1、*USACE / NAVFAC / AFCESA / NASA UFGS-26 08 00 (April 2006)-Preparing Activity: NAVFAC Superseding UFGS-26 08 00 (April 2006)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement with UMRL dated July 2008*SECTION TABLE OF CONTENTSDIVISION 26 - ELECTRICALSECTION 26 08 00APPARATUS INSPECTI
2、ON AND TESTING08/08PART 1 GENERAL1.1 REFERENCES1.2 RELATED REQUIREMENTS1.3 SUBMITTALS1.4 QUALITY ASSURANCE1.4.1 Qualifications1.4.2 Acceptance Tests and Inspections Reports1.4.3 Acceptance Test and Inspections ProcedurePART 2 PRODUCTSPART 3 EXECUTION3.1 ACCEPTANCE TESTS AND INSPECTIONS3.2 SYSTEM ACC
3、EPTANCE3.3 PLACING EQUIPMENT IN SERVICE- End of Section Table of Contents -SECTION 26 08 00 Page 1Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-*USACE / NAVFAC / AFCESA / NASA UFGS-26 08 00 (April 2006)-Preparing Activity: NAVFAC Superseding UFGS-2
4、6 08 00 (April 2006)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement with UMRL dated July 2008*SECTION 26 08 00APPARATUS INSPECTION AND TESTING08/08*NOTE: This guide specification covers the requirements for electrical inspection and testing.Edit this guide specification for projec
5、t specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable items(s) or insert appropriate information.Remove information and requirements not required in respective project, whether or not brackets are present.Comments and suggestions on this guide specific
6、ation are welcome and should be directed to the technical proponent of the specification. A listing of technical proponents, including their organization designation and telephone number, is on the Internet.Recommended changes to a UFGS should be submitted as a Criteria Change Request (CCR).*NOTE: U
7、se this specification on project specifications where NETA testing is required.The following sections reference NETA for power distribution services and equipment.-Section 26 32 13.00 20 SINGLE OPERATION GENERATOR SETS-Section 26 12 19.20 THREE-PHASE PAD-MOUNTED TRANSFORMERS-Section 26 12 19.20 SING
8、LE-PHASE PAD-MOUNTED TRANSFORMERS-Section 33 71 01 OVERHEAD TRANSMISSION AND DISTRIBUTION-Section 33 71 02.00 20 UNDERGROUND ELECTRICAL DISTRIBUTION-Section 26 13 00.00 20 PAD-MOUNTED SF6 INSULATED SECTION 26 08 00 Page 2Provided by IHSNot for ResaleNo reproduction or networking permitted without li
9、cense from IHS-,-,-INTERRUPTER-Section 26 11 16 SECONDARY UNIT SUBSTATIONS-Section 26 11 13.00 20 PRIMARY UNIT SUBSTATIONS-Section 26 36 23.00 20 AUTOMATIC TRANSFER SWITCHES-Section 26 23 00 SWITCHBOARDS AND SWITCHGEARThis section shall also be used for specification sections containing low-voltage
10、or medium voltage generator control switchboards or switchgear, pad-mounted air switches, and medium voltage circuit breakers. Provide the section numbers and titles in this section, and add NETA testing requirements to the applicable section.Coordinate the sections in your contract documents with t
11、his list and with paragraph entitled “Acceptance Tests and Inspection“ in PART 3 of this specification.*PART 1 GENERAL1.1 REFERENCES*NOTE: This paragraph is used to list the publications cited in the text of the guide specification. The publications are referred to in the text by basic designation o
12、nly and listed in this paragraph by organization, designation, date, and title.Use the Reference Wizards Check Reference feature when you add a RID outside of the Sections Reference Article to automatically place the reference in the Reference Article. Also use the Reference Wizards Check Reference
13、feature to update the issue dates.References not used in the text will automatically be deleted from this section of the project specification when you choose to reconcile references in the publish print process.*The publications listed below form a part of this specification to the extent reference
14、d. The publications are referred to within the text by the basic designation only.INTERNATIONAL ELECTRICAL TESTING ASSOCIATION (NETA)NETA ATS (2003) Acceptance Testing Specifications1.2 RELATED REQUIREMENTSSection 26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS applies to this section with add
15、itions and modifications specified herein.SECTION 26 08 00 Page 3Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-1.3 SUBMITTALS*NOTE: Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL PROCEDURES and edit the following list t
16、o reflect only the submittals required for the project. Submittals should be kept to the minimum required for adequate quality control.A “G” following a submittal item indicates that the submittal requires Government approval. Some submittals are already marked with a “G”. Only delete an existing “G
17、” if the submittal item is not complex and can be reviewed through the Contractors Quality Control system. Only add a “G” if the submittal is sufficiently important or complex in context of the project.For submittals requiring Government approval on Army projects, a code of up to three characters wi
18、thin the submittal tags may be used following the “G“ designation to indicate the approving authority. Codes for Army projects using the Resident Management System (RMS) are: “AE“ for Architect-Engineer; “DO“ for District Office (Engineering Division or other organization in the District Office); “A
19、O“ for Area Office; “RO“ for Resident Office; and “PO“ for Project Office. Codes following the “G“ typically are not used for Navy, Air Force, and NASA projects.Choose the first bracketed item for Navy, Air Force and NASA projects, or choose the second bracketed item for Army projects.*Government ap
20、proval is required for submittals with a “G“ designation; submittals not having a “G“ designation are for Contractor Quality Control approval.for information only. When used, a designation following the “G“ designation identifies the office that will review the submittal for the Government. The foll
