API BULL 2TD-2006 Guidelines for Tie-downs on Offshore Production Facilities for Hurricane Season (First Edition)《飓风季节海上生产设施系固装置指南.第1版》.pdf

上传人:吴艺期 文档编号:399428 上传时间:2018-10-21 格式:PDF 页数:14 大小:492.23KB
下载 相关 举报
API BULL 2TD-2006 Guidelines for Tie-downs on Offshore Production Facilities for Hurricane Season (First Edition)《飓风季节海上生产设施系固装置指南.第1版》.pdf_第1页
第1页 / 共14页
API BULL 2TD-2006 Guidelines for Tie-downs on Offshore Production Facilities for Hurricane Season (First Edition)《飓风季节海上生产设施系固装置指南.第1版》.pdf_第2页
第2页 / 共14页
API BULL 2TD-2006 Guidelines for Tie-downs on Offshore Production Facilities for Hurricane Season (First Edition)《飓风季节海上生产设施系固装置指南.第1版》.pdf_第3页
第3页 / 共14页
API BULL 2TD-2006 Guidelines for Tie-downs on Offshore Production Facilities for Hurricane Season (First Edition)《飓风季节海上生产设施系固装置指南.第1版》.pdf_第4页
第4页 / 共14页
API BULL 2TD-2006 Guidelines for Tie-downs on Offshore Production Facilities for Hurricane Season (First Edition)《飓风季节海上生产设施系固装置指南.第1版》.pdf_第5页
第5页 / 共14页
亲,该文档总共14页,到这儿已超出免费预览范围,如果喜欢就下载吧!
资源描述

1、Guidelines for Tie-downs on Offshore Production Facilities for Hurricane SeasonAPI BULLETIN 2TD FIRST EDITION, JUNE 2006Guidelines for Tie-downs on Offshore Production Facilities for Hurricane SeasonUpstream SegmentAPI BULLETIN 2TD FIRST EDITION, JUNE 2006SPECIAL NOTESAPI publications necessarily ad

2、dress problems of a general nature. With respect to particular circumstances, local, state, and federal laws and regulations should be reviewed.Neither API nor any of APIs employees, subcontractors, consultants, committees, or other assignees make any warranty or representation, either express or im

3、plied, with respect to the accuracy, completeness, or usefulness of the information contained herein, or assume any liability or responsibility for any use, or the results of such use, of any information or process disclosed in this publication. Neither API nor any of APIs employees, subcontractors,

4、 con-sultants, or other assignees represent that use of this publication would not infringe upon pri-vately owned rights.API publications may be used by anyone desiring to do so. Every effort has been made by the Institute to assure the accuracy and reliability of the data contained in them; however

5、, the Institute makes no representation, warranty, or guarantee in connection with this publication and hereby expressly disclaims any liability or responsibility for loss or damage resulting from its use or for the violation of any authorities having jurisdiction with which this publi-cation may co

6、nflict.API publications are published to facilitate the broad availability of proven, sound engineer-ing and operating practices. These publications are not intended to obviate the need for applying sound engineering judgment regarding when and where these publications should be utilized. The formul

7、ation and publication of API publications is not intended in any way to inhibit anyone from using any other practices.Any manufacturer marking equipment or materials in conformance with the marking requirements of an API standard is solely responsible for complying with all the applicable requiremen

8、ts of that standard. API does not represent, warrant, or guarantee that such prod-ucts do in fact conform to the applicable API standard.All rights reserved. No part of this work may be reproduced, stored in a retrieval system, or transmitted by any means, electronic, mechanical, photocopying, recor

9、ding, or otherwise, without prior written permission from the publisher. Contact the Publisher, API Publishing Services, 1220 L Street, N.W., Washington, D.C. 20005.Copyright 2006 American Petroleum InstituteFOREWORDThis bulletin is under the jurisdiction of the API Subcommittee on Standardization o

10、f Off-shore Structures. The purpose of this bulletin is to raise the awareness of the need to evaluate the tie-downs in use on offshore production facilities for drilling rigs, permanent equipment, and facilities such as quarters, helidecks, etc. The information contained herein is presented as reco

11、m-mendations that a platform owner/operator or drilling rig owner/operator may choose to undertake in the short-term (i.e., the 2006 hurricane season) and intermediate term (i.e., prior to the 2007 hurricane season) in an effort to improve tie-down performance during hurri-canes.Long-term plans incl

