1、Lessons Learned Entry: 1374Lesson Info:a71 Lesson Number: 1374a71 Lesson Date: 2002-08-29a71 Submitting Organization: JSCa71 Submitted by: Ronald A. MontagueSubject: Accurate Drawings of Facility Systems as a Prerequisite to Project Implementation Abstract: The companys failure to implement and enfo
2、rce their company safety program, as defined in their Safety drawings are not promptly updated, plus one-line (red-line) drawings do not always contain all electrical circuits.4. The existing facility drawings were not provided to the contractor.Find B: Project submittals from the contractor to the
3、government are a requirement. NASA needs to ensure the required submittals have been delivered, reviewed, and accepted before allowing the work to proceed. The following evidence supports this finding: 1. The contractor failed to develop and submit a point-to-point schematic to NASA prior to “demoli
4、tion” of existing wiring, as required by the construction drawings.2. NASA did not confirm delivery of the point-to-point schematic required by the construction drawings.3. The contractor had no formal or organized process to plan or review its days work.Lesson(s) Learned: All drawings available for
5、 the project should be provided to the work team and, if the drawings have not been verified as complete and accurate, NASA should make the work team aware of this.Recommendation(s): 1. NASA should require A/E firms to develop detailed circuit schematics as part of construction drawings.2. 3. NASA s
6、hould ensure that facility drawings are accurate and are provided to construction contractors when appropriate.4. Construction of Facilities (CoF) project budgets should include fenced funding for redlining and updating existing facility drawings associated with the construction.5. NASA should ensur
7、e that contract deliverables are provided by the contractor at the appropriate time and not allow work to continue unless these are provided.6. NASA should require that safety and job hazard analyses be performed and not allow work to start until these are submitted and reviewed.7. NASA should requi
8、re Pre-Project Safety Reviews prior to construction start. This should be more comprehensive than pre-construction meetings with a format analogous to an Operational Readiness Inspection (ORI), Test Readiness Review (TRR), etc.8. NASA should require that construction contractors conduct daily planni
9、ng meetings to review work to be performed during the continuous duty time or shift.Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Evidence of Recurrence Control Effectiveness: PendingDocuments Related to Lesson: JPG 1700.1, “JSC Safety and Health H
10、andbook,“ Chapter 8.1, Safety and Health Requirements for Designing, Constructing, and Operating FacilitiesMission Directorate(s): a71 Exploration Systemsa71 Sciencea71 Space Operationsa71 Aeronautics ResearchAdditional Key Phrase(s): a71 Configuration Managementa71 Energya71 Facilitiesa71 Independe
11、nt Verification and Validationa71 Industrial Operationsa71 Policy & Planninga71 Procurement Small Business & Industrial Relationsa71 Program and Project Managementa71 Risk Management/Assessmenta71 Safety & Mission Assurancea71 Test & VerificationAdditional Info: Approval Info: a71 Approval Date: 2004-01-08a71 Approval Name: Ron Montaguea71 Approval Organization: JSCa71 Approval Phone Number: 281-483-8576Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-