REG NASA-LLIS-0802--2000 Lessons Learned Battery Verification Through Long-Term Simulation.pdf

上传人:Iclinic170 文档编号:1018448 上传时间:2019-03-21 格式:PDF 页数:5 大小:19.83KB
下载 相关 举报
REG NASA-LLIS-0802--2000 Lessons Learned Battery Verification Through Long-Term Simulation.pdf_第1页
第1页 / 共5页
REG NASA-LLIS-0802--2000 Lessons Learned Battery Verification Through Long-Term Simulation.pdf_第2页
第2页 / 共5页
REG NASA-LLIS-0802--2000 Lessons Learned Battery Verification Through Long-Term Simulation.pdf_第3页
第3页 / 共5页
REG NASA-LLIS-0802--2000 Lessons Learned Battery Verification Through Long-Term Simulation.pdf_第4页
第4页 / 共5页
REG NASA-LLIS-0802--2000 Lessons Learned Battery Verification Through Long-Term Simulation.pdf_第5页
第5页 / 共5页
亲,该文档总共5页,全部预览完了,如果喜欢就下载吧!
资源描述

1、Best Practices Entry: Best Practice Info:a71 Committee Approval Date: 2000-04-17a71 Center Point of Contact: MSFCa71 Submitted by: Wil HarkinsSubject: Battery Verification Through Long-Term Simulation Practice: Conduct highly instrumented real-time long term tests and accelerated testing of space fl

2、ight batteries using automated systems that simulate prelaunch, launch, mission, and post mission environments to verify suitability for the mission, to confirm the acceptability of design configurations, to resolve mission anomalies, and to improve reliability.Programs that Certify Usage: This prac

3、tice has been used on Hubble Space Telescope (HST), Advanced x-ray Astrophysics Facility (AXAF), External Tank (ET), Solid Rocket Booster (SRB), Inertial Upper Stage (IUS), and Combined Release and Radiation Effects Satellite (CRRES).Center to Contact for Information: MSFCImplementation Method: This

4、 Lesson Learned is based on Reliability Practice number PT-TE-1434 from NASA Technical Memorandum 4322A, NASA Reliability Preferred Practices for Design and Test.Benefit:Since the operational readiness and future performance of space flight batteries at any point in a mission are strongly dependent

5、upon past power cycles and environments, thoroughly instrumented and analyzed ground testing of space flight batteries identical to flight configurations will ensure Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-predictable performance and high rel

6、iability of flight batteries.Implementation Method:Real-time, long term mission, power cycle simulations of space flight batteries in ground facility test beds provide an excellent indication of expected performance in flight. Complete verification of a full real-time mission is not possible with lo

7、ng-term missions due to the test lead time. Instead of accelerating the test, the test engineers should “lead“ the actual mission by a year or two (as long a lead-time as possible while still being able to use flight designs and configurations). This verification is in addition to qualification step

8、s for the designs. Accelerated testing is not common for low earth orbit (LEO) missions but is used for non-LEO missions.The cells are interconnected in the anticipated flight condition and are housed in a thermally controlled chamber which is purged with an inert gas. Preprogramed, computer control

9、led power supplies and load banks cycle the batteries through the same dormant, power drain, and charging cycles that they would encounter in the space operation. Shading of solar arrays during eclipse periods is simulated by absence of charging current, and charge cycles are simulated during exposu

10、re to the sun. Table 1 lists the principal purposes and features of long-term battery simulations.refer to D descriptionD Table 1. Principal Purposes and Features of Long-Term Battery Simulation All cells are instrumented at various locations for current, voltage, temperature, and pressure. Ambient

11、temperature in the chamber is constantly monitored. Voltage and current values are available in real time through digital readouts. Voltage, current, pressure, and temperature are recorded constantly on strip charts. Data are sampled by computer programs which compute and analyze ongoing performance

12、. Table 2 shows the parameters usually recorded and/or computed for Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-each battery cell from sampled data. Ground testing of batteries and their associated power systems has proven to be a valuable asset

13、for the resolution of in-flight anomalies. Limits testing can be safely simulated on the ground to verify or explore variations in flight performance.refer to D descriptionD Table 2. Recorded and Computed Data Parameters for Each Cell Safety precautions are important in testing of all battery system

14、s because leakage of electrolytes or effluents can be hazardous. Typical precautions and safeguards for nickel-hydrogen (Ni-H2) batteries are shown in Table 3.refer to D descriptionD Table 3. Typical Precautions/Safeguards for Ni-H2Battery Testing Provided by IHSNot for ResaleNo reproduction or netw

15、orking permitted without license from IHS-,-,-An important action that will help to ensure a successful test effort is the preparation of a comprehensive test plan before the test begins. The test plan should describe the overall scope and approach to the test operation, and provide a detailed test

16、sequence including the test set up parameters, data handling requirements, and test procedures. The test setup description should include the cell specifications and method of packaging into the battery configuration, the data acquisition and control procedures, and the thermal control system requir

17、ements. Test procedures should include cell characterization testing procedures (assuming that the cells have already passed through acceptance testing prior to receipt at the test site), launch scenario simulation procedures, mission simulation procedures, and mission capacity test and reconditioni

18、ng procedures if required.Technical Rationale:MSFC has conducted multi-year testing of silver-zinc, nickel-cadmium, and nickel-hydrogen batteries since 1986. Some tests that were started in 1986 are still underway at this writing. Test durations are over eight years and counting. MSFC is conducting

19、8 to 10 tests simultaneously, with up to 400 channels of instrumentation on some tests. To support the Hubble Space Telescope, diode bypass relays on two batteries were opened to simulate an in-flight anomaly. The HST ground tests indicated that strong performance should continue from the HST flight

