1、*USACE / NAVFAC / AFCESA / NASA UFGS-02 55 00 (February 2010)-Preparing Activity: USACE SupersedingUFGS-02 55 00 (April 2006)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement with UMRL dated April 2010*SECTION TABLE OF CONTENTSDIVISION 02 - EXISTING CONDITIONSSECTION 02 55 00SOLIDIF
2、ICATION/STABILIZATION (S/S) OF CONTAMINATED MATERIAL02/10PART 1 GENERAL1.1 UNIT PRICES1.2 REFERENCES1.3 SYSTEM DESCRIPTION1.3.1 Work Plan1.3.2 Other Submittal Requirements1.3.3 Performance Requirements1.3.3.1 Disposal of Treated Material1.3.3.2 Emission Controls1.3.3.3 Noise Control1.4 SUBMITTALS1.5
3、 QUALIFICATIONS1.5.1 Contractor Experience1.5.2 Key Personnel1.6 PROJECT/SITE CONDITIONSPART 2 PRODUCTS2.1 MATERIALS2.1.1 Water2.1.2 Reagents2.1.3 Mix Design2.2 EQUIPMENT2.2.1 Mixing Equipment2.2.2 Reagent Feed Units2.2.3 Accuracy of Measurement EquipmentPART 3 EXECUTION3.1 STOCKPILES3.2 OPERATION3.
4、2.1 Dissimilar Materials3.2.2 Oversize Material3.3 FIELD DEMONSTRATION3.3.1 Full-Scale Processing EquipmentSECTION 02 55 00 Page 1Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-3.3.2 Sampling Locations3.3.3 Testing3.3.4 Volume Increase3.3.5 Field De
5、monstration Test Results3.4 QUALITY CONTROL PROCEDURES3.4.1 Batch Proportions3.4.2 Segregation3.4.3 Quality Control Tests3.4.4 Retesting and Reprocessing3.4.4.1 Retesting3.4.4.2 Reprocessing3.4.5 Adjustments to Mix Design3.4.6 Quality Assurance Testing- End of Section Table of Contents -SECTION 02 5
6、5 00 Page 2Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-*USACE / NAVFAC / AFCESA / NASA UFGS-02 55 00 (February 2010)-Preparing Activity: USACE SupersedingUFGS-02 55 00 (April 2006)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement
7、 with UMRL dated April 2010*SECTION 02 55 00SOLIDIFICATION/STABILIZATION (S/S) OF CONTAMINATED MATERIAL02/10*NOTE: This guide specification covers the requirements for solidification/stabilization (S/S) of contaminated materials.Edit this guide specification for project specific requirements by addi
8、ng, deleting, or revising text. For bracketed items, choose applicable items(s) or insert appropriate information.Remove information and requirements not required in respective project, whether or not brackets are present.Comments and suggestions on this guide specification are welcome and should be
9、 directed to the technical proponent of the specification. A listing of technical proponents, including their organization designation and telephone number, is on the Internet.Recommended changes to a UFGS should be submitted as a Criteria Change Request (CCR).*PART 1 GENERAL1.1 UNIT PRICES*NOTE: Th
10、is paragraph should be deleted if the work is in one lump sum contract or there is a separate Measurement and Payment Section. Batch processing is likely to use weight as the method of measurement. In situ processes are more likely to use volume as the method of measurement.*a. Payment will be based
11、 on the Contract unit price schedule for each in situ metric ton ton cubic meter cubic yard of contaminated material entering the S/S process. This unit price shall include the cost for materials, equipment, waste feed processing, S/S operations, SECTION 02 55 00 Page 3Provided by IHSNot for ResaleN
12、o reproduction or networking permitted without license from IHS-,-,-stockpiles, testing, and all other work associated with the S/S process.b. No payment will be made for materials or labor required to reprocess any processed material not meeting the physical and chemical testing requirements outlin
13、ed in this section. Reprocessed material shall be deducted from the daily production rate.1.2 REFERENCES*NOTE: This paragraph is used to list the publications cited in the text of the guide specification. The publications are referred to in the text by basic designation only and listed in this parag
14、raph by organization, designation, date, and title.Use the Reference Wizards Check Reference feature when you add a RID outside of the Sections Reference Article to automatically place the reference in the Reference Article. Also use the Reference Wizards Check Reference feature to update the issue
15、dates.References not used in the text will automatically be deleted from this section of the project specification when you choose to reconcile references in the publish print process.*The publications listed below form a part of this specification to the extent referenced. The publications are refe
16、rred to within the text by the basic designation only.ASTM INTERNATIONAL (ASTM)ASTM D 1556 (2007) Density and Unit Weight of Soil in Place by the Sand-Cone MethodASTM D 1633 (2000; R 2007) Compressive Strength of Molded Soil-Cement CylindersASTM D 4832 (2002) Preparation and Testing of Controlled Lo
