REG NASA-LLIS-0291--1993 Lessons Learned Design of Dust Covers for Systems Requiring Forced Air Ventilation (Such as Electronics Systems).pdf

上传人:赵齐羽 文档编号:1017939 上传时间:2019-03-21 格式:PDF 页数:3 大小:14.67KB
下载 相关 举报
REG NASA-LLIS-0291--1993 Lessons Learned Design of Dust Covers for Systems Requiring Forced Air Ventilation (Such as Electronics Systems).pdf_第1页
第1页 / 共3页
REG NASA-LLIS-0291--1993 Lessons Learned Design of Dust Covers for Systems Requiring Forced Air Ventilation (Such as Electronics Systems).pdf_第2页
第2页 / 共3页
REG NASA-LLIS-0291--1993 Lessons Learned Design of Dust Covers for Systems Requiring Forced Air Ventilation (Such as Electronics Systems).pdf_第3页
第3页 / 共3页
亲,该文档总共3页,全部预览完了,如果喜欢就下载吧!
资源描述

1、Lessons Learned Entry: 0291Lesson Info:a71 Lesson Number: 0291a71 Lesson Date: 1993-07-15a71 Submitting Organization: JSCa71 Submitted by: Larry GreggSubject: Design of Dust Covers for Systems Requiring Forced Air Ventilation (Such as Electronics Systems) Description of Driving Event: During burn-in

2、 testing of an orbiter General Purpose (Flight) Computer (GPC) in the JSC avionics engineering laboratory, a “fail to synchronize“ error was detected. This error indicates that the computer is out of synch with other GPCs involved in the test, and may be the result of a computer hardware problem. Th

3、e GPC in question was discovered to be very hot to the touch, and inspection of internal sensors indicated the GPC had been overheated beyond design limits. An ensuing investigation showed that the unit had operated without cooling for 11.5 hours due to failure to remove the ventilation system air d

4、uct cover prior to installation of the GPC in the test bed. This event was a direct result of not following installation procedures described in the Test Preparation Sheet (TPS). Additional factors contributing to this event included:A. The design of the cover plate for the GPC cooling duct did not

5、prevent installation of the GPC with the cover in place. Most of the cover plates used in the laboratory were modified with additional foam to preclude installation of the GPC without removing the cover.B. The alarm system used to monitor GPC cooling depended on vacuum sensing instead of positive ai

6、rflow indications. With the air duct cover in place, the vacuum sensor on the GPC in question showed a normal range reading even though there was no air flowing through the computer. The monitoring of an indirect parameter (vacuum) rather than a direct indication of absence of a critical parameter (

7、cooling air flow) or the existence of the hazardous condition of concern (temperature of the GPC) did not guarantee that proper cooling was provided.C. Only one junior technician was assigned to install the GPC. This was a violation of instructions on the TPS, which required two technicians to perfo

8、rm this task. As a result, the quality assurance assignee for the task helped to perform the installation procedure rather than performing his intended monitoring function.D. There was no formal program of training or certification in place for technicians in the laboratory. The training received wa

9、s principally an undetermined amount of on-the-job Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-training.Factory evaluation of the GPC involved in this event determined that it was fit for use only as a test or prototype unit and not as a flight u

10、nit. The difference in cost between a flight GPC and a test GPC is approximately $700,000.Lesson(s) Learned: Design of dust covers for ventilation systems which do not require their removal before hardware installation can result in equipment damage due to interruption of critical cooling air.Recomm

11、endation(s): Corrective actions recommended by the mishap investigation board include modification of all cooling duct covers to ensure that equipment cannot be installed without first removing the cover.Evidence of Recurrence Control Effectiveness: N/ADocuments Related to Lesson: N/AMission Directo

12、rate(s): N/AAdditional Key Phrase(s): a71 Test Articlea71 Test & VerificationAdditional Info: Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Approval Info: a71 Approval Date: 1993-09-13a71 Approval Name: Ron Montaguea71 Approval Organization: JSC/NS3a71 Approval Phone Number: 281-483-8576Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-

