ASTM E1369-2007e1 Standard Guide for Selecting Techniques for Treating Uncertainty and Risk in the Economic Evaluation of Buildings and Building Systems《建筑物和建筑系统经济评估中处理不确定性和风险的选择技术.pdf

上传人:周芸 文档编号:528564 上传时间:2018-12-05 格式:PDF 页数:15 大小:190.69KB
下载 相关 举报
ASTM E1369-2007e1 Standard Guide for Selecting Techniques for Treating Uncertainty and Risk in the Economic Evaluation of Buildings and Building Systems《建筑物和建筑系统经济评估中处理不确定性和风险的选择技术.pdf_第1页
第1页 / 共15页
ASTM E1369-2007e1 Standard Guide for Selecting Techniques for Treating Uncertainty and Risk in the Economic Evaluation of Buildings and Building Systems《建筑物和建筑系统经济评估中处理不确定性和风险的选择技术.pdf_第2页
第2页 / 共15页
ASTM E1369-2007e1 Standard Guide for Selecting Techniques for Treating Uncertainty and Risk in the Economic Evaluation of Buildings and Building Systems《建筑物和建筑系统经济评估中处理不确定性和风险的选择技术.pdf_第3页
第3页 / 共15页
ASTM E1369-2007e1 Standard Guide for Selecting Techniques for Treating Uncertainty and Risk in the Economic Evaluation of Buildings and Building Systems《建筑物和建筑系统经济评估中处理不确定性和风险的选择技术.pdf_第4页
第4页 / 共15页
ASTM E1369-2007e1 Standard Guide for Selecting Techniques for Treating Uncertainty and Risk in the Economic Evaluation of Buildings and Building Systems《建筑物和建筑系统经济评估中处理不确定性和风险的选择技术.pdf_第5页
第5页 / 共15页
亲,该文档总共15页,到这儿已超出免费预览范围,如果喜欢就下载吧!
资源描述

1、Designation: E 1369 07e1Standard Guide forSelecting Techniques for Treating Uncertainty and Risk inthe Economic Evaluation of Buildings and BuildingSystems1This standard is issued under the fixed designation E 1369; the number immediately following the designation indicates the year oforiginal adopt

2、ion or, in the case of revision, the year of last revision. A number in parentheses indicates the year of last reapproval. Asuperscript epsilon (e) indicates an editorial change since the last revision or reapproval.e1NOTEFootnotes updated editorially in August 2007.1. Scope1.1 This guide covers tec

3、hniques for treating uncertainty ininput values to an economic analysis of a building investmentproject. It also recommends techniques for evaluating the riskthat a project will have a less favorable economic outcome thanwhat is desired or expected.21.2 The techniques include breakeven analysis, sen

4、sitivityanalysis, risk-adjusted discounting, the mean-variance criterionand coefficient of variation, decision analysis, and simulation.1.3 The techniques can be used with economic methods thatmeasure economic performance, such as life-cycle cost analy-sis, net benefits, the benefit-to-cost ratio, i

5、nternal rate of return,and payback.2. Referenced Documents2.1 ASTM Standards:3E 631 Terminology of Building ConstructionsE 833 Terminology of Building EconomicsE 917 Practice for Measuring Life-Cycle Costs of Buildingsand Building SystemsE 964 Practice for Measuring Benefit-to-Cost and Savings-to-In

6、vestment Ratios for Buildings and Building SystemsE 1057 Practice for Measuring Internal Rate of Return andAdjusted Internal Rate of Return for Investments in Build-ings and Building SystemsE 1074 Practice for Measuring Net Benefits and Net Sav-ings for Investments in Buildings and Building SystemsE

7、 1121 Practice for Measuring Payback for Investments inBuildings and Building SystemsE 1185 Guide for Selecting Economic Methods for Evalu-ating Investments in Buildings and Building Systems2.2 ASTM Adjuncts:Discount Factor Tables, Adjunct to Practice E 91743. Terminology3.1 DefinitionsFor definitio

8、ns of terms used in this guide,refer to Terminologies E 631 and E 833.4. Summary of Guide4.1 This guide identifies related ASTM standards and ad-juncts. It describes circumstances when measuring uncertaintyand risk may be helpful in economic evaluations of buildinginvestments. This guide defines unc

9、ertainty, risk exposure, andrisk attitude. It presents nonprobabilistic and probabilistictechniques for measuring uncertainty and risk exposure. Thisguide describes briefly each technique, gives the formula forcalculating a measure where appropriate, illustrates the tech-niques with a case example,

10、and summarizes its advantagesand disadvantages.4.2 Since there is no best technique for measuring uncer-tainty and risk in every economic evaluation, this guideconcludes with a discussion of how to select the appropriatetechnique for a particular problem.4.3 This guide describes in detail how risk e

