1、11-11 11 12 00 - 1 SECTION 11 12 00 PARKING CONTROL EQUIPMENT SPEC WRITER NOTES: 1. Delete between /-/ if not applicable to project. Also delete any other items or paragraphs not applicable in section and renumber paragraphs. 2. This section includes parking gate arm and activator units, devices for
2、 card, key, or remote controlled access, and vehicle detection activators. 3. This section is for employee access to restricted employee parking areas. Can not use parking control equipment for patient parking areas. PART 1 GENERAL: 1.1 DESCRIPTION: A. Section Includes: 1. Automatic Barrier Gates. 2
3、. Vehicle Detectors. 3. Card Control Units. 1.2 RELATED WORK: A. Asphaltic paving: Section 32 12 16, ASPHALT PAVING. B. Concrete paving: Section 32 05 23, CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS. C. Concrete foundation work: Section 03 30 00, CAST-IN-PLACE CONCRETE. D. Color and texture: Secti
4、on 09 06 00, SCHEDULE FOR FINISHES. E. Conduit placement for equipment: Section 26 05 33, RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS, Section 27 05 33, RACEWAYS AND BOXES FOR COMMUNICATIONS SYSTEMS and Section 28 05 33, RACEWAYS AND BOXES FOR ELECTRONIC SAFETY AND SECURITY. F. Power supply to disconne
5、ct, junction box, in gate arm unit: Section 26 05 21, LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES (600 VOLTS AND BELOW), Section 27 10 00, STRUCTURED CABLING and Section 28 05 13, CONDUCTORS AND CABLES FOR ELECTRONIC SAFETY AND SECURITY. G. Electrical characteristics and wiring connections: S
6、ection 26 27 26, WIRING DEVICES. Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-11-11 11 12 00 - 2 1.3 QUALITY CONTROL: A. Qualifications: 1. Approval by Contracting Officer is required of products or service of proposed manufacturer, suppliers, and
7、 installers, and will be based upon submission by Contractor of certification that: a. Installer: Approved by manufacturer of materials and has technical qualifications, experience, trained personnel and facilities to install specified items. b. Manufacturers product submitted has been in satisfacto
8、ry operation, on three installations similar and equivalent in size to this project, for three years. Submit list of installations. 2. Maintenance Proximity: Installer shall maintain a place of business with maintenance facilities not more than two (2) hours normal travel time from project site. 3.
9、UL and NEMA Compliance: Provide internal electrical components required as part of parking control equipment that are listed by UL and comply with applicable NEMA standards. 4. Single-Source Responsibility: Obtain parking control equipment from one source and from a single manufacturer. 1.4 SUBMITTA
10、LS: A. In accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES, submit following: 1. Manufacturers Literature and Data: a. Description of parking control equipment material and accessories to be provided. b. Provide data on operating equipment, characteristics and limitations,
11、and operating temperature ranges. 2. Samples: a. Submit two samples of access cards and security program, illustrating size, and coding method. 3. Shop Drawings and Certificates: Indicate plan layout of equipment access lanes, mounting bolt dimensions, conduit and outlet locations, power requirement
12、s, and conformation of building electrical requirements. Provide Contractor with mounting bolt template in time for installation. 4. Wiring Diagrams: Detailing wiring for parking control equipment operator, signal, and control systems differentiating clearly between manufacturer-installed wiring and
13、 field-installed wiring. Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-11-11 11 12 00 - 3 a. Show locations of connections to electrical service provided as a unit of work under other Divisions. 5. Maintenance Data: For parking control equipment co
14、mponents for inclusion in Operating and Maintenance Manuals, include the following: a. Maintenance Instructions: Provide manufacturers instructions for maintenance of parking control equipment. 1) Include recommended methods and frequency for maintaining equipment in optimum operating condition unde
15、r anticipated traffic and use conditions. 2) Include precautions against materials and methods that may be detrimental to finishes and performance. 3) Lubrication Schedule and Information: Provide lubrication and periodic maintenance requirement schedules including parts list and parts numbers. 6. O
16、peration Data: Provide operating data for operating equipment, including clock timer, changing security access code, and any other pertinent information required for Government operation. 7. Certificates: Quality Control Certificate Submittals and lists specified in paragraph, QUALIFICATIONS. B. In