17、w Strength Material (CLSM) Test CylindersASTM D 5084 (2003) Measurement of Hydraulic Conductivity of Saturated Porous Materials Using a Flexible Wall PermeameterU.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)EPA SW-846.3-3 (1999, Third Edition, Update III-A) Test Methods for Evaluating Solid Waste: Physi
18、cal/Chemical MethodsU.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)40 CFR 268 Land Disposal RestrictionsSECTION 02 55 00 Page 4Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-1.3 SYSTEM DESCRIPTION*NOTE: The Contractor is sometimes required
19、to provide treatability study test results prior to performing work at the site. Treatability study test results should include the proposed reagents and mix ratios to be used during full scale treatment. The test results submitted should verify that the mix design proposed meets the post-treatment
20、criteria listed in Table 1. Consideration should also be given to the need to monitor off-gas and dust emissions during the treatability study. Detailed information on testing requirements, test methods, detection limits, and off-gas and dust emission testing requirements should be presented in the
21、appropriate section and referenced here.At projects where strict testing protocols are required to adequately determine the effectiveness of the process being tested, the Contractor should be required to provide a “Treatability Study Work Plan“ for approval prior to performing the treatability study
22、.Prior to performing any treatability study, the untreated samples should be tested to verify that they contain the contaminants of concern at high enough concentrations and these contaminants leach at levels which are representative of the materials found on-site. Additional testing may be needed t
23、o verify that physical properties of the samples are also representative of site conditions.The last two sentences of this paragraph should be omitted if a specific method of treatment (in situ or ex-situ) is desired.*Use an in situ pug mill ex-situ _ S/S system that provides a safe, reliable method
24、 to treat contaminated material so that the treated material conforms to paragraph PERFORMANCE REQUIREMENTS. A system or procedure, other than described in this section, may be used if the approved SUBMITTALS demonstrate equivalent capabilities. Such approval does not relieve the Contractor of respo
25、nsibility for meeting specified requirements for safety, reliability, and performance.1.3.1 Work PlanSubmit an S/S Work Plan within 60 _ days after notice to proceed. No S/S of contaminated material shall be performed until the work plan is approved. A period of 30 _ days shall be allowed in the sch
26、edule for Government review and approval of the work plan. The work plan shall address the technical requirements listed in this section and shall include, but is not limited to the following:a. Contractor Experience: Information to demonstrate that the S/S SECTION 02 55 00 Page 5Provided by IHSNot
27、for ResaleNo reproduction or networking permitted without license from IHS-,-,-Contractor meets the qualification requirements outlined in Paragraph QUALIFICATIONS.b. Mix Design: The proposed mix design and method of mixing to be used in treating the contaminated material. The proposed source of wat
28、er to be used for the S/S process shall also be identified.c. Equipment: Specifications for the proposed homogenization and mixing equipment, batching equipment, and process control instrumentation. Process flow diagrams, mixing times, and processing rates shall be included. Anticipated pretreatment
29、 of the contaminated material shall be identified.d. Drawings: Drawings indicating dimensions and layout of the S/S system on the site. Drawings shall be to scale.e. Emissions: Air emissions, dust, and noise from the system shall be identified and estimated. Control systems required to maintain comp
30、liance with local, state, and federal regulations shall be described as appropriate. Air emissions, dust, and noise testing protocol to be performed during the test run and full scale operations shall also be described.f. Quality Control: A quality control plan which addresses control and documentat
31、ion of batch proportions, mixing time, mixing speed, sample collection, sample curing, and post-treatment testing.g. Demobilization: A post-treatment cleanup and sampling plan for the treatment area.h. Stockpile Design: A proposed stockpile design which meets the criteria outlined in this section.1.