20、 batteries despite the in-flight anomaly.References:1. Whitt, Thomas and Lorna Jackson: “Battery and Cell Testing at Marshall Space Flight Center,“ (a presentation), NASA/MSFC, EB12, Huntsville, AL, 1988.2. Brewer, Jeffrey, John Pajak, and Lorna Jackson: “Test Plan for AXAF-I Ni-H2Battery Mission Si

21、mulation Testing,“ NASA/MSFC, EB71, Huntsville, AL, March 30, 1994.3. Brewer, Jeffrey, and Thomas Whitt: “HST Ni-H2Flight Spare Battery Test,“ NASA/MSFC, EB12, Huntsville, AL, Huntsville, AL, October 6, 1989.4. Whitt, Thomas, and Charles Hall: “HST Ni-H2Six Battery Mission Simulation Test,“ NASA/MSF

22、C, EB12, Huntsville, AL, November 2, 1989.5. Whitt, Thomas, and Jeffrey Brewer: “Fifth Semi-Annual Report on HST Ni-H2Six Battery and Flight Spare Battery Test,“ NASA/MSFC, Huntsville, AL, August 8, 1993.Impact of Non-Practice: Failure to perform long term mission simulations will result in inadequa

23、te knowledge of long duration performance characteristics and could result in the retention of undesirable battery characteristics or failure modes that would result in mission failure.Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Related Practices: N/AAdditional Info: Approval Info: a71 Approval Date: 2000-04-17a71 Approval Name: Eric Raynora71 Approval Organization: QSa71 Approval Phone Number: 202-358-4738Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-

展开阅读全文
相关资源
猜你喜欢
  • ASTM D7691-2016 red 3678 Standard Test Method for Multielement Analysis of Crude Oils Using Inductively Coupled Plasma Atomic Emission Spectrometry (ICP-AES)《用电感耦合等离子体原子发射光谱法 (ICP-.pdf ASTM D7691-2016 red 3678 Standard Test Method for Multielement Analysis of Crude Oils Using Inductively Coupled Plasma Atomic Emission Spectrometry (ICP-AES)《用电感耦合等离子体原子发射光谱法 (ICP-.pdf
  • ASTM D7693 D7693M-2015 0156 Standard Guide for Application of Heat Weldable Modified Bituminous Waterproofing Membranes Systems for New Concrete Decks《新混凝土桥面使用可热焊改性沥青防水膜系统应用的标准指南》.pdf ASTM D7693 D7693M-2015 0156 Standard Guide for Application of Heat Weldable Modified Bituminous Waterproofing Membranes Systems for New Concrete Decks《新混凝土桥面使用可热焊改性沥青防水膜系统应用的标准指南》.pdf
  • ASTM D7698-2011 2500 Standard Test Method for In-Place Estimation of Density and Water Content of Soil and Aggregate by Correlation with Complex Impedance Method《与复数阻抗法相互关联的土壤和nbsp.pdf ASTM D7698-2011 2500 Standard Test Method for In-Place Estimation of Density and Water Content of Soil and Aggregate by Correlation with Complex Impedance Method《与复数阻抗法相互关联的土壤和nbsp.pdf
  • ASTM D7698-2011a 3750 Standard Test Method for In-Place Estimation of Density and Water Content of Soil and &9 Aggregate by Correlation with Complex Impedance Method《通过复阻抗法系数对土壤和集料.pdf ASTM D7698-2011a 3750 Standard Test Method for In-Place Estimation of Density and Water Content of Soil and &9 Aggregate by Correlation with Complex Impedance Method《通过复阻抗法系数对土壤和集料.pdf
  • ASTM D7699 D7699M-2011 6875 Standard Practice for Minimum Geospatial Data for Abandoned Mine Land Problem Areas Planning Units Keyword Features and Project Sites《废弃矿问题区域 规划区域 土地关键字.pdf ASTM D7699 D7699M-2011 6875 Standard Practice for Minimum Geospatial Data for Abandoned Mine Land Problem Areas Planning Units Keyword Features and Project Sites《废弃矿问题区域 规划区域 土地关键字.pdf
  • ASTM D7700-2012 1944 Standard Guide for Selecting Test Methods for Geomembrane Seams《土工瞙缝选择试验方法的标准指南》.pdf ASTM D7700-2012 1944 Standard Guide for Selecting Test Methods for Geomembrane Seams《土工瞙缝选择试验方法的标准指南》.pdf
  • ASTM D7700-2015 red 3080 Standard Guide for Selecting Test Methods for Geomembrane Seams《选择土工膜接缝试验方法的标准指南》.pdf ASTM D7700-2015 red 3080 Standard Guide for Selecting Test Methods for Geomembrane Seams《选择土工膜接缝试验方法的标准指南》.pdf
  • ASTM D7701-2011 6875 Standard Test Method for Determining the Flow Rate of Water and Suspended Solids from a Geotextile Bag《测定土工织袋水和悬浮物流出量的标准试验方法》.pdf ASTM D7701-2011 6875 Standard Test Method for Determining the Flow Rate of Water and Suspended Solids from a Geotextile Bag《测定土工织袋水和悬浮物流出量的标准试验方法》.pdf
  • ASTM D7702 D7702M-2013a red 6638 Standard Guide for Considerations When Evaluating Direct Shear Results Involving Geosynthetics《评估关于土工合成的直剪结果时考虑的标准指南》.pdf ASTM D7702 D7702M-2013a red 6638 Standard Guide for Considerations When Evaluating Direct Shear Results Involving Geosynthetics《评估关于土工合成的直剪结果时考虑的标准指南》.pdf
  • 相关搜索

    当前位置:首页 > 标准规范 > 国际标准 > 其他

    copyright@ 2008-2019 麦多课文库(www.mydoc123.com)网站版权所有
    备案/许可证编号:苏ICP备17064731号-1