JEDEC JESD246-2014 Customer Notification Process for Disasters.pdf

上传人:fatcommittee260 文档编号:807152 上传时间:2019-02-05 格式:PDF 页数:10 大小:55.84KB
下载 相关 举报
JEDEC JESD246-2014 Customer Notification Process for Disasters.pdf_第1页
第1页 / 共10页
JEDEC JESD246-2014 Customer Notification Process for Disasters.pdf_第2页
第2页 / 共10页
JEDEC JESD246-2014 Customer Notification Process for Disasters.pdf_第3页
第3页 / 共10页
JEDEC JESD246-2014 Customer Notification Process for Disasters.pdf_第4页
第4页 / 共10页
JEDEC JESD246-2014 Customer Notification Process for Disasters.pdf_第5页
第5页 / 共10页
点击查看更多>>
资源描述

1、JEDEC STANDARD Customer Notification Process for Disasters JESD246 JANUARY 2014 JEDEC SOLID STATE TECHNOLOGY ASSOCIATION NOTICE JEDEC standards and publications contain material that has been prepared, reviewed, and approved through the JEDEC Board of Directors level and subsequently reviewed and ap

2、proved by the JEDEC legal counsel. JEDEC standards and publications are designed to serve the public interest through eliminating misunderstandings between manufacturers and purchasers, facilitating interchangeability and improvement of products, and assisting the purchaser in selecting and obtainin

3、g with minimum delay the proper product for use by those other than JEDEC members, whether the standard is to be used either domestically or internationally. JEDEC standards and publications are adopted without regard to whether or not their adoption may involve patents or articles, materials, or pr

4、ocesses. By such action JEDEC does not assume any liability to any patent owner, nor does it assume any obligation whatever to parties adopting the JEDEC standards or publications. The information included in JEDEC standards and publications represents a sound approach to product specification and a

5、pplication, principally from the solid state device manufacturer viewpoint. Within the JEDEC organization there are procedures whereby a JEDEC standard or publication may be further processed and ultimately become an ANSI standard. No claims to be in conformance with this standard may be made unless

6、 all requirements stated in the standard are met. Inquiries, comments, and suggestions relative to the content of this JEDEC standard or publication should be addressed to JEDEC at the address below, or refer to www.jedec.org under Standards and Documents for alternative contact information. Publish

7、ed by JEDEC Solid State Technology Association 2014 3103 North 10th Street Suite 240 South Arlington, VA 22201-2107 This document may be downloaded free of charge; however JEDEC retains the copyright on this material. By downloading this file the individual agrees not to charge for or resell the res

8、ulting material. PRICE: Contact JEDEC Printed in the U.S.A. All rights reserved PLEASE! DONT VIOLATE THE LAW! This document is copyrighted by JEDEC and may not be reproduced without permission. For information, contact: JEDEC Solid State Technology Association 3103 North 10th Street Suite 240 South

9、Arlington, VA 22201-2107 or refer to www.jedec.org under Standards-Documents/Copyright Information. JEDEC Standard No. 246 Page 1 CUSTOMER NOTIFICATION PROCESS FOR DISASTERS (From JEDEC Board Ballot JCB-13-61, formulated under the cognizance of JC-14.4 Committee on Quality Processes and Methods.) 1

10、Scope This standard is applicable to suppliers of, and affected customers for, solid-state products and the constituent components used within. This standard establishes the requirements for timely notification to affected customers after a disaster has occurred at a suppliers facility that will aff

11、ect the committed delivery of product. This standard puts specific emphasis on notification, timing, and notification content which includes risk exposure, impact analysis, and recovery plans. Notified customers will then be able to take appropriate action to minimize the impact on the production of

12、 their own products and shipments to their customers. This will help to ensure continuity of supply within the entire supply chain. This standard allows the use of a suppliers existing practices and procedures from any organization within the company (e.g., fulfillment, logistics, sales, marketing,

13、customer service, quality, etc.,) to be used to fulfill the requirements of this standard. This standard may be used as a part of a companys overall Disaster Recovery process. 2 Terms and definitions For the purpose of this standard, the following terms and definitions apply. affected customer: Any

14、organization that 1) is to receive product from the supplier, but the agreed to shipment date of that product is impacted due to a disaster, and that organization has a contract or purchase agreement with Disaster notification requirements; or 2) has requested (and the supplier has agreed to provide

15、) Disaster notifications; or 3) is an approved supplier agent. disaster: Any external hazard (natural or man-made) that has come to fruition, resulting in an event of substantial proportions causing a significant disruption of production that will affect the committed delivery and/or quality of prod

16、uct. NOTE Examples include earthquake, typhoon, tornado, political unrest, and labor strike. JEDEC Standard No. 246 Page 2 3 Notification requirements Notification is required when committed customer shipments are affected. Notifications, both initial and subsequent, may be handled by any of a suppl

17、iers organizations (e.g., fulfillment, logistics, sales, marketing, customer service, quality, etc.,). If customer shipments are not affected by a disaster, but the supplier has a facility near the location of the disaster, it is recommended that a notice be sent out to customers acknowledging the d

18、isaster, but that production shipments have not been disrupted. Alternatively, a general press release may be issued per a suppliers established procedures acknowledging that a disaster has occurred near the suppliers location. NOTE This document does not address minor operating problems and/or dela