32、3.2 Other Submittal RequirementsThe following shall also be sumitted:a. Resumes of key personnel at least 5 _ working days prior to the personnel assuming duties on site.b. Daily batch proportion and mixing quality control data.c. Results of post-treatment tests performed.d. The field demonstration
33、report including pre-treatment and post-treatment test results; it shall document other relevant field demonstration data including but not limited to: batch proportions, mixing time, and mixing speed. Off-gas, dust, and noise test results shall also be included.e. Reagent composition, certificates
34、of analysis, and MSDS documentation. A confidentiality agreement may be requested if proprietary reagents are being used.1.3.3 Performance Requirements*NOTE: The post-treatment testing criteria listed in Table 1 are only examples. Chemical and physical SECTION 02 55 00 Page 6Provided by IHSNot for R
35、esaleNo reproduction or networking permitted without license from IHS-,-,-test criteria should be determined on a site specific basis. Post-treatment criteria may be based on federal regulatory criteria, site specific risk analyses, or site specific criteria based on state and local regulations.*The
36、 Toxicity Characteristic Leaching Procedure as specified in EPA SW-846.3-3 _ shall be performed on representative samples of treated material. The extract shall meet the chemical post-treatment testing criteria listed in Table 1. Chemical testing required in this section shall be conducted in accord
37、ance with Section 01 35 45.00 10 CHEMICAL DATA QUALITY CONTROL _. The treated material shall also meet the physical testing criteria listed in Table 1. The tests listed in Table 1 shall be performed on samples that have been cured for 3 _ days.Table 1. POST-TREATMENT TEST CRITERIATEST TEST VALUE_Ars
38、enic _ mg/LCadmium _ mg/LChromium (Total) _ mg/LLead _ mg/LMin. UnconfinedCompressive Strength ASTM D 1633 _ kPaMax. Permeability ASTM D 5084 _ cm/sMaximum Volume Increase _ percent.1.3.3.1 Disposal of Treated Material*NOTE: Reference the appropriate section which describes requirements for disposal
39、 of treated material, including manifests for off-site disposal. Identify onsite disposal locations on the drawings.*The treated material, upon meeting the physical and chemical testing criteria, shall be disposed of as required by Section 02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS
40、_.1.3.3.2 Emission Controls*NOTE: Site specific requirements should be added to this paragraph.*The S/S system shall include control apparatus necessary to meet local, SECTION 02 55 00 Page 7Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-state, and/
41、or federal regulations for air emissions and dust.1.3.3.3 Noise Control*NOTE: Different day and night noise restrictions may be appropriate.*The S/S system shall meet state and local noise pollution control regulations not exceed _ decibels at any site boundary.1.4 SUBMITTALS*NOTE: Review submittal
42、description (SD) definitions in Section 01 33 00 SUBMITTAL PROCEDURES and edit the following list to reflect only the submittals required for the project. Submittals should be kept to the minimum required for adequate quality control.A “G” following a submittal item indicates that the submittal requires Government approval. Some submittals are already marked with a “G”. Only delete an existing “G” if the submittal item is not complex and can be reviewed through the Contractors Quality Control system. Only add a “G” if the submittal is sufficiently important or complex in context of the proje