1、*USACE / NAVFAC / AFCESA / NASA UFGS-23 09 33.00 40 (August 2010)-Preparing Activity: NASA SupersedingUFGS-23 09 33.00 40 (August 2009)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement with UMRL dated July 2010*SECTION TABLE OF CONTENTSDIVISION 23 - HEATING, VENTILATING, AND AIR CON
2、DITIONINGSECTION 23 09 33.00 40ELECTRIC AND ELECTRONIC CONTROL SYSTEM FOR HVAC08/10PART 1 GENERAL1.1 REFERENCES1.2 SYSTEM DESCRIPTION1.2.1 General Requirements1.2.2 System Requirements1.3 QUALITY ASSURANCE1.3.1 Predictive Testing And Inspection Technology Requirements1.3.2 Material and Equipment Qua
3、lifications1.3.3 Alternative Qualifications1.3.4 Service Support1.3.5 Manufacturers Nameplate1.3.6 Modifications of References1.4 SUBMITTALS1.5 STORAGE AND HANDLING1.6 ACCESSIBILITY1.7 ELECTRICAL REQUIREMENTSPART 2 PRODUCTS2.1 CONTROL COMPONENTS2.1.1 Temperature Sensors2.1.2 Humidity Sensors2.1.3 Re
4、ceiver Controllers2.1.4 Receiver Indicators2.1.5 Space Thermostats2.1.5.1 Electrical Control2.1.5.2 Pneumatic Control2.1.5.3 Space Thermostat Accessories2.1.6 Outdoor Reset Thermostat2.1.7 Immersion Thermostats2.1.8 Airstream Thermostats2.1.9 Line-Voltage Thermostats2.1.10 Electrical Low-Limit Duct
5、Thermostat2.1.11 Fire Thermostats2.1.12 Heating/Cooling Valve-Top ThermostatSECTION 23 09 33.00 40 Page 1Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-2.1.13 Room Humidistats2.1.14 Duct Humidistats2.1.15 High-Limit Duct Humidistats2.1.16 Water Temp
6、erature Controllers2.1.17 Building Static-Pressure Transmitter2.1.18 Building Static-Pressure Controller2.1.19 Pressure Transmitter2.1.20 Remote Pressure Transmitter2.1.21 Remote Element Instruments2.1.22 Airflow Switches2.1.23 Pneumatic Relays2.1.24 Switches2.2 THERMOMETERS2.3 PRESSURE GAGES2.4 CON
7、TROL SYSTEM VALVES2.4.1 Hydronic2.4.2 Steam2.5 PNEUMATIC SYSTEMS ACCESSORIES2.5.1 Control and Instrumentation Tubing2.5.2 Valves2.5.2.1 Diaphragm Control and Instrument Valves (DCIV)2.5.2.2 Gage Cocks2.5.3 Air-Pressure Reducing Stations2.5.3.1 Pressure-Reducing Stations2.5.3.2 Pressure Regulators2.5
8、.3.3 Particle Filters2.5.3.4 Combination Filter/Regulators2.5.3.5 Airborne-Oil Filter2.5.3.6 Pressure Relief Valves2.5.4 Pressure Gages2.6 INSTRUMENT AIR SUPPLY2.6.1 Air Supply Source2.6.2 Mechanical Refrigeration-Type Air Dryer2.7 POWER-OPERATED DAMPERS2.7.1 Frame and Blade Assembly2.7.2 Bearings2.
9、7.3 Installation2.8 CONTROL SYSTEM VALVE AND DAMPER OPERATORS2.8.1 Operators2.8.2 Dampers2.8.3 Pneumatic Operators2.8.4 Electric Operators2.9 CENTRAL CONTROL CABINET2.9.1 Cabinet Construction2.9.2 Finish2.9.3 Graphic System Portrayal2.9.4 Instruments and Components2.9.4.1 Receiver-Type Indicator2.9.