21、owing shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:SD-06 Test ReportsAcceptance tests and inspections; G; G, _SD-07 CertificatesQualifications of organization, and lead engineering technician; G; G, _Acceptance test and inspections procedure; G; G, _1.4 QUALITY ASSURAN
22、CE1.4.1 QualificationsContractor shall engage the services of a qualified testing organization to SECTION 26 08 00 Page 4Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-provide inspection, testing, calibration, and adjustment of the electrical distri
23、bution system and generation equipment listed in paragraph entitled “Acceptance Tests and Inspections“ herein. Organization shall be independent of the supplier, manufacturer, and installer of the equipment. The organization shall be a first tier subcontractor. No work required by this section of th
24、e specification shall be performed by a second tier subcontractor.a. Submit name and qualifications of organization. Organization shall have been regularly engaged in the testing of electrical materials, devices, installations, and systems for a minimum of 5 years. The organization shall have a cali
25、bration program, and test instruments used shall be calibrated in accordance with NETA ATS.b. Submit name and qualifications of the lead engineering technician performing the required testing services. Include a list of three comparable jobs performed by the technician with specific names and teleph
26、one numbers for reference. Testing, inspection, calibration, and adjustments shall be performed by an engineering technician, certified by NETA or the National Institute for Certification in Engineering Technologies (NICET) with a minimum of 5 years experience inspecting, testing, and calibrating el
27、ectrical distribution and generation equipment, systems, and devices.1.4.2 Acceptance Tests and Inspections ReportsSubmit certified copies of inspection reports and test reports. Reports shall include certification of compliance with specified requirements, identify deficiencies, and recommend corre
28、ctive action when appropriate. Type and neatly bind test reports to form a part of the final record. Submit test reports documenting the results of each test not more than 10 days after test is completed.1.4.3 Acceptance Test and Inspections ProcedureSubmit test procedure reports for each item of eq
29、uipment to be field tested at least 45 days prior to planned testing date. Do not perform testing until after test procedure has been approved.PART 2 PRODUCTSNot used.PART 3 EXECUTION3.1 ACCEPTANCE TESTS AND INSPECTIONSTesting organization shall perform acceptance tests and inspections. Test methods
30、, procedures, and test values shall be performed and evaluated in accordance with NETA ATS, the manufacturers recommendations, and paragraph entitled “Field Quality Control“ of each applicable specification section. Tests identified as optional in NETA ATS are not required unless otherwise specified
31、. Equipment shall be placed in service only after completion of required tests and evaluation of the test results have been completed. Contractor shall supply to the testing organization complete sets of shop drawings, settings of adjustable devices, and other information necessary for an accurate t
32、est and inspection of the system prior to the performance SECTION 26 08 00 Page 5Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-of any final testing. Contracting Officer shall be notified at least 14 days in advance of when tests will be conducted b
33、y the testing organization. Perform acceptance tests and inspections on applicable equipment and systems specified in the following sections:*NOTE: Select applicable sections for each project. Ensure each equipment section includes the following information. These changes should be found in the Atla
34、ntic Division Interim Specification Revision.1. NETA ATS listed in the references.2. The words “and Section 16081N, “Apparatus Inspection and Testing“ apply“ added to paragraph entitled “Related Requirements.“3. SD-06 submittals with “Acceptance checks and tests“ added in PART 1.4. Appropriate parag
35、raphs from the NETA manual added under “Field Quality Control“ in PART 3.5. Add any job section numbers and titles containing low-voltage or medium voltage generator control switchgear or switchboards, pad-mounted air switches, or medium voltage circuit breakers. Provide the NETA tests required in t
36、he applicable section.*a. Section 26 32 13.00 20 SINGLE-OPERATION GENERATOR SETS. Functional engine shutdown tests, vibration base-line test, and load bank test shall not be performed by the testing organization. These tests shall be performed by the start-up engineer.b. Section 26 12 19.10 THREE-PH
37、ASE PAD-MOUNTED TRANSFORMERSc. Section 26 12 19.20 SINGLE-PHASE PAD-MOUNTED TRANSFORMERSd. Section 33 71 01 OVERHEAD TRANSMISSION AND DISTRIBUTIONe. Section 33 71 02.00 20 UNDERGROUND ELECTRICAL DISTRIBUTION f. Section 26 13 00.00 20 PAD-MOUNTED SF6 INSULATED INTERRUPTER SWITCHESg. Section 26 11 16
38、SECONDARY UNIT SUBSTATIONSh. Section 26 11 13.00 20 PRIMARY UNIT SUBSTATIONSi. Section 26 36 23.00 20 AUTOMATIC TRANSFER SWITCHESj. Section 26 23 00 SWITCHBOARDS AND SWITCHGEARSECTION 26 08 00 Page 6Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-3.2
39、 SYSTEM ACCEPTANCEFinal acceptance of the system is contingent upon satisfactory completion of acceptance tests and inspections.3.3 PLACING EQUIPMENT IN SERVICEA representative of the approved testing organization shall be present when equipment tested by the organization is initially energized and placed in service.- End of Section -SECTION 26 08 00 Page 7Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-