展开阅读全文
相关资源
猜你喜欢
  • BS QC 400203-1993 Specification for fixed resistors for use in electronic equipment Blank detail specification Fixed power resistors heat-sink types Assessment level H《电子设备用固定电阻器规范 空白详细规范 固定功率.pdf BS QC 400203-1993 Specification for fixed resistors for use in electronic equipment Blank detail specification Fixed power resistors heat-sink types Assessment level H《电子设备用固定电阻器规范 空白详细规范 固定功率.pdf
  • BS QC 760000-1990 Harmonized system of quality assessment for electronic components Film and hybrid film integrated circuits Generic specification《电子元器件质量评估协调体系 薄膜和混合薄膜集成电路 一般规范》.pdf BS QC 760000-1990 Harmonized system of quality assessment for electronic components Film and hybrid film integrated circuits Generic specification《电子元器件质量评估协调体系 薄膜和混合薄膜集成电路 一般规范》.pdf
  • BS S 148-1969 Specification for low nickel-chromium steel (bar for the manufacture of forged bolts only)《仅用于锻制螺栓的低镍-铬钢棒规范》.pdf BS S 148-1969 Specification for low nickel-chromium steel (bar for the manufacture of forged bolts only)《仅用于锻制螺栓的低镍-铬钢棒规范》.pdf
  • BS S 153-1976 Specification 21 2% nickel-chromium-molybdenum steel billets bars forgings and parts (1230-1430 MPa limiting ruling section 40 mm)《规范 5 2%镍-铬-钼钢方坯、棒材、锻件及零件(1230-1430MPa 限定等圆断面40mm)》.pdf BS S 153-1976 Specification 21 2% nickel-chromium-molybdenum steel billets bars forgings and parts (1230-1430 MPa limiting ruling section 40 mm)《规范 5 2%镍-铬-钼钢方坯、棒材、锻件及零件(1230-1430MPa 限定等圆断面40mm)》.pdf
  • BS S 154-1976 Specification 21 2% nickel-chromium-molybdenum steel billets bars forgings and parts (880-1080 MPa limiting ruling section 150 mm)《规范 5 2%镍-铬-钼钢方坯、棒材、锻件及零件规范(880-1080MPa 限定等圆断面150m.pdf BS S 154-1976 Specification 21 2% nickel-chromium-molybdenum steel billets bars forgings and parts (880-1080 MPa limiting ruling section 150 mm)《规范 5 2%镍-铬-钼钢方坯、棒材、锻件及零件规范(880-1080MPa 限定等圆断面150m.pdf
  • BS S 156-1976 Specification for 4% nickel-chromium-molybdenum case-hardening steel (vacuum arc remelted) billets bars forgings and parts (1320-1520 MPa)《4%镍-铬-钼表面硬化钢(真空电弧重熔)坯、棒材、锻件及零件规范(1320-1520M.pdf BS S 156-1976 Specification for 4% nickel-chromium-molybdenum case-hardening steel (vacuum arc remelted) billets bars forgings and parts (1320-1520 MPa)《4%镍-铬-钼表面硬化钢(真空电弧重熔)坯、棒材、锻件及零件规范(1320-1520M.pdf
  • BS S 157-1976 Specification 3% nickel-chromium-molybdenum case-hardening steel billets bars forgings and parts (1180-1380 MPa)《规范 3%镍-铬-钼表面硬化钢方坯、棒材、锻件及零件(1180-1380MPa)》.pdf BS S 157-1976 Specification 3% nickel-chromium-molybdenum case-hardening steel billets bars forgings and parts (1180-1380 MPa)《规范 3%镍-铬-钼表面硬化钢方坯、棒材、锻件及零件(1180-1380MPa)》.pdf
  • BS S 158-1977 Specification for 1% chromium-molybdenum steel bars for the manufacture of forged bolts and forged nuts《锻制螺栓和螺母的含1%铬-钼钢棒规范》.pdf BS S 158-1977 Specification for 1% chromium-molybdenum steel bars for the manufacture of forged bolts and forged nuts《锻制螺栓和螺母的含1%铬-钼钢棒规范》.pdf
  • BS S 162-1990 Specification for 18% nickel-cobalt-molybdenum maraging steel forging stock forgings bars and parts (1800 MPa double vaccuum melted)《锻坯、锻件、棒材和零件用18%镍-钴-钼马氏体时效钢(1800MPa 双倍真空熔化)规范》.pdf BS S 162-1990 Specification for 18% nickel-cobalt-molybdenum maraging steel forging stock forgings bars and parts (1800 MPa double vaccuum melted)《锻坯、锻件、棒材和零件用18%镍-钴-钼马氏体时效钢(1800MPa 双倍真空熔化)规范》.pdf
  • 相关搜索

    当前位置:首页 > 标准规范 > 国际标准 > 其他

    copyright@ 2008-2019 麦多课文库(www.mydoc123.com)网站版权所有
    备案/许可证编号:苏ICP备17064731号-1