12、ude evaluating the need for detailed design requirements for rig and permanent equipment on floating and fixed offshore platforms and, if needed, how to best include that information in the suite of API standards.Nothing contained in any API publication is to be construed as granting any right, by i

13、mpli-cation or otherwise, for the manufacture, sale, or use of any method, apparatus, or product covered by letters patent. Neither should anything contained in the publication be construed as insuring anyone against liability for infringement of letters patent.This document was produced under API s

14、tandardization procedures that ensure appropriate notification and participation in the developmental process and is designated as an API stan-dard. Questions concerning the interpretation of the content of this publication or comments and questions concerning the procedures under which this publica

15、tion was developed should be directed in writing to the Director of Standards, American Petroleum Institute, 1220 L Street, N.W., Washington, D.C. 20005. Requests for permission to reproduce or translate all or any part of the material published herein should also be addressed to the Director.Classi

16、fied areas may vary depending on the location, conditions, equipment, and substances involved in any given situation. Users of this bulletin should consult with the appropriate authorities having jurisdiction.Users of this bulletin should not rely exclusively on the information contained in this doc

17、u-ment. Sound business, scientific, engineering, and safety judgment should be used in employing the information contained herein.Where applicable, authorities having jurisdiction should be consulted. Work sites and equipment operations may differ. Users are solely responsible for assessing their sp

18、ecific equipment and premises in determining the appropriateness of applying the instructions. At all times users should employ sound business, scientific, engineering, and judgment safety when using this bulletin.API is not undertaking to meet the duties of employers, manufacturers, or suppliers to

19、 warn and properly train and equip their employees, and others exposed, concerning health and safety risks and precautions, nor undertaking their obligations to comply with authorities having jurisdiction. Generally, API standards are reviewed and revised, reaffirmed, or withdrawn at least every fiv

20、e years. A one-time extension of up to two years may be added to this review cycle. Status of the publication can be ascertained from the API Standards Department, telephone (202) 682-8000. A catalog of API publications and materials is published annually and updated regularly by API, 1220 L Street,

21、 N.W., Washington, D.C. 20005, www.api.org/cat.Suggested revisions are invited and should be submitted to the Standards Department, API, 1220 L Street, NW, Washington, DC 20005, standardsapi.org.iiiCONTENTSPage1 DRILLING AND WORKOVER DRILLING UNITS. . . . . . . . . . . . . . . . . . . . . . . . . .

22、.11.1 Background . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .11.2 Philosophy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .11.3 Short-Term Recommendations . . . . . . . .

23、 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .11.4 Intermediate-Term Recommendations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .22 PERMANENT EQUIPMENT AND FACILITIES . . . . . . . . . . . . . . . . . . . . . . . . . . . . .22.1 Background . . . . . . . . . .

24、 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .22.2 Philosophy/Design Conditions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .22.3 Short-Term-Recommendations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

25、 . . . . . . .32.4 Intermediate-Term Recommendations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3v1Guidelines for Tie-downs on Offshore Production Facilities for Hurricane Season1 Drilling and Workover Drilling Units 1.1 BACKGROUND The oil and gas industry has experienced rig

26、 failures and movement of rig components during recent hurricanes in the Gulf of Mexico. Some, if not all, of the failures are attributable to the tie-down components. Occurrences on both fixed and floating plat-forms have resulted in significant platform damage as well as lost and/or deferred produ

27、ction. Recent experience shows that enhancements to current industry practice can improve tie-down performance during hurricanes. 1.2 PHILOSOPHY1.2.1 ApplicabilityThis document addresses situations where failure of a drilling or workover rig would result in significant damage to the platform or adja

28、cent infrastructure. Generally, this would include any facility designated as having a high or medium consequence of fail-ure as defined by API RP2A. In other situations, a risk-based operational decision process should be followed. Situations that might allow deviation from the recommendations belo

29、w include drilling operations in the non-hurricane season or the use of light-weight workover masts on shallow water platforms. 1.2.2 Design ConditionsDrilling rig tie-downs to the platform and between drilling components are critical structural components and should have the same, or higher, level

30、of design, material traceability, quality assurance, maintenance, and documentation as other critical struc-tural components.Primary rig and substructure tie-downs should be designed or assessed for location-specific loading conditions (environmental and dynamic) consistent with those utilized in th

31、e facility structural design and should be approved by an engineer experienced and qualified in offshore structural engineering. For the same design environment, wind gust and height factors appropriate for the derrick and substructure may be higher than those used for designing the topside as a who

