1、Lessons Learned Entry: 0201Lesson Info:a71 Lesson Number: 0201a71 Lesson Date: 1992-11-05a71 Submitting Organization: KSCa71 Submitted by: David PenningtonSubject: Advanced Solid Rocket Motor (ASRM) Propellant Manufacturing Facility. Description of Driving Event: The full-scale ASRM propellant manuf

2、acturing facility may not be directly scaleable from the continuous mix pilot plant. Particular problem areas relate to the particle size of the propellant and the screw pump section of the rotofeed.Many parameters and processes for the new facility have not been fully determined. However, another m

3、anufacturer has produced a substantial amount of similar solid propellant using continuous production processes, so the basic techniques are familiar.Safety devices are installed on the propellant flow line to limit the spread of fire in case of an accident. The flow line transporting the uncured pr

4、opellant has several firebreaks to prevent propagation of a fire along the tube. The basic safety device is an explosive-fired guillotine valve that interrupts the flow, with a water spray on the propellant to lower the temperature below the ignition point. In addition, there is a collar in the flow

5、 line upstream of the guillotine and on the casting pit side of a firewall that can be blown to allow the propellant to flow out on the floor and prevent pressure buildup. A matter that must be considered is cleanup after an accident involving a dump of uncured propellant on the floor. The continuou

6、s mix pilot plant at manufacturer provides a way of proving a new propellant and upgrading the equipment before establishing a full-scale facility at yellow creek. The major differences between the pilot plant and the full-scale facility are equipment size and process control software. The pilot pla

7、nt production rate is 1,000 to 1,400 pounds/hour with the full-scale facility producing 20,000 to 26,000 pounds/hour. The ultimate particle size of the propellant is dependent on parameters such as geometry of piping, length of lines, and fluid working pressures that may not be directly scaleable. T

8、here are many challenges such as metering of propellant solids, pre-mix of iron oxide and aluminum, and real-time process control. Upscaling the rotofeed dearator and pump equipment probably presents the greatest challenge.Provided by IHSNot for ResaleNo reproduction or networking permitted without

9、license from IHS-,-,-Lesson(s) Learned: Particular problem areas related to the particle size of the propellant and the screw pump indicate that the facility may not be directly scaleable.Recommendation(s): Scale-up of the ASRM propellant manufacturing plant should be scrutinized closely to ensure t

10、hat safety and schedule are not compromised.Evidence of Recurrence Control Effectiveness: N/ADocuments Related to Lesson: N/AMission Directorate(s): N/AAdditional Key Phrase(s): a71 Energetic Materials - Explosive/Propellant/Pyrotechnica71 Facilitiesa71 Fire ProtectionAdditional Info: Approval Info: a71 Approval Date: 1994-06-06a71 Approval Name: James G. Klinea71 Approval Organization: KSC/HEIa71 Approval Phone Number: 407-867-7614Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-

展开阅读全文
相关资源
猜你喜欢
  • ITU-T X 742 FRENCH-1995 INFORMATION TECHNOLOGY C OPEN SYSTEMS INTERCONNECTION C SYSTEMS MANAGEMENT USAGE METERING FUNCTION FOR ACCOUNTING PURPOSES《信息技术 开放系统互连 系统管理 计费用使用计量功能》.pdf ITU-T X 742 FRENCH-1995 INFORMATION TECHNOLOGY C OPEN SYSTEMS INTERCONNECTION C SYSTEMS MANAGEMENT USAGE METERING FUNCTION FOR ACCOUNTING PURPOSES《信息技术 开放系统互连 系统管理 计费用使用计量功能》.pdf
  • ITU-T X 742 SPANISH-1995 INFORMATION TECHNOLOGY C OPEN SYSTEMS INTERCONNECTION C SYSTEMS MANAGEMENT USAGE METERING FUNCTION FOR ACCOUNTING PURPOSES《信息技术 开放系统互连 系统管理 计费用使用计量功能》.pdf ITU-T X 742 SPANISH-1995 INFORMATION TECHNOLOGY C OPEN SYSTEMS INTERCONNECTION C SYSTEMS MANAGEMENT USAGE METERING FUNCTION FOR ACCOUNTING PURPOSES《信息技术 开放系统互连 系统管理 计费用使用计量功能》.pdf
  • ITU-T X 742-1995 INFORMATION TECHNOLOGY C OPEN SYSTEMS INTERCONNECTION C SYSTEMS MANAGEMENT USAGE METERING FUNCTION FOR ACCOUNTING PURPOSES《信息技术 开放系统互连 系统管理 会计用计费功能的使用 数据和开放网络通信-OS.pdf ITU-T X 742-1995 INFORMATION TECHNOLOGY C OPEN SYSTEMS INTERCONNECTION C SYSTEMS MANAGEMENT USAGE METERING FUNCTION FOR ACCOUNTING PURPOSES《信息技术 开放系统互连 系统管理 会计用计费功能的使用 数据和开放网络通信-OS.pdf
  • ITU-T X 743 CORR 1 FRENCH-2001 Information technology C Open Systems Interconnection C Systems Management Time management function Technical Corrigendum 1《信息技术 开放系统互连 系统管理 时间管理功能 技.pdf ITU-T X 743 CORR 1 FRENCH-2001 Information technology C Open Systems Interconnection C Systems Management Time management function Technical Corrigendum 1《信息技术 开放系统互连 系统管理 时间管理功能 技.pdf
  • ITU-T X 743 CORR 1 SPANISH-2001 Information technology C Open Systems Interconnection C Systems Management Time management function Technical Corrigendum 1《信息技术 开放系统互连 系统管理 时间管理功能 .pdf ITU-T X 743 CORR 1 SPANISH-2001 Information technology C Open Systems Interconnection C Systems Management Time management function Technical Corrigendum 1《信息技术 开放系统互连 系统管理 时间管理功能 .pdf
  • ITU-T X 743 CORR 1-2001 Information technology C Open Systems Interconnection C Systems Management Time management function Technical Corrigendum 1 (Study Group 4)《信息技术 开放系统互连 系统管理.pdf ITU-T X 743 CORR 1-2001 Information technology C Open Systems Interconnection C Systems Management Time management function Technical Corrigendum 1 (Study Group 4)《信息技术 开放系统互连 系统管理.pdf
  • ITU-T X 743 FRENCH-1998 Information technology C Open Systems Interconnection C Systems Management Time management function《信息技术 开放系统互连 系统管理 时间管理功能 数据网络和开放系统通信开放系统互连管理 管理功能和开放型分布式.pdf ITU-T X 743 FRENCH-1998 Information technology C Open Systems Interconnection C Systems Management Time management function《信息技术 开放系统互连 系统管理 时间管理功能 数据网络和开放系统通信开放系统互连管理 管理功能和开放型分布式.pdf
  • ITU-T X 743 SPANISH-1998 Information technology C Open Systems Interconnection C Systems Management Time management function《信息技术 开放系统互连 系统管理 时间管理功能 X系列 数据网络和开放系统通信 开放系统互连(OSI)管理 管.pdf ITU-T X 743 SPANISH-1998 Information technology C Open Systems Interconnection C Systems Management Time management function《信息技术 开放系统互连 系统管理 时间管理功能 X系列 数据网络和开放系统通信 开放系统互连(OSI)管理 管.pdf
  • ITU-T X 743-1998 Information Technology - Open Systems Interconnection - Systems Management Time Management Function - Series X Data Networks and Open System Communications - OSI Mct.pdf ITU-T X 743-1998 Information Technology - Open Systems Interconnection - Systems Management Time Management Function - Series X Data Networks and Open System Communications - OSI Mct.pdf
  • 相关搜索

    当前位置:首页 > 标准规范 > 国际标准 > 其他

    copyright@ 2008-2019 麦多课文库(www.mydoc123.com)网站版权所有
    备案/许可证编号:苏ICP备17064731号-1