10、4.2 Electronic Temperature Indicator2.9.4.3 Electronic Pressure Indicator2.9.4.4 Remote Control Point Adjuster2.9.4.5 Manual Minimum Position Switch2.9.4.6 Remote Temperature Transmitter2.9.4.7 Remote Filter Pressure Transmitter2.9.5 Panel Instrument Tubing2.10 INDIVIDUAL SYSTEM CONTROL PANELS2.11 F
11、ACTORY FINISHINGPART 3 EXECUTIONSECTION 23 09 33.00 40 Page 2Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-3.1 INSTALLATION3.2 CONTROL- AND INSTRUMENT-AIR TUBING INSTALLATION3.2.1 Copper Tubing3.2.2 Plastic Tubing3.3 MECHANICAL REFRIGERATION AIR DR
12、YER INSTALLATION3.4 VIBRATION ISOLATION3.5 FIELD QUALITY CONTROL3.6 OPERATOR TRAINING3.7 SPECIAL TOOLS3.8 OPERATION AND MAINTENANCE- End of Section Table of Contents -SECTION 23 09 33.00 40 Page 3Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-*USACE
13、 / NAVFAC / AFCESA / NASA UFGS-23 09 33.00 40 (August 2010)-Preparing Activity: NASA SupersedingUFGS-23 09 33.00 40 (August 2009)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement with UMRL dated July 2010*SECTION 23 09 33.00 40ELECTRIC AND ELECTRONIC CONTROL SYSTEM FOR HVAC08/10*NOT
14、E: This guide specification covers the requirements for controls and instrumentation for air handling equipment.Coordinate with drawings to include flow schematic and control sequence. Indicate solar compensation requirements in accordance with exposure on drawings.Edit this guide specification for
15、project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable items(s) or insert appropriate information.Remove information and requirements not required in respective project, whether or not brackets are present.Comments and suggestions on this guide sp
16、ecification are welcome and should be directed to the technical proponent of the specification. A listing of technical proponents, including their organization designation and telephone number, is on the Internet.Submit recommended changes to a UFGS as a Criteria Change Request (CCR).*PART 1 GENERAL
17、1.1 REFERENCES*NOTE: This paragraph is used to list the publications cited in the text of the guide specification. The publications are referred to in the text by basic designation only and listed in this paragraph by organization, designation, date, and title.Use the Reference Wizards Check Referen
18、ce feature when you add a RID outside of the Sections SECTION 23 09 33.00 40 Page 4Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Reference Article to automatically place the reference in the Reference Article. Also use the Reference Wizards Check R
19、eference feature to update the issue dates.References not used in the text are automatically deleted from this section of the project specification when you choose to reconcile references in the publish print process.*The publications listed below form a part of this specification to the extent refe
20、renced. The publications are referred to within the text by the basic designation only.AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING ENGINEERS (ASHRAE)ASHRAE 90.1 - IP (2007; Supplement 2008; Addenda r 2009) Energy Standard for Buildings Except Low-Rise Residential BuildingsASHRAE
21、90.1 - SI (2007; Supplement 2008; Errata 2009; Errata 2009; INT 1-3 2009) Energy Standard for Buildings Except Low-Rise Residential BuildingsAMERICAN WELDING SOCIETY (AWS)AWS WHB-2.9 (2004) Welding Handbook; Volume 2, Welding Processes, Part 1ASME INTERNATIONAL (ASME)ASME B16.22 (2001; R 2005) Stand
22、ard for Wrought Copper and Copper Alloy Solder Joint Pressure FittingsASME B40.100 (2005) Pressure Gauges and Gauge AttachmentsASTM INTERNATIONAL (ASTM)ASTM A 666 (2003) Standard Specification for Annealed or Cold-Worked Austenitic Stainless Steel Sheet, Strip, Plate and Flat BarASTM B 280 (2008) St
23、andard Specification for Seamless Copper Tube for Air Conditioning and Refrigeration Field ServiceASTM B 62 (2009) Standard Specification for Composition Bronze or Ounce Metal CastingsASTM D 1693 (2008) Standard Test Method for Environmental Stress-Cracking of Ethylene PlasticsSECTION 23 09 33.00 40
24、 Page 5Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-ISA - INTERNATIONAL SOCIETY OF AUTOMATION (ISA)ISA 7.0.01 (1996) Quality Standard for Instrument AirISA RP60.9 (1981) Piping Guide for Control CentersNATIONAL AERONAUTICS AND SPACE ADMINISTRATION
25、 (NASA)RCBEA GUIDE (2004) NASA Reliability Centered Building and Equipment Acceptance GuideNATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)NEMA DC 3 (2008) Residential Controls - Electrical Wall-Mounted Room ThermostatsNATIONAL FIRE PROTECTION ASSOCIATION (NFPA)NFPA 90A (2009; Errata 09-1) Stand
26、ard for the Installation of Air Conditioning and Ventilating SystemsTHE SOCIETY FOR PROTECTIVE COATINGS (SSPC)SSPC SP 6/NACE No.3 (2007) Commercial Blast CleaningU.S. DEPARTMENT OF DEFENSE (DOD)DOD-G-24508 (1998; Rev A; Am 4) Grease, High Performance, Multipurpose (Metric)MIL-F-18280 (Rev F; Supp 1;
27、 CANC Notice 1) Fittings, Flareless Tube, Fluid ConnectionU.S. GENERAL SERVICES ADMINISTRATION (GSA)FED-STD-595 (Rev C) Colors Used in Government ProcurementFS A-A-2962 (Rev J) Enamel, Alkyd, Gloss, Low VOC Content1.2 SYSTEM DESCRIPTION1.2.1 General Requirements Section 23 00 00 AIR SUPPLY DISTRIBUT
