1、*USACE / NAVFAC / AFCESA / NASA UFGS-01 32 16.00 20 (November 2009)-Preparing Activity: NAVFAC SupersedingUFGS-01 32 16.00 20 (April 2006)UFGS-01320N (December 2003)UNIFIED FACILITIES GUIDE SPECIFICATIONS*SECTION TABLE OF CONTENTSDIVISION 01 - GENERAL REQUIREMENTSCONSTRUCTION PROGRESS DOCUMENTATION1
2、1/09PART 1 GENERAL1.1 SUBMITTALS1.2 ACCEPTANCE1.3 SCHEDULE FORMAT1.3.1 Bar Chart Schedule1.3.2 Network Analysis Schedule (NAS)1.3.2.1 NAS Submittals and Procedures1.4 UPDATED SCHEDULES1.5 3-WEEK LOOK AHEAD SCHEDULE1.6 CORRESPONDENCE AND TEST REPORTS:PART 2 PRODUCTSPART 3 EXECUTION- End of Section Ta
3、ble of Contents -SECTION 01 32 16.00 20 Page 1Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-*USACE / NAVFAC / AFCESA / NASA UFGS-01 32 16.00 20 (November 2009)-Preparing Activity: NAVFAC SupersedingUFGS-01 32 16.00 20 (April 2006)UFGS-01320N (Decem
4、ber 2003)UNIFIED FACILITIES GUIDE SPECIFICATIONS*SECTION 01 32 16.00 20CONSTRUCTION PROGRESS DOCUMENTATION11/09*NOTE: This guide specification covers the requirements for the preparation and use of Design-Bid-Build Schedules.Specification Section 01 32 16.00 20 may be inserted when the contract amou
5、nt is expected to be less than $750,000 and the contract duration is expected to be less than 6 months, when there are no known critical completion dates for the Supported Command. Use Specification Section 01 32 17.00 20 NETWORK ANALYSIS SCHEDULES (NAS) when there is a known critical completion dat
6、e for the Supported Command. Consult the Administering FEAD/ROICC Office on all construction contracts to determine which guide specification to insert.This section shall be reviewed and approved by the administering FEAD/ROICC prior to completion of the Invitation For Bids (IFB).Edit bracketed item
7、s for project specific requirements by choosing applicable items(s) or insert appropriate information.Comments and suggestions on this guide specification are welcome and should be directed to the Technical Proponent of the specification. A listing of technical proponents, including their organizati
8、on designation and telephone number, is on the Internet.Recommended changes to a UFGS should be submitted as a Criteria Change Request (CCR).*PART 1 GENERAL1.1 SUBMITTALS*NOTE: Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL PROCEDURES. Edit the SECTION 01 32 16.00 20 Pag
9、e 2Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-following list to reflect only the submittals required for the project. Submittals should be kept to the minimum required for adequate quality control.A “G” following a submittal item indicates that
10、the submittal requires Government approval. Some submittals are already marked with a “G”. Only delete an existing “G” if the submittal item is not complex and can be reviewed through the Contractors Quality Control system. Only add a “G” if the submittal is sufficiently important or complex in cont
11、ext of the project.*Government approval is required for submittals with a “G“ designation; submittals not having a “G“ designation are for Contractor Quality Control approval. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:SD-01 Preconstruction SubmittalsCo
12、nstruction schedule; G1.2 ACCEPTANCE*NOTE: Select the first bracketed option when a line or bar chart is sufficient to administer theproject. Generally, line and bar chart constructionschedules should only be specified for very simple,low dollar value projects, with short contract duration. Always s
13、elect the Network Analysis Schedule (NAS) option when there is a known critical completion date for the Supported Command. Consult with the administering FEAD/ROICC to determine the form of construction schedule required.*Prior to the start of work, prepare and submit to the Contracting Officer for
14、acceptance a construction schedule in the form of a Bar ChartNetwork Analysis Schedule (NAS) in accordance with the terms in Contract Clause “FAR 52.236-15, Schedules for Construction Contracts,“ except as modified in this contract. Acceptance of an error free Baseline Schedule and updates is a cond
15、ition precedent to processing the Contractors pay request.1.3 SCHEDULE FORMAT*NOTE: Delete bracketed 1.3.1 Bar Chart Schedule from TABLE OF CONTENTS and requirements if a Network Analysis Schedule is required on this project.*1.3.1 Bar Chart ScheduleThe Bar Chart shall show submittals, government re