32、le, and the short-term extremes will be much higher than the average loadings used in combination with wave forces for jacket or mooring design. Guidance in wind codes supports the use of 5-to 15-second gust factors for the design of such components. Dynamic accelerations and tilting of the platform

33、 topside should also be considered, again at the extreme (not RMS) level. Rigid body (quasi-static) analysis of the rig packages themselves may be used as a first approximation. 1.3 SHORT-TERM RECOMMENDATIONS The following items should be considered for implementation as appropriate by the platform

34、operator and/or rig owner in the short-term timeframe: Visually inspect all tie-downs to confirm that they are in good condition and are constructed per the design drawings. Verify that all tie-downs can be properly installed and that no obstructions exist that might prevent installation (e.g. stiff

35、en-ers on plate girders). For bolted tie-downs: - Verify by visual inspection that the bolts are in good physical condition. - Verify that bolts meet the required material specifications and the specifications are suitable for this application. Note: ASTM 325 or 490 high strength bolts are not recom

36、mended, since retorquing of these bolts is not permitted per AISC specifica-tions.- Verify that the number of bolt torquing cycles does not exceed the design allowable. - Verify required bolt torque is defined and required equipment/tools are available to achieve the required torque. - New bolts sho

37、uld be installed if the above items cannot be verified. For mechanical/hydraulic tie-downs:- Verify that the tie-down system is in good working condition.- Verify that operating personnel are familiar with the operating procedures of the equipment. 2 API BULLETIN 2TD- Verify that equipment is fail s

38、afe (tie-down force will be maintained in the event of equipment failure). For welded tie-downs: - Verify that plans, weld size, welding procedures, and inspection procedures are adequate. Verify that welded components of tie-downs have been properly inspected. Determine if there is a preferred well

39、 position for stowing the rig. If so, verify that this is clearly defined in the platform hur-ricane evacuation procedures. Verify that proper tie-down procedures are part of the platform evacuation procedures and that proper tie-down is verified in writing by the Offshore Installation Manager (OIM)

40、 or his designate prior to evacuation. Verify that other procedures such as setting down of all drill pipe, handling of setback load, emptying of tanks, etc. are clearly defined in the evacuation procedures and have been considered in engineering of the tie-down procedures. Verify that all required

41、tie-down tools, equipment, and labor including all required spares will be available as required prior to evacuation. Any new components should be prefabricated for quickness and ease of connection. Verify that hurricane evacuation procedures allow time for proper tie-down prior to evacuation. Where

42、 feasible, an engineered, welded stop should be installed at the end of skid beams to prevent skid packages from skid-ding off the end of the beams. Welds should be of structural quality and properly inspected. Stops should be sized to with-stand shear associated with wind and platform tilt (on floa

43、ting structures) in combination with a lower bound friction assumption. Verify that all rig packages are properly tied down based on risk appropriate environmental and dynamic loads. After each hurricane evacuation, the tie-downs should be visually inspected prior to returning the rig to normal serv

44、ice. Any damage found should be evaluated to determine if any design or procedural modifications are required. Inspection results should be documented. Damage that is repeatedly discovered indicates a need for design and/or procedure change, and should result in more frequent inspections until such

45、inspections indicate that the cause(s) of the fault(s) has been resolved. The above recommendations are considered the minimum required, and any additional inspections or modifications required to prevent movement or failure of rig package tie-downs during design storm conditions should be completed

46、 as soon as possible. 1.4 INTERMEDIATE-TERM RECOMMENDATIONSThe following items should be considered for implementation by the platform operator and/or rig owner in the intermediate-term timeframe: Review design calculations of all tie-downs with updated site-specific environmental and dynamic loads

47、and document results. Analysis and results should be approved by an engineer experienced and qualified in offshore structures. Clamps should be assessed for all appropriate well positions. Special care should be given to calculations that show either no pre-dicted uplift or only a small uplift when

48、compared to the gravity reaction. In such cases, there may effectively be no reserve against slightly higher wind forces. Review fabrication and material records to assure that all tie-down systems are properly documented. Consider replacement of tie-downs if proper documentation is not available. O