11、xposure can bemeasured by probability functions and distribution functions(see Annex A1). It also describes how risk attitude can beincorporated using utility theory and other approaches (seeAnnex A2).5. Significance and Use5.1 Investments in long-lived projects such as buildings arecharacterized by

12、 uncertainties regarding project life, operationand maintenance costs, revenues, and other factors that affect1This guide is under the jurisdiction of ASTM Committee E06 on Performanceof Buildings and is the direct responsibility of Subcommittee E06.81 on BuildingEconomics.Current edition approved A

13、pril 1, 2007. Published April 2007. Originallyapproved in 1990. Last previous edition approved in 2002 as E 1369 02.2For an extensive overview of techniques for treating risk and uncertainty, seeMarshall, Harold E.Techniques for Treating Uncertainty and Risk in the Eco-nomic Evaluation of Building I

14、nvestments, National Institute of Standards andTechnology, Special Publication 757, 1988.3For referenced ASTM standards, visit the ASTM website, www.astm.org, orcontact ASTM Customer Service at serviceastm.org. For Annual Book of ASTMStandards volume information, refer to the standards Document Summ

15、ary page onthe ASTM website.4Available from ASTM International Headquarters. Order Adjunct No.ADJ091703.1Copyright ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959, United States.project economics. Since future values of these variable factorsare generally not

16、 known, it is difficult to make reliableeconomic evaluations.5.2 The traditional approach to project investment analysishas been to apply economic methods of project evaluation tobest-guess estimates of project input variables as if they werecertain estimates and then to present results in single-va

17、lue,deterministic terms. When projects are evaluated withoutregard to uncertainty of inputs to the analysis, decision makersmay have insufficient information to measure and evaluate therisk of investing in a project having a different outcome fromwhat is expected.5.3 Risk analysis is the body of the

18、ory and practice that hasevolved to help decision makers assess their risk exposures andrisk attitudes so that the investment that is the best bet for themcan be selected.NOTE 1The decision maker is the individual or group of individualsresponsible for the investment decision. For example, the decis

19、ion makermay be the chief executive officer or the board of directors.5.4 Uncertainty and risk are defined as follows. Uncertainty(or certainty) refers to a state of knowledge about the variableinputs to an economic analysis. If the decision maker is unsureof input values, there is uncertainty. If t

20、he decision maker issure, there is certainty. Risk refers either to risk exposure orrisk attitude.5.4.1 Risk exposure is the probability of investing in aproject that will have a less favorable economic outcome thanwhat is desired (the target) or is expected.5.4.2 Risk attitude, also called risk pre

21、ference, is the will-ingness of a decision maker to take a chance or gamble on aninvestment of uncertain outcome. The implications of decisionmakers having different risk attitudes is that a given investmentof known risk exposure might be economically acceptable toan investor who is not particularly

22、 risk averse, but totallyunacceptable to another investor who is very risk averse.NOTE 2For completeness, this guide covers both risk averse and risktaking attitudes. Most investors, however, are likely to be risk averse. Theprinciples described herein apply both to the typical case where investorsh

23、ave different degrees of risk aversion and to the atypical case where someinvestors are risk taking while others are risk averse.5.5 No single technique can be labeled the best technique inevery situation for treating uncertainty, risk, or both. What isbest depends on the following: availability of

24、data, availabilityof resources (time, money, expertise), computational aids (forexample, computer services), user understanding, ability tomeasure risk exposure and risk attitude, risk attitude ofdecision makers, level of risk exposure of the project, and sizeof the investment relative to the instit

25、utions portfolio.6. Procedures6.1 The recommended steps for carrying out an evaluationof uncertainty or risk are as follows:6.1.1 Determine appropriate economic measure(s) forevaluating the investment (see Guide E 1185).6.1.2 Identify objectives, alternatives, and constraints (seePractices E 917, E

26、964, E 1057, E 1074, and E 1121).6.1.3 Decide whether an uncertainty and risk evaluation isneeded, and, if so, choose the appropriate technique (seeSections 5, 7, 8, and 10).6.1.4 Compile data and establish assumptions for the evalu-ation.6.1.5 Determine risk attitude of the decision maker (seeSecti

27、on 7 and Annex A2).6.1.6 Compute measures of worth5and associated risk (seeSections 7 and 8).6.1.7 Analyze results and make a decision (see Section 9).6.1.8 Document the evaluation (see Section 11).7. Techniques: Advantages and Disadvantages7.1 This guide considers in detail three nonprobabilisticte