17、accordance with Section 00 72 00, GENERAL CONDITIONS, submit following at project closeout: Guaranty. C. In accordance with Section 01 00 00, GENERAL REQUIREMENTS, submit following at project closeout: 1. Project Record Documents: Record actual locations of concealed conduit and vehicle detection ac
18、tivators. SPEC WRITER NOTE: Use Article below if special code, regulation, applies to the project; delete this article if none apply. 1.5 REGULATORY REQUIREMENTS: A. Conform to / applicable /_/ code for fire/ambulance emergency vehicle access. B. Products Requiring Electrical Connection: Listed and
19、classified by / UL / testing firm acceptable to authority having jurisdiction / as suitable for purpose specified and indicated. 1.6 PROJECT CONDITIONS: A. Coordinate placement of conduit, accessories, and power wiring to operating equipment. Provided by IHSNot for ResaleNo reproduction or networkin
20、g permitted without license from IHS-,-,-11-11 11 12 00 - 4 B. Sequence installation to ensure utility connections are achieved in an orderly and expeditious manner. 1.7 DELIVERY, STORAGE AND HANDLING: A. Deliver materials to site in original sealed packages or containers; labeled for identification
21、 with manufacturers name and brand. B. Store materials in weathertight and dry storage facility. Protect from damage due to handling, weather, and construction operations before, during and after installation. 1.8 APPLICABLE PUBLICATIONS: A. Publications listed below form a part of this specificatio
22、n to extent referenced. Publications are referenced in text by basic designation only. B. American Society for Testing Materials (ASTM): A153/A153M-09 Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware. A500-10 Standard Specification for Cold-Formed Welded and Seamless Carb
23、on Steel Structural Tubing in Rounds and Shapes. A653/A653M-10 Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) by the Hot-Dip Process, Structural (Physical) Quality. C. National Electrical Manufacturers Association (NEMA): MG 1-09(R2010) . Motors and Generators. D. National Fire Pro
24、tection Association (NFPA): 70-11 National Electrical Code. E. Underwriters Laboratories Inc. (UL): Electrical Appliance and Utilization Equipment Directory. 1.9 SYSTEM DESCRIPTION: A. Parking Control System: / Attended / Automatic / operation at entrance and / attended / automatic / operation at ex
25、it. B. Design: Protect against interference or damage by lightning or other electrical influence; include fuse, over-voltage protection, flash-over protection, and line filter. C. Entry Automatic Gate Arm Control: Electrically operated upon / insertion of coded card / insertion of pass key / detecti
26、on of vehicle by sensing loop buried in pavement /. / Activate automatic arm reversing switch if an obstacle is sensed in downward motion. / Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-11-11 11 12 00 - 5 D. Exit Automatic Gate Arm Control: Electr
27、ically operated upon / detection of vehicle by sensing loop buried in pavement / insertion of coded card / insertion of pass key /. / Activate automatic arm reversing switch if an obstacle is sensed in the downward motion. / 1.10 SCHEDULING: SPEC WRITER NOTE: Provide one or more of following subpara
28、graph types appropriate to site equipment requirements. Provide a schedule when differing components may be required at different locations. A. Name Street Gate: Automatic key card operation, single gate arm, single gate exit arm activated with loop detector in pavement, and heated cabinets. B. Empl
29、oyee Gate: Automatic coded card operation, double entrance, each with gate arms, double gate exit arm activated with key card. 1.11 WARRANTY A. Submit manufacturers written warranty for materials and installation in accordance with FAR clause 52.246-21. 1. Warranty: Cover keeping equipment operation
30、al. 2. Final Acceptance: Requirement for final acceptance shall be continued acceptable use of parking control equipment without a breakdown or stoppage for a period of fifteen (15) calendar days after final acceptance of project by Government. PART 2 PRODUCTS 2.1 MATERIALS: A. Iron and Steel Hardwa
31、re: ASTM A153; Zinc coating (hot-dip) on iron and steel hardware. B. Steel: ASTM A653/A653M; Galvanized to / G90 / Z275 /_/. C. Structural tubing in rounds and shapes: A500; Cold-Formed Welded and Seamless Carbon Steel Structural Tubing in Rounds and Shapes. D. Wood: / Clear fir. / Clear cedar. /_./
32、 2.2 AUTOMATIC GATE: A. Provide UL approved automatic barrier gate parking access-control system. SPEC WRITER NOTE: Coordinate with manufacturer and revise next paragraph if aluminum cabinets are required. B. Cabinet: 1.9 /_/ mm, (/ 0.075 /_/ inch) minimum cold-rolled steel sheet cabinet, welded and