19、ys that can be resolved in the normal course of business as per supplier/customer agreements and/or standard business practices and procedures. 3.1 Timing 3.1.1 Supplier with initial direct impact 3.1.1.1 Initial notification If a suppliers operations are directly affected by a disaster (e.g., suppl

20、iers assembly facility was damaged), the supplier shall notify their affected customers of the disasters occurrence as soon as possible, but no longer than one week from when the disaster occurred or when production was disrupted, or within a timeframe agreed to between supplier and customer. NOTE B

21、eyond the requirement of the initial notice being sent out within one week, it is recommended that a brief notice be sent within 1 to 2 days of the disasters occurrence stating whether a facility within the disaster area was affected. 3.1.1.2 Subsequent notification The timing of subsequent notifica

22、tions shall be appropriate for the level of risk exposure (a minimum of weekly is recommended for high risk exposure), or be sent based on a supplier/customer agreed to timeframe, and continue until they are no longer required. 3.1.2 Supplier with subsequent indirect impact Affected customers, who a

23、fter notification from their supplier have determined that their own production will be disrupted due to this disaster (indirect impact), must inform their affected customers per the requirements of 3.1.1. The clock for notifying affected customers does not start until it is determined that committe

24、d shipments cannot be met. However a general notice is still recommended, if it will take longer than a week to determine the extent of indirect impact. JEDEC Standard No. 246 Page 3 3.2 Format The Disaster Notification notice shall be sent in writing or electronically to the affected customer or th

25、e affected customers designated agent. The initial notification must be sent to the affected customer, but subsequent notifications and communication may be managed via email, website, or as per supplier/customer agreement. A press release may be used by the supplier as a general notification to all

26、 of its customers acknowledging that a disaster has occurred near one of its facilities. 3.3 Content Notifications shall state all affected supplier part numbers; however, it is likely that a complete list of affected part numbers will not be available for the initial notification, and may take seve

27、ral weeks to compile. Customer part numbers are optional, if not required per agreed to customer criteria. The content of the first and possibly some subsequent notifications may be limited due to the scope of the disaster and availability of information. 3.3.1 Initial notification The initial notif

28、ication shall include the following information (if available): 3.3.1.1 Initial risk exposure The supplier shall rate the risk exposure of not meeting committed shipment dates due to the disaster according the criteria in Table 1. Table 1 Initial Risk Exposure Ratings High Production impacted. No ot

29、her site can support. Medium Production impacted. Alternate site can support, but start up and/or some qualification required before shipments can be made. Low Production impacted. Alternate site is qualified, but may not be able to meet committed delivery dates (e.g., limited production capacity).

30、None Production not impacted, or the supplier can support all deliveries with current inventory and/or production from an alternate, qualified site. NOTE The level of risk may vary by product (e.g., Products A and B have medium risk, but product C is rated as none) and/or by supplier/customer agreem

31、ents. 3.3.1.2 Initial impact analysis The supplier shall provide a general description of the damage to facilities, equipment, and/or processes for the affected product(s), if available. JEDEC Standard No. 246 Page 4 3.3.2 Subsequent notifications Subsequent notifications shall include the informati

32、on stated per the following four subclauses, as it becomes available: 3.3.2.1 Risk exposure It is recommended that the risk exposure rating per the criteria in Table 2 be included in subsequent notifications, but is required to be included if the rating has changed from a previous notification. Tabl

33、e 2 Subsequent Risk Exposure Ratings High Production impacted. No other site can support. Medium Production impacted. Alternate site can support, but start up and/or some qualification required before shipments can be made. Low Production impacted. Alternate site is qualified, but may not be able to

34、 meet committed delivery dates (e.g., limited production capacity). None Production not impacted, or the supplier can support all deliveries with current inventory and/or production from an alternate, qualified site. NOTE The level of risk may vary by product (e.g., Products A and B have medium risk

35、, but product C is rated as none) and/or by supplier/customer agreements. 3.3.2.2 Impact analysis The supplier shall provide details describing the impact for the affected product(s). This may include, but is not limited to: - general description of damage to facilities, equipment, and/or processes;

36、 - alternate processes, materials, and/or facilities and any qualification testing required to reinstate production (This information may be conveyed per the processes stated in JESD46.); and - any other testing required to reinstate production or assessment of product awaiting shipment from the aff

37、ected facility that may have been damaged by the disaster. 3.3.2.3 Alternative source The supplier shall assist affected customers by providing information and technical data to help locate an alternate source, if applicable. If the alternate source does not meet the same level of functionality, qua

38、lity, and reliability, the supplier must point this out to the affected customer prior to shipment. 3.3.2.4 Recovery plan Supplier shall provide a recovery plan for the affected shipments with target dates. Existing Procurement and Logistic tools may be used for the notification to changes in “ship

39、to” dates. Standard Improvement Form JEDEC JESD246 The purpose of this form is to provide the Technical Committees of JEDEC with input from the industry regarding usage of the subject standard. Individuals or companies are invited to submit comments to JEDEC. All comments will be collected and dispe

40、rsed to the appropriate committee(s). If you can provide input, please complete this form and return to: JEDEC Attn: Publications Department 3103 North 10thStreet Suite 240 South Arlington, VA 22201-2107 Fax: 703.907.7583 1. I recommend changes to the following: Requirement, clause number Test method number Clause number The referenced clause number has proven to be: Unclear Too Rigid In Error Other 2. Recommendations for correction: 3. Other suggestions for document improvement: Submitted by Name: Phone: Company: E-mail: Address: City/State/Zip: Date: