1、 *USACE / NAVFAC / AFCESA / NASA UFGS-26 33 53.00 20 (April 2008)-Preparing Activity: NAVFAC SupersedingUFGS-26 33 53.00 20 (January 2008)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement with UMRL dated March 2008*SECTION TABLE OF CONTENTSDIVISION 26 - ELECTRICALSECTION 26 33 53.00
2、 20UNINTERRUPTIBLE POWER SUPPLY (UPS)04/08PART 1 GENERAL1.1 REFERENCES1.2 RELATED REQUIREMENTS1.3 DEFINITIONS1.4 SUBMITTALS1.5 PERFORMANCE REQUIREMENTS1.5.1 Normal Operation1.5.2 Emergency Operation (Loss or deviation of AC Input Power)1.5.3 Return of AC Input Power Source1.5.4 Failure of AC Input P
3、ower to Return1.5.5 Transfer to Bypass AC Power Source1.5.6 Retransfer to Inverter1.5.7 UPS Bypass Maintenance1.5.8 Battery Maintenance1.6 QUALITY ASSURANCE1.6.1 UPS Drawings1.6.2 UPS Installation1.6.3 Work Plan1.6.4 Factory Test Plan1.6.5 Performance Test Plan1.6.6 Factory Tests Report1.6.7 Perform
4、ance Tests Report1.6.8 Regulatory Requirements1.6.8.1 Reference Standard Compliance1.6.8.2 Independent Testing Organization Certificate1.6.9 Standard Products1.6.9.1 Alternative Qualifications1.6.9.2 Material and Equipment Manufacturing Date1.7 DELIVERY AND STORAGE1.8 PROJECT/SITE CONDITIONS1.8.1 En
5、vironmental Conditions1.8.2 Sound Pressure Levels1.8.3 Verification of Dimensions1.9 SPECIAL TOOLSSECTION 26 33 53.00 20 Page 1Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-1.10 OPERATION AND MAINTENANCE MANUALS1.10.1 Additions to UPS Operation and
6、 Maintenance Manuals1.10.2 Spare Parts1.11 WARRANTYPART 2 PRODUCTS2.1 UPS SYSTEM DESCRIPTION2.1.1 Semiconductor Fusing2.1.2 Control Power2.1.3 EMI/RFI Protection2.1.4 Internal Wiring2.1.5 Internal Assembly2.1.6 Cabinets2.1.6.1 Cabinet Finish2.1.6.2 Live Parts (300 Volts and Above)2.1.6.3 Drawout Ass
7、emblies2.1.7 Safety2.1.8 UPS System Load Profile2.2 UPS SYSTEM RATINGS2.2.1 System Capacity2.2.2 Battery Capacity2.2.3 Static Switch2.2.4 Module Bus Bracing2.2.5 AC Input2.2.6 AC Output2.2.7 Transient Response2.2.7.1 Voltage Transients2.2.7.2 Frequency2.2.8 Efficiency2.3 UPS MODULE2.3.1 General Desc
8、ription2.3.1.1 Interchangeability2.3.2 Rectifier/Charger Unit2.3.2.1 Input Protective Device2.3.2.2 Surge Protection2.3.2.3 Input Isolation Transformer2.3.2.4 Power Walk-In2.3.2.5 Sizing2.3.2.6 Battery Charging Current2.3.2.7 DC Ripple2.3.2.8 DC Voltage Adjustment2.3.2.9 Battery Isolation Protective
9、 Device2.3.3 Inverter Unit2.3.3.1 Output Overload2.3.3.2 Output Frequency Control2.3.3.3 Output Protective Device2.3.3.4 Output Transformer2.3.4 External Protection2.3.5 Internal Protection2.4 STATIC BYPASS TRANSFER CIRCUIT2.4.1 Uninterrupted Transfer2.4.2 Interrupted Transfer2.4.3 Manual Transfer2.