33、 weather tight seams, reinforced Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-11-11 11 12 00 - 6 internally with welded steel angle framing, thermally insulated to permit heater to maintain cabinet temperature to equipment operating minimum, flush
34、 access doors and panels, tamper proof hardware, weather tight gaskets, / master keyed /_/ locks; furnish two (2) keys for each gate, keyed alike. Conceal mounting bolts inside units: 1. Finish cabinet, interior and exterior, with manufacturers standard / white baked enamel finish over primer system
35、. / color as indicated in Section 09 06 00, SCHEDULE FOR FINISHES. / C. Arm Control: Mechanism to raise and lower arm by instant reversing electric motor, enclosed speed reducer operated by self contained, plug-in replaceable controller. Design mechanism with slip clutch to prevent breakage if arm i
36、s forced, and to permit manual operation if required. Arm movement to stop and start at reduced speed. Components of / zinc /_/ coated steel. D. Electrical Components: Self-contained, plug-in, replaceable components. Include wiring for control units, zinc plated connection box, grounded convenience
37、outlet, switch for automatic or manual operation, switch to disconnect power unit, thermostatically controlled minimum / 250 /_/ Watt heater strip with control switch and preset thermostat, and thermal protection disconnect for motor. 2.3 ELECTRICAL CHARACTERISTICS AND COMPONENTS: SPEC WRITER NOTE:
38、Select one or more of following subparagraphs appropriate to equipment requirements. A. Electrical Characteristics: 1. Provide 1/3 /_/ hp (/_/ W.) ( /_/ rated load amperes.) 2. Provide 115 /_/ volts AC, / single / three / phase, 60 Hz. 3. Provide /_/ amperes maximum / fuse size / circuit breaker siz
39、e / overcurrent protection /. (/_/ minimum circuit capacity.) 4. Provide /_/ percent minimum power factor at rated load. 5. Refer to Section 26 27 26, WIRING DEVICES: Electrical connections. B. Motor: Instant reversing motor for operation of gate arm. / Refer to Section 11 05 12, GENERAL MOTOR REQUI
40、REMENTS FOR EQUIPMENT, Section 21 05 12, GENERAL MOTOR REQUIREMENTS FOR FIRE-SUPPRESSION, Section 22 05 12, GENERAL MOTOR REQUIREMENTS FOR PLUMBING EQUIPMENT, Section 23 05 Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-11-11 11 12 00 - 7 12, GENERA
41、L MOTOR REQUIREMENTS FOR HVAC AND STEAM GENERATION EQUIPMENT and Section 26 29 21, DISCONNECT SWITCHES. / NEMA MG1, /_/. C. Controls: Transmit power to gate arm drive shaft through a harmonic acting crank and connecting rod. Fabricate cranks, rod, and drive shaft of galvanized solid bar steel. /_/.
42、D. Wiring Terminations: Provide terminal lugs to match branch circuit conductor quantities, sizes, and materials indicated. Enclose terminal lugs in terminal box sized to NFPA 70. E. Disconnect Switch: Factory mount disconnect switch / in control panel. / on equipment under provisions of Section 26
43、29 21, DISCONNECT SWITCHES. / 2.4 ARM AND SUPPORT: A. Gate Arm: Fabricate gate arm of nominal 25 mm (1 inch) thick, length as indicated, of / Wood / Aluminum /_/, one piece arm, / articulating arm with internal counterbalance /, (/ with safety rubber bottom edge / and automatic instant reversing arm
44、 mechanism that stops downward motion of gates if arm strikes an object, and returning arm immediately to upward position. Equip mechanism with a 0 to 60 second variable time reset device. /). 1. Finish with manufacturers standard coating system with black diagonal stripes on traffic side face. B. A
45、rm Clamp: / Cast metal /_/, quick change clamp and hub bracket, to permit rapid replacement of arm without fitting or drilling. Provide breakaway feature to ensure clean break if arm is struck. SPEC WRITER NOTE: Use Articles below if special length constructed assembly applies to project; delete thi
46、s article if none apply. C. End support post required for gate arm of 4.3 m (14 feet) or longer. D. End Support Post: 50 /_/ mm (/ 2 /_/ inch) / square / round / steel tubular section; 1940 /_/ mm (/ 37 /_/ inches) high, 3.4 mm, (0.135 inch) minimum wall thickness; with alignment bracket, closed cap
47、 and baseplate. E. Padlocking Feature: To lock gate arm in either open or closed position, if required. 2.5 / CARD / KEY / CONTROL: A. General: Provide pedestal mounted card control units to activate barrier gates. Provided by IHSNot for ResaleNo reproduction or networking permitted without license
48、from IHS-,-,-11-11 11 12 00 - 8 B. Control Unit: To activate gate arm by / insertion of coded card / pass key /; /_/ manufactured by /_/. C. Cabinet: 1.9 mm (0.075 inch) minimum welded cold-rolled steel sheet, weather tight seams; thermally insulated to permit heater to maintain cabinet temperature to equipment operating minimum, flush access doors and panels, tamper proof flush mounted lock hardware and two (2) keys