REG NASA-LLIS-0479-1996 Lessons Learned - XTE Instrument Problems.pdf

上传人:cleanass300 文档编号:1018126 上传时间:2019-03-21 格式:PDF 页数:2 大小:13.10KB
下载 相关 举报
REG NASA-LLIS-0479-1996 Lessons Learned - XTE Instrument Problems.pdf_第1页
第1页 / 共2页
REG NASA-LLIS-0479-1996 Lessons Learned - XTE Instrument Problems.pdf_第2页
第2页 / 共2页
亲,该文档总共2页,全部预览完了,如果喜欢就下载吧!
资源描述

1、Lessons Learned Entry: 0479Lesson Info:a71 Lesson Number: 0479a71 Lesson Date: 1996-11-06a71 Submitting Organization: GSFCa71 Submitted by: Bill DavisSubject: XTE Instrument Problems Description of Driving Event: The XTE Instrument Development Team experienced monumental problems with the developmen

2、t of the three small proportional counter detectors used in the All Sky Monitor Instrument. This was completely unexpected since the proportional counters were presented by the Instrument Development Team as low-risk heritage detectors that were nearly identical to detectors that had previously flow

3、n many times.As it turned out, the heritage vendor was unsuccessful in fabricating a working detector. After an exhaustive search by the Instrument Development Team, a second vendor was located in Finland. It took the new vender over a year to fabricate, test, and deliver the required three flight a

4、nd one spare detector. Unfortunately, all of the detectors degraded after delivery and they needed multiple rework cycles of several months each to get acceptable flight detectors. The XTE Program Management Team was able to maintain the Mission schedule by installing degraded flight and/or spare de

5、tectors on the spacecraft during Observatory integration, testing, and launch site activities. The flight detectors were finally installed at the launch site.Lesson(s) Learned: There is no such thing as a low risk heritage detector. Each detector is one-of-a-kind and should be treated as a high risk

6、 item with an appropriate amount of contingency and a good risk mitigation plan. In addition, the XTE detector problem clearly showed the value of flight spare detectors (even if degraded) which can remain on the Observatory to maintain the Mission schedule while other detectors are reworked and qua

7、lified in parallel.Recommendation(s): Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-When developing Mission schedules plan enough schedule and cost contingencies to allow for multiple iterations in the integration of flight detectors with the space

8、craft.Evidence of Recurrence Control Effectiveness: N/ADocuments Related to Lesson: N/AMission Directorate(s): N/AAdditional Key Phrase(s): a71 Hardwarea71 Logisticsa71 Policy & Planninga71 Risk Management/AssessmentAdditional Info: Approval Info: a71 Approval Date: 1996-11-07a71 Approval Name: John W. Remeza71 Approval Organization: 302a71 Approval Phone Number: 301-286-7113Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-

展开阅读全文
相关资源
猜你喜欢
  • ASTM C1101 C1101M-2006(2012) Standard Test Methods for Classifying the Flexibility or Rigidity of Mineral Fiber Blanket and Board Insulation《矿物纤维毯和绝热板的柔性和刚性分类的标准试验方法》.pdf ASTM C1101 C1101M-2006(2012) Standard Test Methods for Classifying the Flexibility or Rigidity of Mineral Fiber Blanket and Board Insulation《矿物纤维毯和绝热板的柔性和刚性分类的标准试验方法》.pdf
  • ASTM C1101 C1101M-2006(2017) Standard Test Methods for Classifying the Flexibility or Rigidity of Mineral Fiber Blanket and Board Insulation《绝热矿物纤维毡及板挠性或刚性分类的标准试验方法》.pdf ASTM C1101 C1101M-2006(2017) Standard Test Methods for Classifying the Flexibility or Rigidity of Mineral Fiber Blanket and Board Insulation《绝热矿物纤维毡及板挠性或刚性分类的标准试验方法》.pdf
  • ASTM C1103-2003 Standard Practice for Joint Acceptance Testing of Installed Precast Concrete Pipe Sewer Lines《已安装的预制混凝土污水管线的接头验收试验的标准规程》.pdf ASTM C1103-2003 Standard Practice for Joint Acceptance Testing of Installed Precast Concrete Pipe Sewer Lines《已安装的预制混凝土污水管线的接头验收试验的标准规程》.pdf
  • ASTM C1103-2003(2009) Standard Practice for Joint Acceptance Testing of Installed Precast Concrete Pipe Sewer Lines《已安装的预制混凝土污水管线的接头验收试验的标准实施规程》.pdf ASTM C1103-2003(2009) Standard Practice for Joint Acceptance Testing of Installed Precast Concrete Pipe Sewer Lines《已安装的预制混凝土污水管线的接头验收试验的标准实施规程》.pdf
  • ASTM C1103-2014 Standard Practice for Joint Acceptance Testing of Installed Precast Concrete Pipe Sewer Lines《已安装的预制混凝土污水管线接头验收试验的标准实践规程》.pdf ASTM C1103-2014 Standard Practice for Joint Acceptance Testing of Installed Precast Concrete Pipe Sewer Lines《已安装的预制混凝土污水管线接头验收试验的标准实践规程》.pdf
  • ASTM C1103M-2003 Standard Practice for Joint Acceptance Testing of Installed Precast Concrete Pipe Sewer Lines (Metric)《已安装的预制混凝土污水管线的接头验收标准规程(米制)》.pdf ASTM C1103M-2003 Standard Practice for Joint Acceptance Testing of Installed Precast Concrete Pipe Sewer Lines (Metric)《已安装的预制混凝土污水管线的接头验收标准规程(米制)》.pdf
  • ASTM C1103M-2003(2009) Standard Practice for Joint Acceptance Testing of Installed Precast Concrete Pipe Sewer Lines (Metric)《已安装的预制混凝土污水管线的接头验收标准实施规程【米制单位】》.pdf ASTM C1103M-2003(2009) Standard Practice for Joint Acceptance Testing of Installed Precast Concrete Pipe Sewer Lines (Metric)《已安装的预制混凝土污水管线的接头验收标准实施规程【米制单位】》.pdf
  • ASTM C1103M-2014 Standard Practice for Joint Acceptance Testing of Installed Precast Concrete Pipe Sewer Lines (Metric)《已安装的预制混凝土污水管线 (米制) 接头验收试验的标准实践规程》.pdf ASTM C1103M-2014 Standard Practice for Joint Acceptance Testing of Installed Precast Concrete Pipe Sewer Lines (Metric)《已安装的预制混凝土污水管线 (米制) 接头验收试验的标准实践规程》.pdf
  • ASTM C1104 C1104M-2000(2006) Standard Test Method for Determining the Water Vapor Sorption of Unfaced Mineral Fiber Insulation《测定未覆面矿物纤维绝缘材料的水蒸汽吸收性的标准试验方法》.pdf ASTM C1104 C1104M-2000(2006) Standard Test Method for Determining the Water Vapor Sorption of Unfaced Mineral Fiber Insulation《测定未覆面矿物纤维绝缘材料的水蒸汽吸收性的标准试验方法》.pdf
  • 相关搜索

    当前位置:首页 > 标准规范 > 国际标准 > 其他

    copyright@ 2008-2019 麦多课文库(www.mydoc123.com)网站版权所有
    备案/许可证编号:苏ICP备17064731号-1