10、4.4 Automatic Uninterrupted Forward Transfer2.4.5 Forced Transfer2.4.6 Overload Ratings2.4.7 Static Switch Disconnect2.5 MAINTENANCE BYPASS SWITCHSECTION 26 33 53.00 20 Page 2Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-2.5.1 General2.5.2 Load Tra
11、nsfer2.5.3 Load Bank Protection Device2.5.4 Voltage MatchingIsolation Transformer2.6 MODULE CONTROL PANEL2.6.1 Module Meters2.6.1.1 Monitored Functions2.6.1.2 Meter Construction2.6.2 Module Controls2.6.3 Module Alarm Indicators2.6.4 Module Emergency OFF Button2.7 SELF-DIAGNOSTIC CIRCUITS2.8 REMOTE M
12、ONITORING PANEL2.8.1 Indicators2.8.2 Audible Alarm2.9 COMMUNICATIONS AND DATA ACQUISITION2.9.1 Emergency Control Contacts2.10 TEMPERATURE CONTROL2.10.1 General2.10.2 Blower Power Source2.10.3 Temperature Sensors2.11 BATTERY SYSTEM2.11.1 General2.11.2 Battery Ratings2.11.3 Battery Construction2.11.4
13、Battery Cabinet2.11.5 Battery Rack2.11.6 Cell-Terminal Covers2.11.7 Battery Disconnect2.11.8 Seismic Requirements2.11.9 Battery Monitor2.12 FACTORY TESTING2.12.1 Transient Tests2.12.2 Efficiency Tests2.13 CABLE LUGS AND TERMINATIONS2.13.1 Cable Lugs2.13.2 Terminations2.14 INSPECTION2.15 FIELD FABRIC
14、ATED NAMEPLATES2.16 MANUFACTURERS NAMEPLATES2.17 FACTORY APPLIED FINISHPART 3 EXECUTION3.1 INSTALLATION3.1.1 Control Cable3.1.2 Grounding Conductor3.1.3 UPS Output Conductors3.1.4 DC Power Conductors3.1.5 Seismic Protection3.1.6 Conduit Entries3.1.7 Battery Rack Assembly3.1.8 Battery Cabinet Assembl
15、y3.1.9 Battery Installation3.2 FIELD QUALITY CONTROL3.2.1 Installation Preparation3.2.2 Initial Inspection and Tests3.2.3 Performance Tests3.2.3.1 UPS Unit Performance TestsSECTION 26 33 53.00 20 Page 3Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-
16、3.2.3.2 Emergency Generator Operation3.2.3.3 Battery Performance Test (Constant KW)3.3 DEMONSTRATION3.3.1 Instructing Government Personnel3.4 FINAL ADJUSTMENTS3.5 NAMEPLATE MOUNTING3.6 FIELD APPLIED PAINTING3.7 DISPOSAL- End of Section Table of Contents -SECTION 26 33 53.00 20 Page 4Provided by IHSN
17、ot for ResaleNo reproduction or networking permitted without license from IHS-,-,-*USACE / NAVFAC / AFCESA / NASA UFGS-26 33 53.00 20 (April 2008)-Preparing Activity: NAVFAC SupersedingUFGS-26 33 53.00 20 (January 2008)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement with UMRL date
18、d March 2008*SECTION 26 33 53.00 20UNINTERRUPTIBLE POWER SUPPLY (UPS)04/08*NOTE: This guide specification covers the requirements for static UPS to provide continuous ac power to critical loads and/or to improve the quality of ac power to critical loads. The covered range of UPS units is between 10k
19、VA and 750kVA 3-phase systems only. Single phase systems are not addressed. This specification covers UPS with electro-chemical batteries. Electro-mechanical (stored energy) UPS are not addressed.Comments and suggestions on this guide specification are welcome and should be directed to the technical
20、 proponent of the specification. A listing of technical proponents, including their organization designation and telephone number, is on the Internet.Recommended changes to a UFGS should be submitted as a Criteria Change Request (CCR).Use of electronic communication is encouraged.Brackets are used i
21、n the text to indicated designer choices or locations where text must be supplied by the designer.*NOTE: For Air Force projects only, UPS specifications, criteria, and purchases shall be approved by the Power Conditioning and Continuation Interfacing Equipment (PCCIE) Group Manager at Ogden Air Logi
22、stics Center (OO-ALC/LGHC) http:/www.hill.af.mil/lg2/WebLGH.htm*NOTE: This guide specification is intended to be used with individual UPS units which contain a single module or multiple modules within the same SECTION 26 33 53.00 20 Page 5Provided by IHSNot for ResaleNo reproduction or networking pe
23、rmitted without license from IHS-,-,-assembly. Parallel units are not specifically addressed and require additional components. There are two types of parallel systems commonly available. One is a parallel system that requires a system control panel, external static bypass switch to control the indi
24、vidual units and additional output switchgear with maintenance bypass to connect the output of all the units; the other is individual units that have integrated controls and static bypass switches that communicate with one another and only require the output switchgear with maintenance bypass to con
25、nect the output of all the parallel units. The designer should be aware of the differences and select the system that addresses the design requirements. Parallel systems require additional paragraphs to address the additional components (system control panel with static bypass switch, output switchg
26、ear, etc) and overall system requirements.*NOTE: This guide specification will not be used in the preparation of project documents for installation of Government-furnished (GFE) UPS systems. For UPS and battery installation instructions for GFE projects refer to “UPS Manufacturers Installation Drawi
