1、05-01-12 10 21 13 - 1 SECTION 10 21 13 TOILET COMPARTMENTS SPEC WRITER NOTES: 1. Delete between /_/ if not applicable to project. Also delete any other item or paragraph not applicable in the section and renumber the paragraphs. 2. See VA Standard Details 10162-1 and 10162-2. 3. See 40 CFR 247 for g

2、uidelines on the use of recycled materials. PART 1 - GENERAL 1.1 DESCRIPTION This section specifies / metal / solid phenolic / solid polyethylene / toilet partitions, / and / urinal screens, / and / entrance screens. 1.2 RELATED WORK A. Overhead structural steel supports for ceiling hung pilasters:

3、Section 05 50 00, METAL FABRICATIONS. B. Color of baked enamel finish: Section 09 06 00, SCHEDULE FOR FINISHES. C. Grab bars and toilet tissue holders: Section 10 28 00, TOILET, BATH, AND LAUNDRY ACCESSORIES. 1.3 SUBMITTALS A. Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA,

4、AND SAMPLES. B. Samples: Prime coat of paint on 150 mm (six-inch) square of metal panel with baked enamel finish coat over half of panel. C. Manufacturers Literature and Data: Specified items indicating all hardware and fittings, material, finish, and latching. D. Shop Drawings: Construction details

5、 at 1/2 scale, showing installation details, anchoring and leveling devices. E. Manufacturers certificate, attesting that zinc-coatings conform to specified requirements. 1.4 APPLICABLE PUBLICATIONS A. Publications listed below form a part of this specification to the extent referenced. Publications

6、 are referenced in the text by the basic designation only. B. Federal Specifications (Fed. Spec.): FF-B-575C Bolt, Hexagon and Square Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-05-01-12 10 21 13 - 2 C. Code of Federal Regulations (CFR): 40 CFR 2

7、47 . Comprehensive Procurement Guidelines for Products Containing Recovered Materials D. Commercial Item Descriptions (CID): A-A-1925 . Shield, Expansion (Nail Anchors) A-A-60003 Partitions, Toilet, Complete PART 2 - PRODUCTS SPEC WRITER NOTE: 1. Use of ceiling hung toilet partitions and entrance sc

8、reens is required at not more than 2400 mm (8 ft) ceiling height to provide stability and resistance to lateral force. 2. Verify drawings show dropped ceiling for support of pilasters at 2400 mm (8 ft) height. 3. Use of other support methods, for floor and overhead bracing will be permitted only wit

9、h written permission. Do not use cantilevered or wall hung assemblies. 2.1 TOILET PARTITIONS: A. /Solid phenolic / solid polyethylene /: water resistant; graffiti resistant; non-absorbent; contain a minimum 30 percent post consumer recycled plastic; Class C flame spread rating. B. Conform to Fed. CI

10、D A-A-60003, except as modified herein. C. Fabricate to dimensions shown or specified. D. Toilet Enclosures: 1. Type 1, Style B (Ceiling hung) / A (Floor supported). / C (overhead braced) /. 2. Reinforce panels shown to receive toilet tissue holders or grab bars. 3. Upper pivots and lower hinges adj

11、ustable to hold doors open 30 degrees. 4. Latching devices and hinges for handicap compartments shall comply with ADA requirements. 5. Keeper: a. U-slot to engage bar of throw latch. b. Combined with rubber bumper stop. 6. Wheelchair Toilets: a. Upper pivots and lower hinges to hold out swinging doo

12、rs in closed position. b. Provide U-type doors pulls, approximately 100 mm (four inches) long on pull side. Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-05-01-12 10 21 13 - 3 7. Finish: a. Finish 1 (baked enamel) on steel doors, pilasters, and enc

13、losure panels except those adjacent to urinals and as specified. b. Finish 3 (stainless steel) on panel of enclosure panels adjacent to urinals / and on dividing partitions used in Spinal Cord Injury (SCI) Bowel Training Area /. SPEC WRITER NOTE: Use bracket with not less than four anchor bolts each

14、 side full height of screen. E. Urinal Screens: 1. Type III, Style E (wall hung), finish 2 or 3. a. With integral flanges and continuous, full height wall anchor plate. b. Option: Full height U-Type bracket. c. Wall anchor plate drilled for 4 anchors on both sides of screen. 2. Screen 600 mm (24 inc

15、hes) wide and 1060 mm (42 inches high). F. Room Entrance Screens: 1. Type II, Style B, (ceiling hung) / style A (Floor supported) / style C (Overhead Braced) / Style E (Floor-to-ceiling Post Supported) /. 2. Self-closing doors swinging into the toilet room. 3. Provide door pull on pull side and flat

16、 stainless steel push plate 250 mm by 70 mm (10 inches by 2-3/4 inches) with beveled ground edges, locate 1200 mm (four feet) above floor. 4. Provide door stop with rubber bumper on pilaster opposite pull. 5. Where doors open against wall, provide rubber tipped bumpers having a three inch projection

17、 at point of contact of top edge of door. 6. Finish the same as toilet enclosures. 2.2 FASTENERS A. Partition Fasteners: CID A-A-60003. B. Use expansion bolts, CID A-A-60003, for anchoring to solid masonry or concrete. C. Use toggle bolts, CID A-A-60003, for anchoring to hollow masonry or stud fram

18、ed walls. D. Use steel bolts FS-B-575, for anchoring pilasters to overhead steel supports. PART 3 - EXECUTION 3.1 INSTALLATION A. General: 1. Install in rigid manner, straight, plumb and with all horizontal lines level. Provided by IHSNot for ResaleNo reproduction or networking permitted without lic

