpipe grade. See Fig. 4. If placed in layers, the thickness of the layers shall b
22、e as required to achieve the specified compaction andas required by the project specifications.9.2 The bedding layers for standard installation Types 1, 2, and 3 shall be placed to be as uniform as possible, but shall beloosely placed uncompacted material under the middle third of the pipe prior to
23、placement of the pipe.9.3 The maximum aggregate size shall be 25 mm when the bedding thickness is less than 150 mm and 38 mm when the beddingthickness is 150 mm or greater, except as noted in 9.4.9.4 When in situ soils conforming to project specifications are used in constructing the outer bedding f
24、or Type 3 and 4installations, the maximum aggregate size shall not be greater than 75 mm, or half the bedding thickness, whichever is less.9.5 The use of aggregate sizes larger than 25 mm shall be limited to 20 % of the bedding material by weight.9.6 Bell holes shall be excavated in the bedding or f
25、oundation, or both, when installing pipe with expanded bells so that the pipeis supported by the barrel and not by the bells. See Fig. 4.9.7 Any outer bedding under the lower side areas shall be compacted to at least the same requirements as for the lower sideareas.FIG. 2 Standard Embankment Install
26、ationsC1479M 13310. Pipe Placement and Joining10.1 Pipe shall be installed to the line and grade shown on the project plans and specifications. The joint shall be as specifiedin the project specifications and shall be installed in accordance with the pipe manufacturers recommendations.NOTE 1(Advisor
27、y) Where practical, work should be started at the lowest end of the pipeline and the pipe laid with the bell end upgrade.10.2 If required, the top of the pipe section being laid shall be positioned to the correct rotational orientation and then joined.10.3 The bedding grade under the middle third of
28、 the pipe outside diameter shall be prepared before laying the pipe section.Making adjustments in grade by exerting force on the barrel of the pipe with excavating equipment, by lifting and dropping thepipe, or by lifting the pipe and packing bedding material under it shall be prohibited. If the ins
29、talled pipe section is not on grade,the pipe section shall be completely unjoined, the grade corrected, and the pipe then rejoined.11. Haunch11.1 The haunch shall be constructed using the specified soil type and the minimum compaction level required for thedesignated standard installation. It shall
30、be placed and compacted uniformly for the full length of the pipe barrel so as to distributethe load-bearing reaction uniformly to the bedding over the full length of the pipe barrel. If placed in layers, the thickness of thelayers shall be as required to achieve the specified compaction and as requ
31、ired by the project specifications.11.2 The maximum aggregate size for the haunch shall be the same as the maximum aggregate size in the bedding as definedin 9.3, except as noted in 11.3.11.3 When in situ soils conforming to project specifications are used in constructing the pipe haunches for Type
32、3 and 4installations, the maximum aggregate size shall not be greater than 75 mm.11.4 The use of aggregate sizes larger than 25 mm shall be limited to 20 % of the haunch material by weight.11.5 Placed soil shall be deposited and compacted to the specified density uniformly on each side of the pipe t
33、o prevent lateraldisplacement of the pipe.NOTE 1Clearance between pipe and trench wall shall be adequate to enable specified compaction but not less than Do/6.FIG. 3 Standard Trench InstallationsC1479M 13412. Lower Side12.1 The lower side, if not in situ, shall be constructed using the specified soi
34、l type and the minimum compaction level requiredfor the designated standard installation. If placed in layers, the thickness of the layers shall be as required to achieve the specifiedcompaction and as required by the project specifications.12.2 The soil, if not in situ, shall be material conforming
35、 to the project specifications, and contain no debris, organic matter,frozen material, or large stones with a diameter greater than one half the thickness of the compacted layers being placed.12.3 Placed soil shall be deposited and compacted to the specified density uniformly on each side of the pip