27、ngs“ and “Battery Manufacturers Rack Assembly and Battery Installation Instructions“ which must be obtained from the Contracting Officer.All plans/specifications having uninterruptible power supply systems, which were procured as Government-furnished/Contractor installed equipment, must be reviewed
28、and concurred by the Contracting Officer.*PART 1 GENERAL1.1 REFERENCES*NOTE: Issue (date) of references included in project specifications need not be more current than provided by the latest guide specification. Use of SpecsIntact automated reference checking is recommended for projects based on ol
29、der guide specifications.*The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.Acoustical Society of America (ASA)ASA S1.4 (1983; R 2006) Specification for Sound SECTION 26 33 53.00 20
30、 Page 6Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Level Meters (ASA 47)ASTM INTERNATIONAL (ASTM)ASTM B 173 (2001a; R 2007e1) Standard Specification for Rope-Lay-Stranded Copper Conductors Having Concentric-Stranded Members, for Electrical Conduc
31、torsASTM D 709 (2001; R 2007) Laminated Thermosetting MaterialsINSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)IEEE C2 (2007; Errata 2007) National Electrical Safety CodeIEEE C57.110 (1998; R 2004) Recommended Practice for Establishing Transformer Capability When Supplying Nonsinusoidal Load
32、 CurrentsIEEE C62.41.1 (2002) IEEE Guide on the Surges Environment in Low-Voltage (1000 V and Less) AC Power CircuitsIEEE C62.41.2 (2002) IEEE Recommended Practice on Characterization of Surges in Low-Voltage (1000 V and Less) AC Power CircuitsIEEE Std 100 (2000) The Authoritave Dictionary of IEEE S
33、tandards TermsIEEE Std 450 (2002) Recommended Practice for Maintenance, Testing, and Replacement of Vented Lead-Acid Batteries for Stationary ApplicationsINTERNATIONAL ELECTRICAL TESTING ASSOCIATION (NETA)NETA ATS (2003) Acceptance Testing SpecificationsINTERNATIONAL ORGANIZATION FOR STANDARDIZATION
34、 (ISO)ISO 9001 (2000) Quality management systems- RequirementsNATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)NEMA 250 (2003) Enclosures for Electrical Equipment (1000 Volts Maximum)NEMA PE 1 (2003; R 2003) Uninterruptible Power Systems - Specification and Performance VerificationNATIONAL FIRE P
35、ROTECTION ASSOCIATION (NFPA)NFPA 70 (2007) National Electrical Code - 2008 EditionSECTION 26 33 53.00 20 Page 7Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-UNDERWRITERS LABORATORIES (UL)UL 1449 (2006) Surge Protective DevicesUL 1778 (2005; Rev thr
36、u Jul 2006) Uninterruptible Power Systems1.2 RELATED REQUIREMENTS*NOTE: Include Section 26 08 00 APPARATUS INSPECTION AND TESTING on all projects involving medium voltage and specialized power distribution equipment.*Section 26 08 00 APPARATUS INSPECTION AND TESTING applies to this section, with the
37、 additions and modifications specified herein.1.3 DEFINITIONSUnless otherwise specified or indicated, electrical and electronics terms used in these specifications, and on the drawings, shall be as defined in IEEE Std 100.1.4 SUBMITTALS*NOTE: Submittals must be limited to those necessary for adequat
38、e quality control. The importance of an item in the project should be one of the primary factors in determining if a submittal for the item should be required.A “G“ following a submittal item indicates that the submittal requires Government approval. Some submittals are already marked with a “G“. On
39、ly delete an existing “G“ if the submittal item is not complex and can be reviewed through the Contractors Quality Control system. Only add a “G“ if the submittal is sufficiently important or complex in context of the project.For submittals requiring Government approval on Army projects, a code of u
40、p to three characters within the submittal tags may be used following the “G“ designation to indicate the approving authority. Codes for Army projects using the Resident Management System (RMS) are: “RE“ for Resident Engineer approval, “ED for Engineering approval, and “AE“ for Architect-Engineer ap
41、proval“AE“ for Architect-Engineer; “DO“ for District Office (Engineering Division or other organization in the District Office); “AO“ for Area Office; “RO“ for Resident Office; and “PO“ for Project Office. Codes following the “G“ typically are not used for Navy projects.Submittal items not designate
42、d with a “G“ are SECTION 26 33 53.00 20 Page 8Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-considered as being for information only for Army projects and for Contractor Quality Control approval for Navy projects.*Government approval is required fo
43、r submittals with a “G“ designation; submittals not having a “G“ designation are for Contractor Quality Control approval.for information only. When used, a designation following the “G“ designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:SD-02 Shop DrawingsUPS Drawings; G; G, _UPS Installation; G; G, _SD-03 Product DataUPS Module; G; G, _Submittal shall include manufacturers information for each component, device, and accessory provided with the trans