28、ION, VENTILATION, AND EXHAUST SYSTEMS applies to work specified in this section.Section 40 17 30.00 40 WELDING GENERAL PIPING applies to work specified in this section.Section 26 60 13.00 40 LOW -VOLTAGE MOTORS applies to this section. Submit Material, Equipment, and Fixture Lists for control and in
29、strumentation systems including manufacturers style or catalog numbers, specification and drawing reference numbers, warranty information, and fabrication site information.SECTION 23 09 33.00 40 Page 6Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-S
30、ubmit Records of Existing Conditions consisting of the results of survey of work area conditions and features of existing structures and facilities within and adjacent to the jobsite. Commencement of work constitutes acceptance of existing conditions.1.2.2 System RequirementsProvide automatic temper
31、ature control systems that are complete in all details and that include all necessary accessories to maintain conditions indicated or specified.Provide equivalent pneumatic electronic electric/electronic low-voltage electric pneumatic/electronic automatic temperature control systems. As far as pract
32、ical, provide control equipment that is the product of a single automatic control systems manufacturer. Provide automatic control systems components not the product of the control system manufacturer that are approved for use with the control system as indicated.Provide automatically controlled valv
33、es to control environment that are furnished by the automatic control systems manufacturer.Provide automatically controlled dampers, independent of dampers integral with manufactured air-handling units, furnished by the automatic control systems manufacturer. Use a damper manufacturer that is licens
34、ed to display the AMCA seal.Provide dual-duct system mixing boxes and air-mixing valve operators that are furnished by the automatic control systems manufacturer.Submit Fabrication Drawings for control and instrumentation systems consisting of fabrication and assembly details to be performed in the
35、factory.Submit Operating Instructions for control and instrumentation consisting of standard operating procedures including startup, shutdown, and emergency operation.1.3 QUALITY ASSURANCE1.3.1 Predictive Testing And Inspection Technology Requirements*NOTE: The Predictive Testing and Inspection (PT
36、the nameplate of the distributing agent is not acceptable.1.3.6 Modifications of ReferencesIn each of the publications referred to herein, consider the advisory provisions to be mandatory, wherever the words shall, should, will, would, or may appear. Interpret references in these publications to the
37、 “authority having jurisdiction“, or words of similar meaning, to mean the “Contracting Officer“.1.4 SUBMITTALS*NOTE: Review Submittal Description (SD) definitions in Section 01 33 00 SUBMITTAL PROCEDURES and edit the following list to reflect only the submittals required for the project. Keep submi
38、ttals to the SECTION 23 09 33.00 40 Page 8Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-minimum required for adequate quality control.A “G” following a submittal item indicates that the submittal requires Government approval. Some submittals are al
39、ready marked with a “G”. Only delete an existing “G” if the submittal item is not complex and can be reviewed through the Contractors Quality Control system. Only add a “G” if the submittal is sufficiently important or complex in context of the project.For submittals requiring Government approval on
40、 Army projects, use a code of up to three characters within the submittal tags following the “G“ designation to indicate the approving authority. Codes for Army projects using the Resident Management System (RMS) are: “AE“ for Architect-Engineer; “DO“ for District Office (Engineering Division or oth
41、er organization in the District Office); “AO“ for Area Office; “RO“ for Resident Office; and “PO“ for Project Office. Codes following the “G“ typically are not used for Navy, Air Force, and NASA projects.Choose the first bracketed item for Navy, Air Force and NASA projects, or choose the second brac
42、keted item for Army projects.*Government approval is required for submittals with a “G“ designation; submittals not having a “G“ designation are for Contractor Quality Control approval.for information only. When used, a designation following the “G“ designation identifies the office that reviews the
43、 submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:SD-01 Preconstruction SubmittalsSubmit Material, Equipment, and Fixture Lists for control and instrumentation systems in accordance with paragraph entitled, “General Requirements,“ of this se
44、ction.Submit Records of Existing Conditions in accordance with paragraph entitled, “General Requirements,“ of this section.SD-02 Shop DrawingsSubmit Fabrication Drawings for control and instrumentation systems in accordance with paragraph entitled, “System Description,“ of this section.Submit Instal
45、lation Drawings for the following items in accordance with the paragraph entitled, “Installations,“ of this section. Include details of equipment room layout and design on the drawings.SD-03 Product DataSubmit Equipment and performance data for the following items SECTION 23 09 33.00 40 Page 9Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-consisting of use life, system functional flows, safety features, and mechanical automated details. Submit curves indicating tested and certified e