28、chniques (breakeven analysis, sensitivity analysis, and risk-adjusted discounting) and three probabilistic techniques (mean-variance criterion and coefficient of variation, decision analy-sis, and simulation) for treating uncertainty and risk.This guidealso summarizes several additional techniques t

29、hat are usedless frequently.7.2 Breakeven Analysis:7.2.1 When an uncertain variable is critical to the economicsuccess of a project, decision makers frequently want to knowthe minimum or maximum value that variable can reach andstill have a breakeven project; that is, a project where benefits(saving

30、s) equal costs. For example, the breakeven value of aninput cost variable is the maximum amount one can afford topay for the input and still break even compared to benefitsearned. A breakeven value of an input benefit variable is theminimum amount the project can produce in that benefitcategory and

31、still cover the projected costs of the project.NOTE 3Benefits and costs are treated throughout this guide on adiscounted cash-flow basis, taking into account taxes where appropriate.(See Practice E 917 for an explanation of discounted cash flows consid-ering taxes.)7.2.2 To perform a breakeven analy

32、sis, an equation isconstructed wherein the benefits are set equal to the costs for agiven investment project, the values of all inputs except thebreakeven variable are specified, and the breakeven variable issolved algebraically.7.2.3 Suppose a decision maker is deciding whether or notto invest in a

33、 piece of energy conserving equipment for agovernment-owned building. The deviation of the formula forcomputing breakeven investment costs for the equipment is asfollows:S 5 C (1)C 5 I 1 O or acombination might include optimistic values for some vari-ables in conjunction with pessimistic or expected

34、 values forothers. Examining different combinations is required if theuncertain variables are interrelated.7.3.3 The following illustration of sensitivity analysis treatsan accept/reject decision. Consider a decision on whether ornot to install a programmable time clock to control heating,ventilatin

35、g, and air conditioning (HVAC) equipment in abuilding. The time clock reduces electricity consumption byturning off that part of the HVAC equipment that is not neededduring hours when the building is unoccupied. Using thebenefit-to-cost ratio (BCR) as the economic method, the timeclock is acceptable

36、 on economic grounds if its BCR is greaterthan 1.0. The energy reduction benefits from the time clock,however, are uncertain.They are a function of three factors: theinitial price of energy, the rate of change in energy prices overthe life cycle of the time clock, and the number of kilowatthours sav

37、ed. Assume that the initial price of energy and thenumber of kilowatt-hours saved are relatively certain, and thatthe sensitivity of the BCR is being tested with respect to thefollowing three values of energy price change: a low rate ofenergy price escalation (slowly increasing benefits from energys

38、avings); a moderate rate of escalation (moderately increasingbenefits); and a high rate of escalation (rapidly increasingbenefits). These three assumed values of energy price changemight correspond to our projections of pessimistic, expected,and optimistic values. Three BCR estimates result from rep

39、eat-ing the BCR computation for each of the three energy priceescalation rates. For example, BCRs of 0.8, 2.0, and 4.0 mightresult. Whereas a deterministic approach might have generateda BCR estimate of 2.0, now it is apparent that the BCR couldbe significantly less than 2.0, and even less than 1.0.

40、 Thusaccepting the time clock could lead to an inefficient outcome.7.3.4 There are several advantages of sensitivity analysis.First, it shows how significant a single input variable is indetermining project outcomes. Second, it recognizes the un-certainty associated with the input. Third, it gives i

41、nformationabout the range of output variability. And fourth, it does all ofthese when there is little information, resources, or time to usemore sophisticated techniques.7.3.5 Disadvantages of sensitivity analysis in evaluatingrisk are that it gives no explicit probabilistic measure of riskexposure

42、and it includes no explicit treatment of risk attitude.The findings of sensitivity analysis are ambiguous. How likelyis a pessimistic or expected or optimistic value, for example,and how likely is the corresponding outcome value? Sensitivityanalysis can in fact be misleading if all pessimistic assum

43、ptionsor all optimistic assumptions are combined in calculatingeconomic measures. Such combinations of inputs are unlikelyin the real world.7.3.6 Sensitivity results can be presented in text, tables, orgraphs. One type of graph that is useful in showing thesensitivity of project worth to a critical

44、variable is illustrated inFig. 1. Net benefits (NB) for Projects A and B decrease as thediscount rate increases. The slopes of the functions show thatNB is more sensitive to discount rate changes for Project Athan for Project B, assuming other variables remain unchanged.These functions also help in

45、making comparisons as to whichproject is more cost effective.At a discount rate below 7 %, forexample, Project A has the greater NB. At a rate above 7 %,Project B yields the greater NB. And at 7 %, the two projectsprovide identical NB.7.3.7 Note that the functions indicate the potential values ofNB

