1、Lessons Learned Entry: 1324Lesson Info:a71 Lesson Number: 1324a71 Lesson Date: 2002-10-11a71 Submitting Organization: KSCa71 Submitted by: Kristine RelviniSubject: Potential Payload Test and Checkout System (PTCS) Impact Due to Scheduling Conflicts of Hardware Description of Driving Event: Due to th
2、e scheduling impact, based on the Microgravity Science Glove Box (MSG) payload rack requiring on-line to off-line support by the payload provider, there was a potential that testing in the Payload Test and Checkout System (PTCS) would slip other payload missions from testing in PTCS.Lesson(s) Learne
3、d: If a payload developers (PD) mission slips and the ground support equipment (gse) required to support activities at KSC is promised to another mission for process, the PD would have to supply their own equipment. Recommendation(s): Provide schedule with sufficient padding to mitigate impact on ot
4、her payload PTCS.Develop a common set of equipment that could be used at the payload developers site to mitigate risk prior to delivery and testing at KSC.Evidence of Recurrence Control Effectiveness: N/ADocuments Related to Lesson: Provided by IHSNot for ResaleNo reproduction or networking permitte
5、d without license from IHS-,-,-N/AMission Directorate(s): a71 Space Operationsa71 Exploration SystemsAdditional Key Phrase(s): a71 Ground Equipmenta71 Ground Operationsa71 Human Factorsa71 Risk Management/AssessmentAdditional Info: Approval Info: a71 Approval Date: 2003-03-17a71 Approval Name: Gena Bakera71 Approval Organization: KSCa71 Approval Phone Number: 321-867-4261Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-