19、ense from IHS-,-,-05-01-12 10 21 13 - 4 2. Conceal evidence of drilling, cutting and fitting in finish work. 3. Use hex-bolts for through-bolting. 4. Adjust hardware and leave in freely working order. 5. Clean finished surfaces and leave free of imperfections. B. Panels and Pilasters: 1. Support pan

20、els, except urinal screens, and pilaster abutting building walls near top and bottom by stirrup supports secured to partitions with through-bolts. 2. Secure stirrups to walls with two suitable anchoring devices for each stirrup. 3. Secure panels to faces of pilaster near top and bottom with stirrup

21、supports, through-bolted to panels and machine screwed to each pilaster. 4. Secure edges of panels to edges of pilasters near top and bottom with “U“ shaped brackets. /5. Where overhead braced, secure pilasters to building walls by headrails clamped on or set into top of each pilaster. a. Secure cla

22、mps to pilasters with two through-bolts to each clamp. b. When headrails are set into pilasters, through-bolt them to the pilasters. c. Support headrails on wall flange fittings secured to building walls with minimum of two anchor bolts to each flange fitting. / C. Urinal Screens: 1. Anchor urinal screen flange to walls with minimum of four bolts both side of panel. 2. Space anchors at top and bottom and equally in between. - - - E N D - - - Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-

展开阅读全文
相关资源
猜你喜欢
  • EN 736-3-2008 en Valves - Terminology - Part 3 Definition of terms《阀门 术语 第3部分 术语的定义》.pdf EN 736-3-2008 en Valves - Terminology - Part 3 Definition of terms《阀门 术语 第3部分 术语的定义》.pdf
  • EN 74-1-2005 en Couplers spigot pins and baseplates for use in falsework and scaffolds - Part 1 Couplers for tubes - Requirements and test procedures《脚手架和支承架用联结件 中心螺栓和踏板 第1部分 钢管用联结.pdf EN 74-1-2005 en Couplers spigot pins and baseplates for use in falsework and scaffolds - Part 1 Couplers for tubes - Requirements and test procedures《脚手架和支承架用联结件 中心螺栓和踏板 第1部分 钢管用联结.pdf
  • EN 74-2-2008 en Couplers spigot pins and baseplates for use in falsework and scaffolds - Part 2 Special couplers - Requirements and test procedures《脚手架和支撑架用联接件 定位销和底板 第2部分 特殊联接件 要求.pdf EN 74-2-2008 en Couplers spigot pins and baseplates for use in falsework and scaffolds - Part 2 Special couplers - Requirements and test procedures《脚手架和支撑架用联接件 定位销和底板 第2部分 特殊联接件 要求.pdf
  • EN 74-3-2007 en Couplers spigot pins and baseplates for use in falsework and scaffolds - Part 3 Plain base plates and spigot pins - Requirements and test procedures《脚手架和支承架用连接件 定位销.pdf EN 74-3-2007 en Couplers spigot pins and baseplates for use in falsework and scaffolds - Part 3 Plain base plates and spigot pins - Requirements and test procedures《脚手架和支承架用连接件 定位销.pdf
  • EN 741-2000 en Continuous handling equipment and systems - Safety requirements for systems and their components for pneumatic handling of bulk materials (Incorporates Amendment A1 .pdf EN 741-2000 en Continuous handling equipment and systems - Safety requirements for systems and their components for pneumatic handling of bulk materials (Incorporates Amendment A1 .pdf
  • EN 744-1995 en Plastics Piping and Ducting Systems - Thermoplastics Pipes - Test Method for Resistance to External Blows by the Round-the- Clock Method《塑料管道和导管系统 热塑管 耐连续吹风的试验方法》.pdf EN 744-1995 en Plastics Piping and Ducting Systems - Thermoplastics Pipes - Test Method for Resistance to External Blows by the Round-the- Clock Method《塑料管道和导管系统 热塑管 耐连续吹风的试验方法》.pdf
  • EN 746-1-1997 en Industrial thermoprocessing equipment - Part 1 Common safety requirements for industrial thermoprocessing equipment (Incorporates Amendment A1 2009)《工业热处理设备 第1部分 工.pdf EN 746-1-1997 en Industrial thermoprocessing equipment - Part 1 Common safety requirements for industrial thermoprocessing equipment (Incorporates Amendment A1 2009)《工业热处理设备 第1部分 工.pdf
  • EN 746-2-2010 en Industrial thermoprocessing equipment - Safety requirements for combustion and fuel handling systems《工业热加工工艺设备 燃烧和燃料储运系统安全要求》.pdf EN 746-2-2010 en Industrial thermoprocessing equipment - Safety requirements for combustion and fuel handling systems《工业热加工工艺设备 燃烧和燃料储运系统安全要求》.pdf
  • EN 746-3-1997 en Industrial thermoprocessing equipment - Part 3 Safety requirements for the generation and use of atmosphere gases (Incorporates Amendment A1 2009)《工业热处理设备 第3部分 环境气.pdf EN 746-3-1997 en Industrial thermoprocessing equipment - Part 3 Safety requirements for the generation and use of atmosphere gases (Incorporates Amendment A1 2009)《工业热处理设备 第3部分 环境气.pdf
  • 相关搜索

    当前位置:首页 > 标准规范 > 国际标准 > 其他

    copyright@ 2008-2019 麦多课文库(www.mydoc123.com)网站版权所有
    备案/许可证编号:苏ICP备17064731号-1