16、view periods, material/equipment delivery, utility outages, on-site construction, inspection, testing, and closeout activities. The Bar Chart shall be time SECTION 01 32 16.00 20 Page 3Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-scaled and genera
17、ted using an electronic spreadsheet program.*NOTE: Delete bracketed 1.3.2 NETWORK ANALYSIS SCHEDULE (including 1.3.2.1 NAS Submittals and Procedures) from TABLE OF CONTENTS and requirements if a Bar Chart Schedule is used on this project.*1.3.2 Network Analysis Schedule (NAS)The Contractor shall use
18、 the critical path method (CPM) to schedule and control project activities. Project schedules shall be prepared and maintained using Primavera P3, Primavera SureTrak or current mandated scheduling program. Save files in Concentric P3 or current mandated scheduling program file format, compatible wit
19、h the Governments version of the scheduling program. Importing data into P3/SureTrak/current mandated scheduling program using data conversion techniques or third party software will be cause for rejection of the submitted schedule. The schedule shall be built as follows:The Project Schedule shall s
20、how submittals, government review periods, material/equipment delivery, utility outages, all on-site construction, inspection, testing, and closeout activities. Government and Contractor on-site work activities shall be driven by calendars that reflect Saturdays, Sundays and all Federal Holidays as
21、non-work days.With the exception of the Contract Award and End Contract milestone activities, no activities shall be open-ended; each activity shall have predecessor and successor ties.Each activity shall be assigned its appropriate Responsibility Code indicating responsibility to accomplish the wor
22、k indicated by the activity, Phase Code and Work Location Code.Date/time constraint(s) and/or lags, other than those required by the contract, shall not be allowed unless accepted by the Contracting Officer. The Contractor shall include as the last activity in the contract schedule, a milestone acti
23、vity named “Contract Completion Date“. The “Contract Completion Date“ milestone shall have a “Mandatory Finish“ constraint equal to the contract completion date.1.3.2.1 NAS Submittals and ProceduresSubmit all network analysis and updates in hard copy and on electronic media that is acceptable to the
24、 Contracting Officer. Submit an electronic back-up of the project schedule in an import format compatible with the governments scheduling program.1.4 UPDATED SCHEDULESUpdate the Construction schedule at monthly intervals or when the schedule has been revised. The updated schedule shall be kept curre
25、nt, reflecting actual activity progress and plan for completing the remaining work. Submit copies of purchase orders and confirmation of delivery dates as directed.SECTION 01 32 16.00 20 Page 4Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-1.5 3-WEE
26、K LOOK AHEAD SCHEDULEThe Contractor shall prepare and issue a 3-Week Look Ahead schedule to provide a more detailed day-to-day plan of upcoming work identified on the Construction Schedule. The work plans shall be keyed to activity numbers when a NAS is required and updated each week to show the pla
27、nned work for the current and following two-week period. Additionally, include upcoming outages, closures, preparatory meetings, and initial meetings. Identify critical path activities on the Three-Week Look Ahead Schedule. The detail work plans are to be bar chart type schedules, maintained separat
28、ely from the Construction Schedule on an electronic spreadsheet program and printed on 8 by 11 sheets as directed by the Contracting Officer. Activities shall not exceed 5 working days in duration and have sufficient level of detail to assign crews, tools and equipment required to complete the work.
29、 Three hard copies and one electronic file of the 3-Week Look Ahead Schedule shall be delivered to the Contracting Officer no later than 8 a.m. each Monday and reviewed during the weekly CQC Coordination Meeting. 1.6 CORRESPONDENCE AND TEST REPORTS:All correspondence (e.g., letters, Requests for Inf
30、ormation (RFIs), e-mails, meeting minute items, Production and QC Daily Reports, material delivery tickets, photographs, etc.) shall reference Schedule activities that are being addressed. All test reports (e.g., concrete, soil compaction, weld, pressure, etc.) shall reference schedule activities that are being addressed.PART 2 PRODUCTSNot used.PART 3 EXECUTIONNot used.- End of Section -SECTION 01 32 16.00 20 Page 5Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-