36、e to prevent lateraldisplacement of the pipe.13. Overfill13.1 Overfill shall be constructed as specified in the project specifications. If placed in layers, the thickness of the layers shallbe as required to achieve the specified compaction and as required by the project specifications.TABLE 1 Stand
37、ard Embankment Installation Soils and Minimum Compaction RequirementsNOTE 1Compaction and soil symbols (that is, 95 % Category I), refer to a soil material category with a minimum standard proctor density. See Table3 for equivalent modified proctor values and soil types.NOTE 2Type 1 installations re
38、quire greater soil stiffness from the surrounding soils than the Type 2, 3, and 4 installations. Proper field verificationof soil properties and compaction levels must be performed to ensure compliance with the design requirements. See Appendix X2 for more informationand guidance.NOTE 3For Type 1 in
39、stallation, crushed rock is not an appropriate material for bedding under the pipe. An uncompacted, non-crushed material mustbe used under the middle third of the pipe outside diameter. While crushed rock meeting the requirements of this specification may self compact vertically,it will not flow lat
40、erally to provide support for the haunches of the pipe. To achieve a 90 to 95 % compaction with crushed rock, work material underthe haunch and compact it to achieve the specified density. Otherwise, the specified installation is not achieved.NOTE 4Soil in the outer bedding, haunch, and lower side z
41、ones, except within Do/3 from the pipe springline, shall be compacted to at least the samecompaction as the majority of soil in the overfill zone.NOTE 5Required bedding thickness is the thickness of the bedding prior to placement of the pipe.NOTE 6A subtrench is defined as a trench with its top belo
42、w finished grade by more than 0.1H or, for roadways, its top is at an elevation lower than0.3 m below the bottom of the pavement base material.The minimum width of a subtrench shall be 1.33 Do, or wider, if required for adequate space to attain the specified compaction in the haunch and beddingzones
43、.For subtrenches, except within Do/3 from the springline, any portion of the lower side zone in the subtrench wall shall be at least as firm as an equivalentsoil placed to the compaction requirements specified for the lower side zone and as firm as the majority of soil in the overfill zone, or it sh
44、all be removedand replaced with soil compacted to the specified level.NOTE 7“Dumped” material without additional compactive effort will not provide the design haunch support required for Type 1 and 2 installationsand it should be checked for Type 3 installations.InstallationTypeBeddingThicknessHaunc
45、h andOuter Bedding Lower SideType 1 Do/24 minimum;not less than 75 mmIf rock foundation,use Do/12 minimum;not less than 150 mm95 % Category I 90 % Category I,95 % Category II, or100 % Category IIIType 1 Do/24 minimum;not less than 75 mmIf rock foundation,use Do/12 minimum;not less than 150 mm95 % Ca
46、tegory I 90 % Category I,95 % Category IIType 2 Do/24 minimum;not less than 75 mmIf rock foundation,use Do/12 minimum;not less than 150 mm90 % Category I or95 % Category II85 % Category I,90 % Category II, or95 % Category IIIType 3 Do/24 minimum;not less than 75 mmIf rock foundation,use Do/12 minimu
47、m;not less than 150 mm85 % Category I,90 % Category II, or95 % Category III85 % Category I,90 % Category II, or95 % Category IIIType 4 No bedding required,except if rockfoundation, useDo/12 minimum;not less than 150 mmNo compactionrequired, exceptif Category III, use85 % Category IIINo compactionreq
48、uired, exceptif Category III, use85 % Category IIIC1479M 13513.2 The soil shall be material conforming to the project specifications, and contain no debris, organic matter, frozen material,or large stones with a diameter greater than one half the thickness of the compacted layers being placed.TABLE
49、2 Standard Trench Installation Soils and Minimum Compaction RequirementsNOTE 1Compaction and soil symbols (that is, 95 % Category I), refer to a soil material category with a minimum standard proctor density. See Table3 for equivalent modified proctor values and soil types.NOTE 2Type 1 installations require greater soil stiffness from the surrounding soils than the Type 2, 3, and 4 installations. Proper field verificationof soil properties and compaction levels must be performed to ensure compliance with the design requirements. See Appendix X2 for more i