49、therwise, make an assessment based on conservative assumptions of material and weld properties. Review derrick or mast and substructure design based on site-specific environmental and dynamic loads and document results. Analysis and results should be approved by an engineer experienced and qualified in this area. 2 Permanent Equipment and Facilities2.1 BACKGROUNDPermanent equipment, quarters, and helidecks also suffered severe damage due to tie-down failure during the recent Gulf of Mex-ico hurricanes. This resulted in a significant amount of damage as well as lo

展开阅读全文
相关资源
  • API SALES OF NGL & LRG-2018 2016 Sales of Natural Gas Liquids and Liquefied Refinery Gas.pdfAPI SALES OF NGL & LRG-2018 2016 Sales of Natural Gas Liquids and Liquefied Refinery Gas.pdf
  • API MPMS 9 4-2018 Manual of Petroleum Measurement Standards Chapter 9 4-Continuous Density Measurement Under Dynamic (Flowing) Conditions (FIRST EDITION).pdfAPI MPMS 9 4-2018 Manual of Petroleum Measurement Standards Chapter 9 4-Continuous Density Measurement Under Dynamic (Flowing) Conditions (FIRST EDITION).pdf
  • API MPMS 9 3-2012 Manual of Petroleum Measurement Standards Chapter 9 3 Standard Test Method for Density Relative Density and API Gravity of Crude Petroleum and.pdfAPI MPMS 9 3-2012 Manual of Petroleum Measurement Standards Chapter 9 3 Standard Test Method for Density Relative Density and API Gravity of Crude Petroleum and.pdf
  • API MPMS 9 2-2012 Manual of Petroleum Measurement Standards Chapter 9 2 Standard Test Method for Density or Relative Density of Light Hydrocarbons by Pressure H.pdfAPI MPMS 9 2-2012 Manual of Petroleum Measurement Standards Chapter 9 2 Standard Test Method for Density or Relative Density of Light Hydrocarbons by Pressure H.pdf
  • API MPMS 9 1-2012 Manual of Petroleum Measurement Standards Chapter 9 1 Standard Test Method for Density Relative Density or API Gravity of Crude Petroleum and .pdfAPI MPMS 9 1-2012 Manual of Petroleum Measurement Standards Chapter 9 1 Standard Test Method for Density Relative Density or API Gravity of Crude Petroleum and .pdf
  • API MPMS 8 5-2015 Manual of Petroleum Measurement Standards Chapter 8 5 Standard Practice for Manual Piston Cylinder Sampling for Volatile Crude Oils Condensate.pdfAPI MPMS 8 5-2015 Manual of Petroleum Measurement Standards Chapter 8 5 Standard Practice for Manual Piston Cylinder Sampling for Volatile Crude Oils Condensate.pdf
  • API MPMS 8 5 SPANISH-2015 Manual of Petroleum Measurement Standards Chapter 8 5 - Standard Practice for Manual Piston Cylinder Sampling for Volatile Crude Oils .pdfAPI MPMS 8 5 SPANISH-2015 Manual of Petroleum Measurement Standards Chapter 8 5 - Standard Practice for Manual Piston Cylinder Sampling for Volatile Crude Oils .pdf
  • API MPMS 8 4-2017 Manual of Petroleum Measurement Standards Chapter 8 4 Standard Practice for Sampling and Handling of Fuels for Volatility Measurement (FOURTH .pdfAPI MPMS 8 4-2017 Manual of Petroleum Measurement Standards Chapter 8 4 Standard Practice for Sampling and Handling of Fuels for Volatility Measurement (FOURTH .pdf
  • API MPMS 8 4-2014 Manual of Petroleum Measurement Standards Chapter 8 4 Standard Practice for Sampling and Handling of Fuels for Volatility Measurement (THIRD E.pdfAPI MPMS 8 4-2014 Manual of Petroleum Measurement Standards Chapter 8 4 Standard Practice for Sampling and Handling of Fuels for Volatility Measurement (THIRD E.pdf
  • API MPMS 8 3-1995 Manual of Petroleum Measurement Standards Chapter 8 - Sampling Section 3 - Standard Practice for Mixing and Handling of Liquid Samples of Petr.pdfAPI MPMS 8 3-1995 Manual of Petroleum Measurement Standards Chapter 8 - Sampling Section 3 - Standard Practice for Mixing and Handling of Liquid Samples of Petr.pdf
  • 猜你喜欢
    相关搜索

    当前位置:首页 > 标准规范 > 国际标准 > API

    copyright@ 2008-2019 麦多课文库(www.mydoc123.com)网站版权所有
    备案/许可证编号:苏ICP备17064731号-1