46、if different values of the discount rate occur. If decisionmakers have some idea as to the likelihood of specific discountrates, the graph will help them evaluate the NB implications forE136907e13these two projects. The sensitivity graph in this sense contrib-utes to an implicit description of risk

47、exposure. Yet the graphfails to provide a quantitative measure of the probability of anygiven NB occurring.7.3.8 Another special graph for sensitivity analysis thatpresents a snapshot of potential impacts of uncertain inputvariables on project outcomes is the spider diagram. The oneillustrated in Fi

48、g. 2 shows for a prospective commercialbuilding investment the sensitivity of the adjusted internal rateof return (AIRR) to three variables: operation, maintenance,and replacement costs (OM project life (PL); and thereinvestment rate (RR). Each variable is represented by alabeled function that shows

49、 what AIRR values would resultfrom different values of the uncertain variable. For example,the downward-sloping OM that is, as future benefitsbecome more uncertain, the RADR technique requires raisingthe discount rate to make the project look less desirable. Forcost streams, AR1 and AR2 are adjusted downwards asperceived risk increases; that is, as future costs become moreuncertain, the correct application of the RADR techniquerequires lowering the discount rate to make the project lookless cost effective. It follows then that the appropriate adjust-ment for risk when using lif

展开阅读全文
相关资源
猜你喜欢
  • BS ISO 9711-1-1995 Freight containers - Information related to containers on board vessels - Bay plan system《货运集装箱 船载集装箱的有关资料 箱位坐标》.pdf BS ISO 9711-1-1995 Freight containers - Information related to containers on board vessels - Bay plan system《货运集装箱 船载集装箱的有关资料 箱位坐标》.pdf
  • BS ISO 9714-1-2012 Orthopaedic drilling instruments Drill bits taps and countersink cutters《整形外科钻孔设备 钻头 龙头和沉头铣刀》.pdf BS ISO 9714-1-2012 Orthopaedic drilling instruments Drill bits taps and countersink cutters《整形外科钻孔设备 钻头 龙头和沉头铣刀》.pdf
  • BS ISO 9727-1-2007 Cylindrical cork stoppers - Physical tests - Determination of dimensions《圆柱形软木塞 物理试验 尺寸测定》.pdf BS ISO 9727-1-2007 Cylindrical cork stoppers - Physical tests - Determination of dimensions《圆柱形软木塞 物理试验 尺寸测定》.pdf
  • BS ISO 9727-2-2007 Cylindrical cork stoppers - Physical tests - Determination of mass and apparent density for agglomerated cork stoppers《圆柱形软木塞 物理试验 成团软木塞质量和表观密度的测定》.pdf BS ISO 9727-2-2007 Cylindrical cork stoppers - Physical tests - Determination of mass and apparent density for agglomerated cork stoppers《圆柱形软木塞 物理试验 成团软木塞质量和表观密度的测定》.pdf
  • BS ISO 9727-3-2007 Cylindrical cork stoppers - Physical tests - Determination of humidity content《圆柱形软木塞 物理试验 含水量测定》.pdf BS ISO 9727-3-2007 Cylindrical cork stoppers - Physical tests - Determination of humidity content《圆柱形软木塞 物理试验 含水量测定》.pdf
  • BS ISO 9727-4-2007 Cylindrical cork stoppers - Physical tests - Determination of dimensional recovery after compression《圆柱形软木塞 物理试验 压缩后尺寸恢复的测定》.pdf BS ISO 9727-4-2007 Cylindrical cork stoppers - Physical tests - Determination of dimensional recovery after compression《圆柱形软木塞 物理试验 压缩后尺寸恢复的测定》.pdf
  • BS ISO 9727-5-2007 Cylindrical cork stoppers - Physical tests - Determination of extraction force《圆柱形软木塞 物理试验 拔出力测定》.pdf BS ISO 9727-5-2007 Cylindrical cork stoppers - Physical tests - Determination of extraction force《圆柱形软木塞 物理试验 拔出力测定》.pdf
  • BS ISO 9727-6-2007 Cylindrical cork stoppers - Physical tests - Determination of liquid tightness《圆柱形软木塞 物理试验 液体紧密性测定》.pdf BS ISO 9727-6-2007 Cylindrical cork stoppers - Physical tests - Determination of liquid tightness《圆柱形软木塞 物理试验 液体紧密性测定》.pdf
  • BS ISO 9727-7-2007 Cylindrical cork stoppers - Physical tests - Determination of dust content《圆柱形软木塞 物理试验 含尘量测定》.pdf BS ISO 9727-7-2007 Cylindrical cork stoppers - Physical tests - Determination of dust content《圆柱形软木塞 物理试验 含尘量测定》.pdf