1、Lessons Learned Entry: 1032Lesson Info:a71 Lesson Number: 1032a71 Lesson Date: 2001-07-20a71 Submitting Organization: DFRCa71 Submitted by: Roy TryonSubject: Construction Site Safety, Sheet Metal Panels Materials Handling Description of Driving Event: DFRC B4823Incident Report: An iron worker, worki
2、ng alone, was rolling up large sheets (4x10) of galvanized sheet metal that had been laid down on the slab in front of an addition to a flightline building. While rolling one of the sheets into the wind, a gust of wind picked up one end of the sheet metal causing it to curl up rapidly towards the wo
3、rker. A corner of the sheet slashed backward, cutting deeply into the workers left forearm.Medical personnel arrived quickly. The wound was treated and bandaged at the site and the worker was transported to the hospital for stitches. The accident occurred on a Friday, and the ironworker recuperated
4、over the weekend. He returned to work on Monday morning. Just prior to the accident, the project inspector advised the ironworker to roll up the metal sheets in the direction of the wind.Lesson(s) Learned: 1. Do not handle large materials on open exposed flightline on windy days.2. Even routine mate
5、rial handling operations can be hazardous when that activity is not well planned.Recommendation(s): 1. Materials with large surface areas should be handled INSIDE the shelter of the building-not outside in the wind.2. When working with large material items, provide a second person to help secure and
6、 control the materialProvided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-3. Include hazard awareness and mitigation measures in the daily safety meeting prior to handling large items. When a NASA safety officer (the project inspector) provides safety adv
7、ice, listen and follow that advice.Evidence of Recurrence Control Effectiveness: N/ADocuments Related to Lesson: N/AMission Directorate(s): a71 Exploration Systemsa71 Aeronautics ResearchAdditional Key Phrase(s): a71 Environmenta71 FacilitiesAdditional Info: Approval Info: a71 Approval Date: 2001-12-05a71 Approval Name: John Marcruma71 Approval Organization: DFRCa71 Approval Phone Number: 661-276-2825Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-